The licensee, certificate holder, and applicant for a CoC shall establish and execute a program for inspection of activities affecting quality by or for the organization performing the activity, to verify conformance with the documented instructions, procedures, and drawings for accomplishing the activity. The inspection must be performed by individuals other than those who performed the activity being inspected. Examination, measurements, or tests of material or products processed must be performed for each work operation where necessary to assure quality. If direct inspection of processed material or products is not carried out, indirect control by monitoring processing methods, equipment, and personnel must be provided. Both inspection and process monitoring must be provided when quality control is inadequate without both. If mandatory inspection hold points, which require witnessing or inspecting by the licensee's designated representative and beyond which work should not proceed without the consent of its designated representative, are required, the specific hold points must be indicated in appropriate documents.
authority: Atomic Energy Act of 1954, secs. 53, 57, 62, 63, 81, 161, 182, 183, 223, 234, 1701 (
42 U.S.C. 2073,
2077,
2092,
2093,
2111,
2201,
2232,
2233,
2273,
2282,
2297f; Energy Reorganization Act of 1974, secs. 201, 202, 206, 211 (
42 U.S.C. 5841,
5842,
5846,
5851; Nuclear Waste Policy Act of 1982, sec. 180 (
42 U.S.C. 10175);
44 U.S.C. 3504 note
source: 60 FR 50264, Sept. 28, 1995, unless otherwise noted.
cite as: 10 CFR 71.121