Regulations last checked for updates: Oct 17, 2024

Title 32 - National Defense last revised: Oct 15, 2024
§ 37.565 - May I use a hybrid instrument that provides fixed support for only a portion of a project?

Yes, for a research project that is to be carried out by a number of participants, you may award a TIA that provides for some participants to perform under fixed-support arrangements and others to perform under expenditure-based arrangements. This approach may be useful, for example, if a commercial firm that is a participant will not accept an agreement with all of the post-award requirements of an expenditure-based award. Before using a fixed-support arrangement for that firm's portion of the project, you must judge that it meets the criteria in § 37.305.

authority: 5 U.S.C. 301 and 10 U.S.C. 113.
source: 68 FR 47160, Aug. 7, 2003, unless otherwise noted.
cite as: 32 CFR 37.565