§ 75.601 - Approval of the construction.

(a) The Secretary approves a direct grantee construction project—

(1) When the initial grant application is approved; or

(2) After the grant has been awarded.

(b) A grantee may not advertise or place the construction project on the market for bidding until after the Secretary has approved the project.

[89 FR 70331, Aug. 29, 2024]
authority: 20 U.S.C. 1221e-3 and 3474, unless otherwise noted
source: 45 FR 22497, Apr. 3, 1980, unless otherwise noted. Redesignated at 45 FR 77368, Nov. 21, 1980.
cite as: 34 CFR 75.601