(a) The provisions of this subpart apply to each municipal solid waste landfill that commenced construction, reconstruction, or modification on or after May 30, 1991, but before July 18, 2014.
(b) The following authorities shall be retained by the Administrator and not transferred to the State: § 60.754(a)(5).
(c) Activities required by or conducted pursuant to a CERCLA, RCRA, or State remedial action are not considered construction, reconstruction, or modification for purposes of this subpart.
(d) An affected municipal solid waste landfill must continue to comply with this subpart until it:
(1) Becomes subject to the more stringent requirements in an approved and effective state or federal plan that implements subpart Cf of this part, or
(2) Modifies or reconstructs after July 17, 2014, and thus becomes subject to subpart XXX of this part.
[61 FR 9919, Mar. 12, 1996, as amended at 63 FR 32750, June 16, 1998; 85 FR 17260, Mar. 26, 2020]