Regulations last checked for updates: Oct 18, 2024

Title 43 - Public Lands: Interior last revised: Sep 06, 2024
§ 2885.14 - What happens if I need a right-of-way wider than 50 feet plus the ground occupied by the pipeline and related facilities?

(a) You may apply to BLM at any time for a right-of-way wider than 50 feet plus the ground occupied by the pipeline and related facilities. In your application you must show that the wider right-of-way is necessary to:

(1) Properly operate and maintain the pipeline after you have constructed it;

(2) Protect the environment; or

(3) Provide for public safety.

(b) BLM will notify you in writing of its finding(s) and its decision on your application for a wider right-of-way. If the decision is adverse to you, you may appeal it under § 2881.10 of this part.

authority: 30 U.S.C. 185 and 189, and 43 U.S.C. 1732(b), 1733, and 1740
source: 70 FR 21078, Apr. 22, 2005, unless otherwise noted.
cite as: 43 CFR 2885.14