(a) Preparation and submission of initial CBDPP to DOE. (1) The responsible employer at a DOE facility must ensure that a CBDPP is prepared for the facility and submitted to the appropriate Head of DOE Field Element before beginning beryllium activities, but no later than April 6, 2000 of this part.
(2) If the CBDPP has separate sections addressing the activities of multiple contractors at the facility, the Head of DOE Field Element will designate a single DOE contractor to review and approve the sections prepared by other contractors, so that a single consolidated CBDPP for the facility is submitted to the Head of DOE Field Element for review and approval.
(b) DOE review and approval. The appropriate Head of DOE Field Element must review and approve the CBDPP.
(1) The initial CBDPP and any updates are deemed approved 90 days after submission if they are not specifically approved or rejected by DOE earlier.
(2) The responsible employer must furnish a copy of the approved CBDPP, upon request, to the DOE Director, Office of Environment, Health, Safety and Security or designee, DOE program offices, and affected workers or their designated representatives.
(c) Update. The responsible employer must submit an update of the CBDPP to the appropriate Head of DOE Field Element for review and approval whenever a significant change or significant addition to the CBDPP is made or a change in contractors occurs. The Head of DOE Field Element must review the CBDPP at least annually and, if necessary, require the responsible employer to update the CBDPP.
(d) Labor Organizations. If a responsible employer employs or supervises beryllium-associated workers who are represented for collective bargaining by a labor organization, the responsible employer must:
(1) Give the labor organization timely notice of the development and implementation of the CBDPP and any updates thereto; and
(2) Upon timely request, bargain concerning implementation of this part, consistent with the Federal labor laws.
[64 FR 68905, Dec. 8, 1999, as amended at 71 FR 68733, Nov. 28, 2006; 80 FR 5008, Jan. 30, 2015; 88 FR 41293, June 26, 2023]
(a) The CBDPP must specify the existing and planned operational tasks that are within the scope of the CBDPP. The CBDPP must augment and, to the extent feasible, be integrated into the existing worker protection programs that cover activities at the facility.
(b) The detail, scope, and content of the CBDPP must be commensurate with the hazard of the activities performed, but in all cases the CBDPP must:
(1) Include formal plans and measures for maintaining exposures to beryllium at or below the permissible exposure level prescribed in § 850.22;
(2) Satisfy each requirement in subpart C of this part;
(3) Contain provisions for:
(i) Minimizing the number of workers exposed and potentially exposed to beryllium;
(ii) Minimizing the number of opportunities for workers to be exposed to beryllium;
(iii) Minimizing the disability and lost work time of workers due to chronic beryllium disease, beryllium sensitization and associated medical care; and
(iv) Setting specific exposure reduction and minimization goals that are appropriate for the beryllium activities covered by the CBDPP to further reduce exposure below the permissible exposure limit prescribed in § 850.22.
(a) The responsible employer must manage and control beryllium exposures in all DOE beryllium activities consistent with the approved CBDPP.
(b) No person employed by DOE or a DOE contractor may take or cause any action inconsistent with the requirements of:
(1) This part,
(2) An approved CBDPP, and
(3) Any other Federal statute or regulation concerning the exposure of workers to beryllium at DOE facilities.
(c) No task involving potential exposure to airborne beryllium that is outside the scope of the existing CBDPP may be initiated until an update of the CBDPP is approved by the Head of DOE Field Element, except in an unexpected situation and, then, only upon approval of the Head of DOE Field Element.
(d) Nothing in this part precludes a responsible employer from taking any additional protective action that it determines to be necessary to protect the health and safety of workers.
(e) Nothing in this part affects the responsibilities of DOE officials under the Federal Employee Occupational Safety and Health Program (29 CFR part 1960) and related DOE directives.
(a) The responsible employer must conduct activities in compliance with its CBDPP.
(b) The responsible employer must achieve compliance with all elements of its CBDPP no later than January 7, 2002.
(c) With respect to a particular beryllium activity, the contractor in charge of the activity is responsible for complying with this part. If no contractor is responsible for a beryllium activity, DOE must ensure implementation of, and compliance with, this part.