Regulations last checked for updates: Nov 22, 2024

Title 10 - Energy last revised: Nov 19, 2024
§ 1021.400 - Level of NEPA review.

(a) This subpart identifies DOE actions that normally:

(1) Do not require preparation of either an EIS or an EA (are categorically excluded from preparation of either document) (appendices A and B to this subpart D);

(2) Require preparation of an EA, but not necessarily an EIS (appendix C to this subpart D); or

(3) Require preparation of an EIS (appendix D to this subpart D).

(b) Any completed, valid NEPA review does not have to be repeated, and no completed NEPA documents need to be redone by reasons of these regulations, except as provided in § 1021.314.

(c) If a DOE proposal is encompassed within a class of actions listed in the appendices to this subpart D, DOE shall proceed with the level of NEPA review indicated for that class of actions, unless there are extraordinary circumstances related to the specific proposal that may affect the significance of the environmental effects of the proposal.

(d) If a DOE proposal is not encompassed within the classes of actions listed in the appendices to this subpart D, or if there are extraordinary circumstances related to the proposal that may affect the significance of the environmental effects of the proposal, DOE shall either:

(1) Prepare an EA and, on the basis of that EA, determine whether to prepare an EIS or a FONSI; or

(2) Prepare an EIS and ROD.

§ 1021.410 - Application of categorical exclusions (classes of actions that normally do not require EAs or EISs).

(a) The actions listed in appendices A and B to this subpart D are classes of actions that DOE has determined do not individually or cumulatively have a significant effect on the human environment (categorical exclusions).

(b) To find that a proposal is categorically excluded, DOE shall determine the following:

(1) The proposal fits within a class of actions that is listed in appendix A or B to this subpart D;

(2) There are no extraordinary circumstances related to the proposal that may affect the significance of the environmental effects of the proposal. Extraordinary circumstances are unique situations presented by specific proposals, including, but not limited to, scientific controversy about the environmental effects of the proposal; uncertain effects or effects involving unique or unknown risks; and unresolved conflicts concerning alternative uses of available resources; and

(3) The proposal has not been segmented to meet the definition of a categorical exclusion. Segmentation can occur when a proposal is broken down into small parts in order to avoid the appearance of significance of the total action. The scope of a proposal must include the consideration of connected and cumulative actions, that is, the proposal is not connected to other actions with potentially significant impacts (40 CFR 1508.25(a)(1)), is not related to other actions with individually insignificant but cumulatively significant impacts (40 CFR 1508.27(b)(7)), and is not precluded by 40 CFR 1506.1 or § 1021.211 of this part concerning limitations on actions during EIS preparation.

(c) All categorical exclusions may be applied by any organizational element of DOE. The sectional divisions in appendix B to this subpart D are solely for purposes of organization of that appendix and are not intended to be limiting.

(d) A class of actions includes activities foreseeably necessary to proposals encompassed within the class of actions (such as award of implementing grants and contracts, site preparation, purchase and installation of equipment, and associated transportation activities).

(e) Categorical exclusion determinations for actions listed in appendix B shall be documented and made available to the public by posting online, generally within two weeks of the determination, unless additional time is needed in order to review and protect classified information, “confidential business information,” or other information that DOE would not disclose pursuant to the Freedom of Information Act (FOIA) (5 U.S.C. 552). Posted categorical exclusion determinations shall not disclose classified information, “confidential business information,” or other information that DOE would not disclose pursuant to FOIA. (See also 10 CFR 1021.340.)

(f) Proposed recurring activities to be undertaken during a specified time period, such as routine maintenance activities for a year, may be addressed in a single categorical exclusion determination after considering the potential aggregated impacts.

(g) The following clarifications are provided to assist in the appropriate application of categorical exclusions that employ the terms or phrases:

(1) “Previously disturbed or developed” refers to land that has been changed such that its functioning ecological processes have been and remain altered by human activity. The phrase encompasses areas that have been transformed from natural cover to non-native species or a managed state, including, but not limited to, utility and electric power transmission corridors and rights-of-way, and other areas where active utilities and currently used roads are readily available.

(2) DOE considers terms such as “small” and “small-scale” in the context of the particular proposal, including its proposed location. In assessing whether a proposed action is small, in addition to the actual magnitude of the proposal, DOE considers factors such as industry norms, the relationship of the proposed action to similar types of development in the vicinity of the proposed action, and expected outputs of emissions or waste. When considering the physical size of a proposed facility, for example, DOE would review the surrounding land uses, the scale of the proposed facility relative to existing development, and the capacity of existing roads and other infrastructure to support the proposed action.

Appendix Appendix A - Appendix A to Subpart D of Part 1021—Categorical Exclusions Applicable to General Agency Actions
Table of Contents A1 Routine DOE business actions A2 Clarifying or administrative contract actions A3 Certain actions by Office of Hearings and Appeals A4 Interpretations and rulings for existing regulations A5 Interpretive rulemakings with no change in environmental effect A6 Procedural rulemakings A7 [Reserved] A8 Awards of certain contracts A9 Information gathering, analysis, and dissemination A10 Reports and recommendations on non-DOE legislation A11 Technical advice and assistance to organizations A12 Emergency preparedness planning A13 Procedural documents A14 Approval of technical exchange arrangements A15 International agreements for energy research and development A1 Routine DOE business actions

Routine actions necessary to support the normal conduct of DOE business limited to administrative, financial, and personnel actions.

A2 Clarifying or administrative contract actions

Contract interpretations, amendments, and modifications that are clarifying or administrative in nature.

A3 Certain actions by Office of Hearings and Appeals

Adjustments, exceptions, exemptions, appeals and stays, modifications, or rescissions of orders issued by the Office of Hearings and Appeals.

A4 Interpretations and rulings for existing regulations

Interpretations and rulings with respect to existing regulations, or modifications or rescissions of such interpretations and rulings.

A5 Interpretive rulemakings with no change in environmental effect

Rulemakings interpreting or amending an existing rule or regulation that does not change the environmental effect of the rule or regulation being amended.

A6 Procedural rulemakings

Rulemakings that are strictly procedural, including, but not limited to, rulemaking (under 48 CFR chapter 9) establishing procedures for technical and pricing proposals and establishing contract clauses and contracting practices for the purchase of goods and services, and rulemaking (under 10 CFR part 600) establishing application and review procedures for, and administration, audit, and closeout of, grants and cooperative agreements.

A7 [Reserved] A8 Awards of certain contracts

Awards of contracts for technical support services, management and operation of a government-owned facility, and personal services.

A9 Information gathering, analysis, and dissemination

Information gathering (including, but not limited to, literature surveys, inventories, site visits, and audits), data analysis (including, but not limited to, computer modeling), document preparation (including, but not limited to, conceptual design, feasibility studies, and analytical energy supply and demand studies), and information dissemination (including, but not limited to, document publication and distribution, and classroom training and informational programs), but not including site characterization or environmental monitoring. (See also B3.1 of appendix B to this subpart.)

A10 Reports and recommendations on non-DOE legislation

Reports and recommendations on legislation or rulemaking that are not proposed by DOE.

A11 Technical advice and assistance to organizations

Technical advice and planning assistance to international, national, state, and local organizations.

A12 Emergency preparedness planning

Emergency preparedness planning activities, including, but not limited to, the designation of onsite evacuation routes.

A13 Procedural documents

Administrative, organizational, or procedural Policies, Orders, Notices, Manuals, and Guides.

A14 Approval of technical exchange arrangements

Approval of technical exchange arrangements for information, data, or personnel with other countries or international organizations (including, but not limited to, assistance in identifying and analyzing another country's energy resources, needs and options).

A15 International agreements for energy research and development

Approval of DOE participation in international “umbrella” agreements for cooperation in energy research and development activities that would not commit the U.S. to any specific projects or activities.

Appendix Appendix B - Appendix B to Subpart D of Part 1021—Categorical Exclusions Applicable to Specific Agency Actions
Table of Contents B. Conditions that Are Integral Elements of the Classes of Actions in Appendix B B1. Categorical Exclusions Applicable to Facility Operation B1.1 Changing rates and prices B1.2 Training exercises and simulations B1.3 Routine maintenance B1.4 Air conditioning systems for existing equipment B1.5 Existing steam plants and cooling water systems B1.6 Tanks and equipment to control runoff and spills B1.7 Electronic equipment B1.8 Screened water intake and outflow structures B1.9 Airway safety markings and painting B1.10 Onsite storage of activated material B1.11 Fencing B1.12 Detonation or burning of explosives or propellants after testing B1.13 Pathways, short access roads, and rail lines B1.14 Refueling of nuclear reactors B1.15 Support buildings B1.16 Asbestos removal B1.17 Polychlorinated biphenyl removal B1.18 Water supply wells B1.19 Microwave, meteorological, and radio towers B1.20 Protection of cultural resources, fish and wildlife habitat B1.21 Noise abatement B1.22 Relocation of buildings B1.23 Demolition and disposal of buildings B1.24 Property transfers B1.25 Real property transfers for cultural resources protection, habitat preservation, and wildlife management B1.26 Small water treatment facilities B1.27 Disconnection of utilities B1.28 Placing a facility in an environmentally safe condition B1.29 Disposal facilities for construction and demolition waste B1.30 Transfer actions B1.31 Installation or relocation of machinery and equipment B1.32 Traffic flow adjustments B1.33 Stormwater runoff control B1.34 Lead-based paint containment, removal, and disposal B1.35 Drop-off, collection, and transfer facilities for recyclable materials B1.36 Determinations of excess real property B2. Categorical Exclusions Applicable to Safety and Health B2.1 Workplace enhancements B2.2 Building and equipment instrumentation B2.3 Personnel safety and health equipment B2.4 Equipment qualification B2.5 Facility safety and environmental improvements B2.6 Recovery of radioactive sealed sources B3. Categorical Exclusions Applicable to Site Characterization, Monitoring, and General Research B3.1 Site characterization and environmental monitoring B3.2 Aviation activities B3.3 Research related to conservation of fish, wildlife, and cultural resources B3.4 Transport packaging tests for radioactive or hazardous material B3.5 Tank car tests B3.6 Small-scale research and development, laboratory operations, and pilot projects B3.7 New terrestrial infill exploratory and experimental wells B3.8 Outdoor terrestrial ecological and environmental research B3.9 Projects to reduce emissions and waste generation B3.10 Particle accelerators B3.11 Outdoor tests and experiments on materials and equipment components B3.12 Microbiological and biomedical facilities B3.13 Magnetic fusion experiments B3.14 Small-scale educational facilities B3.15 Small-scale indoor research and development projects using nanoscale materials B3.16 Research activities in aquatic environments B4. Categorical Exclusions Applicable to Electric Power and Transmission B4.1 Contracts, policies, and marketing and allocation plans for electric power B4.2 Export of electric energy B4.3 Electric power marketing rate changes B4.4 Power marketing services and activities B4.5 Temporary adjustments to river operations B4.6 Additions and modifications to transmission facilities B4.7 Fiber optic cable B4.8 Electricity transmission agreements B4.9 Multiple use of powerline rights-of-way B4.10 Removal of electric transmission facilities B4.11 Electric power substations and interconnection facilities B4.12 Construction of powerlines B4.13 Upgrading and rebuilding existing powerlines B4.14 Construction and Operation of Electrochemical-Battery or Flywheel Energy Storage Systems B5. Categorical Exclusions Applicable to Conservation, Fossil, and Renewable Energy Activities B5.1 Actions to conserve energy or water B5.2 Modifications to pumps and piping B5.3 Modification or abandonment of wells B5.4 Repair or replacement of pipelines B5.5 Short pipeline segments B5.6 Oil spill cleanup B5.7 Export of natural gas and associated transportation by marine vessel B5.8 [Reserved] B5.9 Temporary exemptions for electric powerplants B5.10 Certain permanent exemptions for existing electric powerplants B5.11 Permanent exemptions allowing mixed natural gas and petroleum B5.12 Workover of existing wells B5.13 Experimental wells for injection of small quantities of carbon dioxide B5.14 Combined heat and power or cogeneration systems B5.15 Small-scale renewable energy research and development and pilot projects B5.16 Solar photovoltaic systems B5.17 Solar thermal systems B5.18 Wind turbines B5.19 Ground source heat pumps B5.20 Biomass power plants B5.21 Methane gas recovery and utilization systems B5.22 Alternative fuel vehicle fueling stations B5.23 Electric vehicle charging stations B5.24 Drop-in hydroelectric systems B5.25 Small-scale renewable energy research and development and pilot projects in aquatic environments B6. Categorical Exclusions Applicable to Environmental Restoration and Waste Management Activities B6.1 Cleanup actions B6.2 Waste collection, treatment, stabilization, and containment facilities B6.3 Improvements to environmental control systems B6.4 Facilities for storing packaged hazardous waste for 90 days or less B6.5 Facilities for characterizing and sorting packaged waste and overpacking waste B6.6 Modification of facilities for storing, packaging, and repacking waste B6.7 [Reserved] B6.8 Modifications for waste minimization and reuse of materials B6.9 Measures to reduce migration of contaminated groundwater B6.10 Upgraded or replacement waste storage facilities B7. Categorical Exclusions Applicable to International Activities B7.1 Emergency measures under the International Energy Program B7.2 Import and export of special nuclear or isotopic materials B. Conditions That Are Integral Elements of the Classes of Actions in Appendix B

The classes of actions listed below include the following conditions as integral elements of the classes of actions. To fit within the classes of actions listed below, a proposal must be one that would not:

(1) Threaten a violation of applicable statutory, regulatory, or permit requirements for environment, safety, and health, or similar requirements of DOE or Executive Orders;

(2) Require siting and construction or major expansion of waste storage, disposal, recovery, or treatment facilities (including incinerators), but the proposal may include categorically excluded waste storage, disposal, recovery, or treatment actions or facilities;

(3) Disturb hazardous substances, pollutants, contaminants, or CERCLA-excluded petroleum and natural gas products that preexist in the environment such that there would be uncontrolled or unpermitted releases;

(4) Have the potential to cause significant impacts on environmentally sensitive resources. An environmentally sensitive resource is typically a resource that has been identified as needing protection through Executive Order, statute, or regulation by Federal, state, or local government, or a Federally recognized Indian tribe. An action may be categorically excluded if, although sensitive resources are present, the action would not have the potential to cause significant impacts on those resources (such as construction of a building with its foundation well above a sole-source aquifer or upland surface soil removal on a site that has wetlands). Environmentally sensitive resources include, but are not limited to:

(i) Property (such as sites, buildings, structures, and objects) of historic, archeological, or architectural significance designated by a Federal, state, or local government, Federally recognized Indian tribe, or Native Hawaiian organization, or property determined to be eligible for listing on the National Register of Historic Places;

(ii) Federally-listed threatened or endangered species or their habitat (including critical habitat) or Federally-proposed or candidate species or their habitat (Endangered Species Act); state-listed or state-proposed endangered or threatened species or their habitat; Federally-protected marine mammals and Essential Fish Habitat (Marine Mammal Protection Act; Magnuson-Stevens Fishery Conservation and Management Act); and otherwise Federally-protected species (such as the Bald and Golden Eagle Protection Act or the Migratory Bird Treaty Act);

(iii) Floodplains and wetlands (as defined in 10 CFR 1022.4, “Compliance with Floodplain and Wetland Environmental Review Requirements: Definitions,” or its successor);

(iv) Areas having a special designation such as Federally- and state-designated wilderness areas, national parks, national monuments, national natural landmarks, wild and scenic rivers, state and Federal wildlife refuges, scenic areas (such as National Scenic and Historic Trails or National Scenic Areas), and marine sanctuaries;

(v) Prime or unique farmland, or other farmland of statewide or local importance, as defined at 7 CFR 658.2(a), “Farmland Protection Policy Act: Definitions,” or its successor;

(vi) Special sources of water (such as sole-source aquifers, wellhead protection areas, and other water sources that are vital in a region); and

(vii) Tundra, coral reefs, or rain forests; or

(5) Involve genetically engineered organisms, synthetic biology, governmentally designated noxious weeds, or invasive species, unless the proposed activity would be contained or confined in a manner designed and operated to prevent unauthorized release into the environment and conducted in accordance with applicable requirements, such as those of the Department of Agriculture, the Environmental Protection Agency, and the National Institutes of Health.

B1. Categorical Exclusions Applicable to Facility Operation B1.1 Changing rates and prices

Changing rates for services or prices for products marketed by parts of DOE other than Power Marketing Administrations, and approval of rate or price changes for non-DOE entities, that are consistent with the change in the implicit price deflator for the Gross Domestic Product published by the Department of Commerce, during the period since the last rate or price change.

B1.2 Training exercises and simulations

Training exercises and simulations (including, but not limited to, firing-range training, small-scale and short-duration force-on-force exercises, emergency response training, fire fighter and rescue training, and decontamination and spill cleanup training) conducted under appropriately controlled conditions and in accordance with applicable requirements.

B1.3 Routine maintenance

Routine maintenance activities and custodial services for buildings, structures, rights-of-way, infrastructures (including, but not limited to, pathways, roads, and railroads), vehicles and equipment, and localized vegetation and pest control, during which operations may be suspended and resumed, provided that the activities would be conducted in a manner in accordance with applicable requirements. Custodial services are activities to preserve facility appearance, working conditions, and sanitation (such as cleaning, window washing, lawn mowing, trash collection, painting, and snow removal). Routine maintenance activities, corrective (that is, repair), preventive, and predictive, are required to maintain and preserve buildings, structures, infrastructures, and equipment in a condition suitable for a facility to be used for its designated purpose. Such maintenance may occur as a result of severe weather (such as hurricanes, floods, and tornados), wildfires, and other such events. Routine maintenance may result in replacement to the extent that replacement is in-kind and is not a substantial upgrade or improvement. In-kind replacement includes installation of new components to replace outmoded components, provided that the replacement does not result in a significant change in the expected useful life, design capacity, or function of the facility. Routine maintenance does not include replacement of a major component that significantly extends the originally intended useful life of a facility (for example, it does not include the replacement of a reactor vessel near the end of its useful life). Routine maintenance activities include, but are not limited to:

(a) Repair or replacement of facility equipment, such as lathes, mills, pumps, and presses;

(b) Door and window repair or replacement;

(c) Wall, ceiling, or floor repair or replacement;

(d) Reroofing;

(e) Plumbing, electrical utility, lighting, and telephone service repair or replacement;

(f) Routine replacement of high-efficiency particulate air filters;

(g) Inspection and/or treatment of currently installed utility poles;

(h) Repair of road embankments;

(i) Repair or replacement of fire protection sprinkler systems;

(j) Road and parking area resurfacing, including construction of temporary access to facilitate resurfacing, and scraping and grading of unpaved surfaces;

(k) Erosion control and soil stabilization measures (such as reseeding, gabions, grading, and revegetation);

(l) Surveillance and maintenance of surplus facilities in accordance with DOE Order 435.1, “Radioactive Waste Management,” or its successor;

(m) Repair and maintenance of transmission facilities, such as replacement of conductors of the same nominal voltage, poles, circuit breakers, transformers, capacitors, crossarms, insulators, and downed powerlines, in accordance, where appropriate, with 40 CFR part 761 (Polychlorinated Biphenyls Manufacturing, Processing, Distribution in Commerce, and Use Prohibitions) or its successor;

(n) Routine testing and calibration of facility components, subsystems, or portable equipment (such as control valves, in-core monitoring devices, transformers, capacitors, monitoring wells, lysimeters, weather stations, and flumes);

(o) Routine decontamination of the surfaces of equipment, rooms, hot cells, or other interior surfaces of buildings (by such activities as wiping with rags, using strippable latex, and minor vacuuming), and removal of contaminated intact equipment and other material (not including spent nuclear fuel or special nuclear material in nuclear reactors); and

(p) Removal of debris.

B1.4 Air conditioning systems for existing equipment

Installation or modification of air conditioning systems required for temperature control for operation of existing equipment.

B1.5 Existing steam plants and cooling water systems

Minor improvements to existing steam plants and cooling water systems (including, but not limited to, modifications of existing cooling towers and ponds), provided that the improvements would not: (1) Create new sources of water or involve new receiving waters; (2) have the potential to significantly alter water withdrawal rates; (3) exceed the permitted temperature of discharged water; or (4) increase introductions of, or involve new introductions of, hazardous substances, pollutants, contaminants, or CERCLA-excluded petroleum and natural gas products.

B1.6 Tanks and equipment to control runoff and spills

Installation or modification of retention tanks or small (normally under one acre) basins and associated piping and pumps for existing operations to control runoff or spills (such as under 40 CFR part 112). Modifications include, but are not limited to, installing liners or covers. (See also B1.33 of this appendix.)

B1.7 Electronic equipment

Acquisition, installation, operation, modification, and removal of electricity transmission control and monitoring devices for grid demand and response, communication systems, data processing equipment, and similar electronic equipment.

B1.8 Screened water intake and outflow structures

Modifications to screened water intake and outflow structures such that intake velocities and volumes and water effluent quality and volumes are consistent with existing permit limits.

B1.9 Airway safety markings and painting

Placement of airway safety markings on, painting of, and repair and in-kind replacement of lighting on powerlines and antenna structures, wind turbines, and similar structures in accordance with applicable requirements (such as Federal Aviation Administration standards).

B1.10 Onsite storage of activated material

Routine, onsite storage at an existing facility of activated equipment and material (including, but not limited to, lead) used at that facility, to allow reuse after decay of radioisotopes with short half-lives.

B1.11 Fencing

Installation of fencing, including, but not limited to border marking, that would not have the potential to significantly impede wildlife population movement (including migration) or surface water flow.

B1.12 Detonation or burning of explosives or propellants after testing

Outdoor detonation or burning of explosives or propellants that failed (duds), were damaged (such as by fracturing), or were otherwise not consumed in testing. Outdoor detonation or burning would be in areas designated and routinely used for those purposes under existing applicable permits issued by Federal, state, and local authorities (such as a permit for a RCRA miscellaneous unit (40 CFR part 264, subpart X)).

B1.13 Pathways, short access roads, and rail lines

Construction, acquisition, and relocation, consistent with applicable right-of-way conditions and approved land use or transportation improvement plans, of pedestrian walkways and trails, bicycle paths, small outdoor fitness areas, and short access roads and rail lines (such as branch and spur lines).

B1.14 Refueling of nuclear reactors

Refueling of operating nuclear reactors, during which operations may be suspended and then resumed.

B1.15 Support buildings

Siting, construction or modification, and operation of support buildings and support structures (including, but not limited to, trailers and prefabricated and modular buildings) within or contiguous to an already developed area (where active utilities and currently used roads are readily accessible). Covered support buildings and structures include, but are not limited to, those for office purposes; parking; cafeteria services; education and training; visitor reception; computer and data processing services; health services or recreation activities; routine maintenance activities; storage of supplies and equipment for administrative services and routine maintenance activities; security (such as security posts); fire protection; small-scale fabrication (such as machine shop activities), assembly, and testing of non-nuclear equipment or components; and similar support purposes, but exclude facilities for nuclear weapons activities and waste storage activities, such as activities covered in B1.10, B1.29, B1.35, B2.6, B6.2, B6.4, B6.5, B6.6, and B6.10 of this appendix.

B1.16 Asbestos removal

Removal of asbestos-containing materials from buildings in accordance with applicable requirements (such as 40 CFR part 61, “National Emission Standards for Hazardous Air Pollutants”; 40 CFR part 763, “Asbestos”; 29 CFR part 1910, subpart I, “Personal Protective Equipment”; and 29 CFR part 1926, “Safety and Health Regulations for Construction”; and appropriate state and local requirements, including certification of removal contractors and technicians).

B1.17 Polychlorinated biphenyl removal

Removal of polychlorinated biphenyl (PCB)-containing items (including, but not limited to, transformers and capacitors), PCB-containing oils flushed from transformers, PCB-flushing solutions, and PCB-containing spill materials from buildings or other aboveground locations in accordance with applicable requirements (such as 40 CFR part 761).

B1.18 Water supply wells

Siting, construction, and operation of additional water supply wells (or replacement wells) within an existing well field, or modification of an existing water supply well to restore production, provided that there would be no drawdown other than in the immediate vicinity of the pumping well, and the covered actions would not have the potential to cause significant long-term decline of the water table, and would not have the potential to cause significant degradation of the aquifer from the new or replacement well.

B1.19 Microwave, meteorological, and radio towers

Siting, construction, modification, operation, and removal of microwave, radio communication, and meteorological towers and associated facilities, provided that the towers and associated facilities would not be in a governmentally designated scenic area (see B(4)(iv) of this appendix) unless otherwise authorized by the appropriate governmental entity.

B1.20 Protection of cultural resources, fish and wildlife habitat

Small-scale activities undertaken to protect cultural resources (such as fencing, labeling, and flagging) or to protect, restore, or improve fish and wildlife habitat, fish passage facilities (such as fish ladders and minor diversion channels), or fisheries. Such activities would be conducted in accordance with an existing natural or cultural resource plan, if any.

B1.21 Noise abatement

Noise abatement measures (including, but not limited to, construction of noise barriers and installation of noise control materials).

B1.22 Relocation of buildings

Relocation of buildings (including, but not limited to, trailers and prefabricated buildings) to an already developed area (where active utilities and currently used roads are readily accessible).

B1.23 Demolition and disposal of buildings

Demolition and subsequent disposal of buildings, equipment, and support structures (including, but not limited to, smoke stacks and parking lot surfaces), provided that there would be no potential for release of substances at a level, or in a form, that could pose a threat to public health or the environment.

B1.24 Property transfers

Transfer, lease, disposition, or acquisition of interests in personal property (including, but not limited to, equipment and materials) or real property (including, but not limited to, permanent structures and land), provided that under reasonably foreseeable uses (1) there would be no potential for release of substances at a level, or in a form, that could pose a threat to public health or the environment and (2) the covered actions would not have the potential to cause a significant change in impacts from before the transfer, lease, disposition, or acquisition of interests.

B1.25 Real property transfers for cultural resources protection, habitat preservation, and wildlife management

Transfer, lease, disposition, or acquisition of interests in land and associated buildings for cultural resources protection, habitat preservation, or fish and wildlife management, provided that there would be no potential for release of substances at a level, or in a form, that could pose a threat to public health or the environment.

B1.26 Small water treatment facilities

Siting, construction, expansion, modification, replacement, operation, and decommissioning of small (total capacity less than approximately 250,000 gallons per day) wastewater and surface water treatment facilities whose liquid discharges are externally regulated, and small potable water and sewage treatment facilities.

B1.27 Disconnection of utilities

Activities that are required for the disconnection of utility services (including, but not limited to, water, steam, telecommunications, and electrical power) after it has been determined that the continued operation of these systems is not needed for safety.

B1.28 Placing a facility in an environmentally safe condition

Minor activities that are required to place a facility in an environmentally safe condition where there is no proposed use for the facility. These activities would include, but are not limited to, reducing surface contamination, and removing materials, equipment or waste (such as final defueling of a reactor, where there are adequate existing facilities for the treatment, storage, or disposal of the materials, equipment or waste). These activities would not include conditioning, treatment, or processing of spent nuclear fuel, high-level waste, or special nuclear materials.

B1.29 Disposal facilities for construction and demolition waste

Siting, construction, expansion, modification, operation, and decommissioning of small (less than approximately 10 acres) solid waste disposal facilities for construction and demolition waste, in accordance with applicable requirements (such as 40 CFR part 257, “Criteria for Classification of Solid Waste Disposal Facilities and Practices,” and 40 CFR part 61, “National Emission Standards for Hazardous Air Pollutants”) that would not release substances at a level, or in a form, that could pose a threat to public health or the environment.

B1.30 Transfer actions

Transfer actions, in which the predominant activity is transportation, provided that (1) the receipt and storage capacity and management capability for the amount and type of materials, equipment, or waste to be moved already exists at the receiving site and (2) all necessary facilities and operations at the receiving site are already permitted, licensed, or approved, as appropriate. Such transfers are not regularly scheduled as part of ongoing routine operations.

B1.31 Installation or relocation of machinery and equipment

Installation or relocation and operation of machinery and equipment (including, but not limited to, laboratory equipment, electronic hardware, manufacturing machinery, maintenance equipment, and health and safety equipment), provided that uses of the installed or relocated items are consistent with the general missions of the receiving structure. Covered actions include modifications to an existing building, within or contiguous to a previously disturbed or developed area, that are necessary for equipment installation and relocation. Such modifications would not appreciably increase the footprint or height of the existing building or have the potential to cause significant changes to the type and magnitude of environmental impacts.

B1.32 Traffic flow adjustments

Traffic flow adjustments to existing roads (including, but not limited to, stop sign or traffic light installation, adjusting direction of traffic flow, and adding turning lanes), and road adjustments (including, but not limited to, widening and realignment) that are within an existing right-of-way and consistent with approved land use or transportation improvement plans.

B1.33 Stormwater runoff control

Design, construction, and operation of control practices to reduce stormwater runoff and maintain natural hydrology. Activities include, but are not limited to, those that reduce impervious surfaces (such as vegetative practices and use of porous pavements), best management practices (such as silt fences, straw wattles, and fiber rolls), and use of green infrastructure or other low impact development practices (such as cisterns and green roofs).

B1.34 Lead-based paint containment, removal, and disposal

Containment, removal, and disposal of lead-based paint in accordance with applicable requirements (such as provisions relating to the certification of removal contractors and technicians at 40 CFR part 745, “Lead-Based Paint Poisoning Prevention In Certain Residential Structures”).

B1.35 Drop-off, collection, and transfer facilities for recyclable materials

Siting, construction, modification, and operation of recycling or compostable material drop-off, collection, and transfer stations on or contiguous to a previously disturbed or developed area and in an area where such a facility would be consistent with existing zoning requirements. The stations would have appropriate facilities and procedures established in accordance with applicable requirements for the handling of recyclable or compostable materials and household hazardous waste (such as paint and pesticides). Except as specified above, the collection of hazardous waste for disposal and the processing of recyclable or compostable materials are not included in this class of actions.

B1.36 Determinations of excess real property

Determinations that real property is excess to the needs of DOE and, in the case of acquired real property, the subsequent reporting of such determinations to the General Services Administration or, in the case of lands withdrawn or otherwise reserved from the public domain, the subsequent filing of a notice of intent to relinquish with the Bureau of Land Management, Department of the Interior. Covered actions would not include disposal of real property.

B2. Categorical Exclusions Applicable to Safety and Health B2.1 Workplace enhancements

Modifications within or contiguous to an existing structure, in a previously disturbed or developed area, to enhance workplace habitability (including, but not limited to, installation or improvements to lighting, radiation shielding, or heating/ventilating/air conditioning and its instrumentation, and noise reduction).

B2.2 Building and equipment instrumentation

Installation of, or improvements to, building and equipment instrumentation (including, but not limited to, remote control panels, remote monitoring capability, alarm and surveillance systems, control systems to provide automatic shutdown, fire detection and protection systems, water consumption monitors and flow control systems, announcement and emergency warning systems, criticality and radiation monitors and alarms, and safeguards and security equipment).

B2.3 Personnel safety and health equipment

Installation of, or improvements to, equipment for personnel safety and health (including, but not limited to, eye washes, safety showers, radiation monitoring devices, fumehoods, and associated collection and exhaust systems), provided that the covered actions would not have the potential to cause a significant increase in emissions.

B2.4 Equipment qualification

Activities undertaken to (1) qualify equipment for use or improve systems reliability or (2) augment information on safety-related system components. These activities include, but are not limited to, transportation container qualification testing, crane and lift-gear certification or recertification testing, high efficiency particulate air filter testing and certification, stress tests (such as “burn-in” testing of electrical components and leak testing), and calibration of sensors or diagnostic equipment.

B2.5 Facility safety and environmental improvements

Safety and environmental improvements of a facility (including, but not limited to, replacement and upgrade of facility components) that do not result in a significant change in the expected useful life, design capacity, or function of the facility and during which operations may be suspended and then resumed. Improvements include, but are not limited to, replacement/upgrade of control valves, in-core monitoring devices, facility air filtration systems, or substation transformers or capacitors; addition of structural bracing to meet earthquake standards and/or sustain high wind loading; and replacement of aboveground or belowground tanks and related piping, provided that there is no evidence of leakage, based on testing in accordance with applicable requirements (such as 40 CFR part 265, “Interim Status Standards for Owners and Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities” and 40 CFR part 280, “Technical Standards and Corrective Action Requirements for Owners and Operators of Underground Storage Tanks”). These actions do not include rebuilding or modifying substantial portions of a facility (such as replacing a reactor vessel).

B2.6 Recovery of radioactive sealed sources

Recovery of radioactive sealed sources and sealed source-containing devices from domestic or foreign locations provided that (1) the recovered items are transported and stored in compliant containers, and (2) the receiving site has sufficient existing storage capacity and all required licenses, permits, and approvals.

B3. Categorical Exclusions Applicable to Site Characterization, Monitoring, and General Research B3.1 Site characterization and environmental monitoring

Site characterization and environmental monitoring (including, but not limited to, siting, construction, modification, operation, and dismantlement and removal or otherwise proper closure (such as of a well) of characterization and monitoring devices, and siting, construction, and associated operation of a small-scale laboratory building or renovation of a room in an existing building for sample analysis). Such activities would be designed in conformance with applicable requirements and use best management practices to limit the potential effects of any resultant ground disturbance. Covered activities include, but are not limited to, site characterization and environmental monitoring under CERCLA and RCRA. (This class of actions excludes activities in aquatic environments. See B3.16 of this appendix for such activities.) Specific activities include, but are not limited to:

(a) Geological, geophysical (such as gravity, magnetic, electrical, seismic, radar, and temperature gradient), geochemical, and engineering surveys and mapping, and the establishment of survey marks. Seismic techniques would not include large-scale reflection or refraction testing;

(b) Installation and operation of field instruments (such as stream-gauging stations or flow-measuring devices, telemetry systems, geochemical monitoring tools, and geophysical exploration tools);

(c) Drilling of wells for sampling or monitoring of groundwater or the vadose (unsaturated) zone, well logging, and installation of water-level recording devices in wells;

(d) Aquifer and underground reservoir response testing;

(e) Installation and operation of ambient air monitoring equipment;

(f) Sampling and characterization of water, soil, rock, or contaminants (such as drilling using truck- or mobile-scale equipment, and modification, use, and plugging of boreholes);

(g) Sampling and characterization of water effluents, air emissions, or solid waste streams;

(h) Installation and operation of meteorological towers and associated activities (such as assessment of potential wind energy resources);

(i) Sampling of flora or fauna; and

(j) Archeological, historic, and cultural resource identification in compliance with 36 CFR part 800 and 43 CFR part 7.

B3.2 Aviation activities

Aviation activities for survey, monitoring, or security purposes that comply with Federal Aviation Administration regulations.

B3.3 Research related to conservation of fish, wildlife, and cultural resources

Field and laboratory research, inventory, and information collection activities that are directly related to the conservation of fish and wildlife resources or to the protection of cultural resources, provided that such activities would not have the potential to cause significant impacts on fish and wildlife habitat or populations or to cultural resources.

B3.4 Transport packaging tests for radioactive or hazardous material

Drop, puncture, water-immersion, thermal, and fire tests of transport packaging for radioactive or hazardous materials to certify that designs meet the applicable requirements (such as 49 CFR 173.411 and 173.412 and 10 CFR 71.73).

B3.5 Tank car tests

Tank car tests under 49 CFR part 179 (including, but not limited to, tests of safety relief devices, pressure regulators, and thermal protection systems).

B3.6 Small-scale research and development, laboratory operations, and pilot projects

Siting, construction, modification, operation, and decommissioning of facilities for small-scale research and development projects; conventional laboratory operations (such as preparation of chemical standards and sample analysis); and small-scale pilot projects (generally less than 2 years) frequently conducted to verify a concept before demonstration actions, provided that construction or modification would be within or contiguous to a previously disturbed or developed area (where active utilities and currently used roads are readily accessible). Not included in this category are demonstration actions, meaning actions that are undertaken at a scale to show whether a technology would be viable on a larger scale and suitable for commercial deployment.

B3.7 New terrestrial infill exploratory and experimental wells

Siting, construction, and operation of new terrestrial infill exploratory and experimental (test) wells, for either extraction or injection use, in a locally characterized geological formation in a field that contains existing operating wells, properly abandoned wells, or unminable coal seams containing natural gas, provided that the site characterization has verified a low potential for seismicity, subsidence, and contamination of freshwater aquifers, and the actions are otherwise consistent with applicable best practices and DOE protocols, including those that protect against uncontrolled releases of harmful materials. Such wells may include those for brine, carbon dioxide, coalbed methane, gas hydrate, geothermal, natural gas, and oil. Uses for carbon sequestration wells include, but are not limited to, the study of saline formations, enhanced oil recovery, and enhanced coalbed methane extraction.

B3.8 Outdoor terrestrial ecological and environmental research

Outdoor terrestrial ecological and environmental research in a small area (generally less than 5 acres), including, but not limited to, siting, construction, and operation of a small-scale laboratory building or renovation of a room in an existing building for associated analysis. Such activities would be designed in conformance with applicable requirements and use best management practices to limit the potential effects of any resultant ground disturbance.

B3.9 Projects to reduce emissions and waste generation

Projects to reduce emissions and waste generation at existing fossil or alternative fuel combustion or utilization facilities, provided that these projects would not have the potential to cause a significant increase in the quantity or rate of air emissions. For this category of actions, “fuel” includes, but is not limited to, coal, oil, natural gas, hydrogen, syngas, and biomass; but “fuel” does not include nuclear fuel. Covered actions include, but are not limited to:

(a) Test treatment of the throughput product (solid, liquid, or gas) generated at an existing and fully operational fuel combustion or utilization facility;

(b) Addition or replacement of equipment for reduction or control of sulfur dioxide, oxides of nitrogen, or other regulated substances that requires only minor modification to the existing structures at an existing fuel combustion or utilization facility, for which the existing use remains essentially unchanged;

(c) Addition or replacement of equipment for reduction or control of sulfur dioxide, oxides of nitrogen, or other regulated substances that involves no permanent change in the quantity or quality of fuel burned or used and involves no permanent change in the capacity factor of the fuel combustion or utilization facility; and

(d) Addition or modification of equipment for capture and control of carbon dioxide or other regulated substances, provided that adequate infrastructure is in place to manage such substances.

B3.10 Particle accelerators

Siting, construction, modification, operation, and decommissioning of particle accelerators, including electron beam accelerators, with primary beam energy less than approximately 100 million electron volts (MeV) and average beam power less than approximately 250 kilowatts (kW), and associated beamlines, storage rings, colliders, and detectors, for research and medical purposes (such as proton therapy), and isotope production, within or contiguous to a previously disturbed or developed area (where active utilities and currently used roads are readily accessible), or internal modification of any accelerator facility regardless of energy, that does not increase primary beam energy or current. In cases where the beam energy exceeds 100 MeV, the average beam power must be less than 250 kW, so as not to exceed an average current of 2.5 milliamperes (mA).

B3.11 Outdoor tests and experiments on materials and equipment components

Outdoor tests and experiments for the development, quality assurance, or reliability of materials and equipment (including, but not limited to, weapon system components) under controlled conditions. Covered actions include, but are not limited to, burn tests (such as tests of electric cable fire resistance or the combustion characteristics of fuels), impact tests (such as pneumatic ejector tests using earthen embankments or concrete slabs designated and routinely used for that purpose), or drop, puncture, water-immersion, or thermal tests. Covered actions would not involve source, special nuclear, or byproduct materials, except encapsulated sources manufactured to applicable standards that contain source, special nuclear, or byproduct materials may be used for nondestructive actions such as detector/sensor development and testing and first responder field training.

B3.12 Microbiological and biomedical facilities

Siting, construction, modification, operation, and decommissioning of microbiological and biomedical diagnostic, treatment and research facilities (excluding Biosafety Level-3 and Biosafety Level-4), in accordance with applicable requirements and best practices (such as Biosafety in Microbiological and Biomedical Laboratories, 5th Edition, Dec. 2009, U.S. Department of Health and Human Services) including, but not limited to, laboratories, treatment areas, offices, and storage areas, within or contiguous to a previously disturbed or developed area (where active utilities and currently used roads are readily accessible). Operation may include the purchase, installation, and operation of biomedical equipment (such as commercially available cyclotrons that are used to generate radioisotopes and radiopharmaceuticals, and commercially available biomedical imaging and spectroscopy instrumentation).

B3.13 Magnetic fusion experiments

Performing magnetic fusion experiments that do not use tritium as fuel, within existing facilities (including, but not limited to, necessary modifications).

B3.14 Small-scale educational facilities

Siting, construction, modification, operation, and decommissioning of small-scale educational facilities (including, but not limited to, conventional teaching laboratories, libraries, classroom facilities, auditoriums, museums, visitor centers, exhibits, and associated offices) within or contiguous to a previously disturbed or developed area (where active utilities and currently used roads are readily accessible). Operation may include, but is not limited to, purchase, installation, and operation of equipment (such as audio/visual and laboratory equipment) commensurate with the educational purpose of the facility.

B3.15 Small-scale indoor research and development projects using nanoscale materials

Siting, construction, modification, operation, and decommissioning of facilities for indoor small-scale research and development projects and small-scale pilot projects using nanoscale materials in accordance with applicable requirements (such as engineering, worker safety, procedural, and administrative regulations) necessary to ensure the containment of any hazardous materials. Construction and modification activities would be within or contiguous to a previously disturbed or developed area (where active utilities and currently used roads are readily accessible).

B3.16 Research activities in aquatic environments

Small-scale, temporary surveying, site characterization, and research activities in aquatic environments, limited to:

(a) Acquisition of rights-of-way, easements, and temporary use permits;

(b) Installation, operation, and removal of passive scientific measurement devices, including, but not limited to, antennae, tide gauges, flow testing equipment for existing wells, weighted hydrophones, salinity measurement devices, and water quality measurement devices;

(c) Natural resource inventories, data and sample collection, environmental monitoring, and basic and applied research, excluding (1) large-scale vibratory coring techniques and (2) seismic activities other than passive techniques; and

(d) Surveying and mapping.

These activities would be conducted in accordance with, where applicable, an approved spill prevention, control, and response plan and would incorporate appropriate control technologies and best management practices. None of the activities listed above would occur within the boundary of an established marine sanctuary or wildlife refuge, a governmentally proposed marine sanctuary or wildlife refuge, or a governmentally recognized area of high biological sensitivity, unless authorized by the agency responsible for such refuge, sanctuary, or area (or after consultation with the responsible agency, if no authorization is required). If the proposed activities would occur outside such refuge, sanctuary, or area and if the activities would have the potential to cause impacts within such refuge, sanctuary, or area, then the responsible agency shall be consulted in order to determine whether authorization is required and whether such activities would have the potential to cause significant impacts on such refuge, sanctuary, or area. Areas of high biological sensitivity include, but are not limited to, areas of known ecological importance, whale and marine mammal mating and calving/pupping areas, and fish and invertebrate spawning and nursery areas recognized as being limited or unique and vulnerable to perturbation; these areas can occur in bays, estuaries, near shore, and far offshore, and may vary seasonally. No permanent facilities or devices would be constructed or installed. Covered actions do not include drilling of resource exploration or extraction wells.

B4. Categorical Exclusions Applicable to Electrical Power and Transmission B4.1 Contracts, policies, and marketing and allocation plans for electric power

Establishment and implementation of contracts, policies, and marketing and allocation plans related to electric power acquisition that involve only the use of the existing transmission system and existing generation resources operating within their normal operating limits.

B4.2 Export of electric energy

Export of electric energy as provided by Section 202(e) of the Federal Power Act over existing transmission systems or using transmission system changes that are themselves categorically excluded.

B4.3 Electric power marketing rate changes

Rate changes for electric power, power transmission, and other products or services provided by a Power Marketing Administration that are based on a change in revenue requirements if the operations of generation projects would remain within normal operating limits.

B4.4 Power Marketing Services and Activities

Power marketing services and power management activities (including, but not limited to, storage, load shaping and balancing, seasonal exchanges, and other similar activities), provided that the operations of generating projects would remain within normal operating limits. (See B4.14 of this appendix for energy storage systems.)

B4.5 Temporary adjustments to river operations

Temporary adjustments to river operations to accommodate day-to-day river fluctuations, power demand changes, fish and wildlife conservation program requirements, and other external events, provided that the adjustments would occur within the existing operating constraints of the particular hydrosystem operation.

B4.6 Additions and Modifications To Transmission Facilities

Additions or modifications to electric power transmission facilities within a previously disturbed or developed facility area. Covered activities include, but are not limited to, switchyard rock grounding upgrades, secondary containment projects, paving projects, seismic upgrading, tower modifications, load shaping projects (such as reducing energy use during periods of peak demand), changing insulators, and replacement of poles, circuit breakers, conductors, transformers, and crossarms. (See B4.14 of this appendix for energy storage systems.)

B4.7 Fiber optic cable

Adding fiber optic cables to transmission facilities or burying fiber optic cable in existing powerline or pipeline rights-of-way. Covered actions may include associated vaults and pulling and tensioning sites outside of rights-of-way in nearby previously disturbed or developed areas.

B4.8 Electricity transmission agreements

New electricity transmission agreements, and modifications to existing transmission arrangements, to use a transmission facility of one system to transfer power of and for another system, provided that no new generation projects would be involved and no physical changes in the transmission system would be made beyond the previously disturbed or developed facility area.

B4.9 Multiple use of powerline rights-of-way

Granting or denying requests for multiple uses of a transmission facility's rights-of-way (including, but not limited to, grazing permits and crossing agreements for electric lines, water lines, natural gas pipelines, communications cables, roads, and drainage culverts).

B4.10 Removal of electric transmission facilities

Deactivation, dismantling, and removal of electric transmission facilities (including, but not limited to, electric powerlines, substations, and switching stations) and abandonment and restoration of rights-of-way (including, but not limited to, associated access roads).

B4.11 Electric power substations and interconnection facilities

Construction or modification of electric power substations or interconnection facilities (including, but not limited to, switching stations and support facilities).

B4.12 Construction of powerlines

Construction of electric powerlines approximately 10 miles in length or less, or approximately 20 miles in length or less within previously disturbed or developed powerline or pipeline rights-of-way.

B4.13 Upgrading and Rebuilding Existing Powerlines

Upgrading or rebuilding existing electric powerlines, which may involve relocations of small segments of the powerlines within an existing powerline right-of-way or within otherwise previously disturbed or developed lands (as discussed at 10 CFR 1021.410(g)(1)). Upgrading or rebuilding existing electric powerlines also may involve widening an existing powerline right-of-way to meet current electrical standards if the widening remains within previously disturbed or developed lands and only extends into a small area beyond such lands as needed to comply with applicable electrical standards. Covered actions would be in accordance with applicable requirements, including the integral elements listed at the start of appendix B of this part; and would incorporate appropriate design and construction standards, control technologies, and best management practices. This categorical exclusion does not apply to underwater powerlines. As used in this categorical exclusion, “small” has the meaning discussed at 10 CFR 1021.410(g)(2).

B4.14 Construction and Operation of Electrochemical-Battery or Flywheel Energy Storage Systems

Construction, operation, upgrade, or decommissioning of an electrochemical-battery or flywheel energy storage system within a previously disturbed or developed area or within a small (as discussed at 10 CFR 1021.410(g)(2)) area contiguous to a previously disturbed or developed area. Covered actions would be in accordance with applicable requirements (such as land use and zoning requirements) in the proposed project area and the integral elements listed at the start of appendix B of this part, and would incorporate appropriate safety standards (including the current National Fire Protection Association 855, Standard for the Installation of Stationary Energy Storage Systems), design and construction standards, control technologies, and best management practices.

B5. Categorical Exclusions Applicable to Conservation, Fossil, and Renewable Energy Activities B5.1 Actions to conserve energy or water

(a) Actions to conserve energy or water, demonstrate potential energy or water conservation, and promote energy efficiency that would not have the potential to cause significant changes in the indoor or outdoor concentrations of potentially harmful substances. These actions may involve financial and technical assistance to individuals (such as builders, owners, consultants, manufacturers, and designers), organizations (such as utilities), and governments (such as state, local, and tribal). Covered actions include, but are not limited to weatherization (such as insulation and replacing windows and doors); programmed lowering of thermostat settings; placement of timers on hot water heaters; installation or replacement of energy efficient lighting, low-flow plumbing fixtures (such as faucets, toilets, and showerheads), heating, ventilation, and air conditioning systems, and appliances; installation of drip-irrigation systems; improvements in generator efficiency and appliance efficiency ratings; efficiency improvements for vehicles and transportation (such as fleet changeout); transportation management systems (such as traffic signal control systems, car navigation, speed cameras, and automatic plate number recognition); development of energy-efficient manufacturing, industrial, or building practices; and small-scale energy efficiency and conservation research and development and small-scale pilot projects. Covered actions include building renovations or new structures, provided that they occur in a previously disturbed or developed area. Covered actions could involve commercial, residential, agricultural, academic, institutional, or industrial sectors. Covered actions do not include rulemakings, standard-settings, or proposed DOE legislation, except for those actions listed in B5.1(b) of this appendix.

(b) Covered actions include rulemakings that establish energy conservation standards for consumer products and industrial equipment, provided that the actions would not: (1) Have the potential to cause a significant change in manufacturing infrastructure (such as construction of new manufacturing plants with considerable associated ground disturbance); (2) involve significant unresolved conflicts concerning alternative uses of available resources (such as rare or limited raw materials); (3) have the potential to result in a significant increase in the disposal of materials posing significant risks to human health and the environment (such as RCRA hazardous wastes); or (4) have the potential to cause a significant increase in energy consumption in a state or region.

B5.2 Modifications to pumps and piping

Modifications to existing pump and piping configurations (including, but not limited to, manifolds, metering systems, and other instrumentation on such configurations conveying materials such as air, brine, carbon dioxide, geothermal system fluids, hydrogen gas, natural gas, nitrogen gas, oil, produced water, steam, and water). Covered modifications would not have the potential to cause significant changes to design process flow rates or permitted air emissions.

B5.3 Modification or abandonment of wells

Modification (but not expansion) or plugging and abandonment of wells, provided that site characterization has verified a low potential for seismicity, subsidence, and contamination of freshwater aquifers, and the actions are otherwise consistent with best practices and DOE protocols, including those that protect against uncontrolled releases of harmful materials. Such wells may include, but are not limited to, storage and injection wells for brine, carbon dioxide, coalbed methane, gas hydrate, geothermal, natural gas, and oil. Covered modifications would not be part of site closure.

B5.4 Repair or replacement of pipelines

Repair, replacement, upgrading, rebuilding, or minor relocation of pipelines within existing rights-of-way, provided that the actions are in accordance with applicable requirements (such as Army Corps of Engineers permits under section 404 of the Clean Water Act). Pipelines may convey materials including, but not limited to, air, brine, carbon dioxide, geothermal system fluids, hydrogen gas, natural gas, nitrogen gas, oil, produced water, steam, and water.

B5.5 Short pipeline segments

Construction and subsequent operation of short (generally less than 20 miles in length) pipeline segments conveying materials (such as air, brine, carbon dioxide, geothermal system fluids, hydrogen gas, natural gas, nitrogen gas, oil, produced water, steam, and water) between existing source facilities and existing receiving facilities (such as facilities for use, reuse, transportation, storage, and refining), provided that the pipeline segments are within previously disturbed or developed rights-of-way.

B5.6 Oil spill cleanup

Removal of oil and contaminated materials recovered in oil spill cleanup operations and disposal of these materials in accordance with applicable requirements (such as the National Oil and Hazardous Substances Pollution Contingency Plan).

B5.7 Export of natural gas and associated transportation by marine vessel

Approvals or disapprovals of new authorizations or amendments of existing authorizations to export natural gas under section 3 of the Natural Gas Act and any associated transportation of natural gas by marine vessel.

B5.8 [Reserved] B5.9 Temporary exemptions for electric powerplants

Grants or denials of temporary exemptions under the Powerplant and Industrial Fuel Use Act of 1978, as amended, for electric powerplants.

B5.10 Certain permanent exemptions for existing electric powerplants

For existing electric powerplants, grants or denials of permanent exemptions under the Powerplant and Industrial Fuel Use Act of 1978, as amended, other than exemptions under section 312(c) relating to cogeneration and section 312(b) relating to certain state or local requirements.

B5.11 Permanent exemptions allowing mixed natural gas and petroleum

For new electric powerplants, grants or denials of permanent exemptions from the prohibitions of Title II of the Powerplant and Industrial Fuel Use Act of 1978, as amended, to permit the use of certain fuel mixtures containing natural gas or petroleum.

B5.12 Workover of existing wells

Workover (operations to restore production, such as deepening, plugging back, pulling and resetting lines, and squeeze cementing) of existing wells (including, but not limited to, activities associated with brine, carbon dioxide, coalbed methane, gas hydrate, geothermal, natural gas, and oil) to restore functionality, provided that workover operations are restricted to the existing wellpad and do not involve any new site preparation or earthwork that would have the potential to cause significant impacts on nearby habitat; that site characterization has verified a low potential for seismicity, subsidence, and contamination of freshwater aquifers; and the actions are otherwise consistent with best practices and DOE protocols, including those that protect against uncontrolled releases of harmful materials.

B5.13 Experimental wells for injection of small quantities of carbon dioxide

Siting, construction, operation, plugging, and abandonment of experimental wells for the injection of small quantities of carbon dioxide (and other incidentally co-captured gases) in locally characterized, geologically secure storage formations at or near existing carbon dioxide sources to determine the suitability of the formations for large-scale sequestration, provided that (1) The characterization has verified a low potential for seismicity, subsidence, and contamination of freshwater aquifers; (2) the wells are otherwise in accordance with applicable requirements, best practices, and DOE protocols, including those that protect against uncontrolled releases of harmful materials; and (3) the wells and associated drilling activities are sufficiently remote so that they would not have the potential to cause significant impacts related to noise and other vibrations. Wells may be used for enhanced oil or natural gas recovery or for secure storage of carbon dioxide in saline formations or other secure formations. Over the duration of a project, the wells would be used to inject, in aggregate, less than 500,000 tons of carbon dioxide into the geologic formation. Covered actions exclude activities in aquatic environments. (See B3.16 of this appendix for activities in aquatic environments.)

B5.14 Combined heat and power or cogeneration systems

Conversion to, replacement of, or modification of combined heat and power or cogeneration systems (the sequential or simultaneous production of multiple forms of energy, such as thermal and electrical energy, in a single integrated system) at existing facilities, provided that the conversion, replacement, or modification would not have the potential to cause a significant increase in the quantity or rate of air emissions and would not have the potential to cause significant impacts to water resources.

B5.15 Small-scale renewable energy research and development and pilot projects

Small-scale renewable energy research and development projects and small-scale pilot projects, provided that the projects are located within a previously disturbed or developed area. Covered actions would be in accordance with applicable requirements (such as local land use and zoning requirements) in the proposed project area and would incorporate appropriate control technologies and best management practices.

B5.16 Solar Photovoltaic Systems

(a) The installation, modification, operation, or decommissioning of commercially available solar photovoltaic systems:

(1) Located on a building or other structure (such as rooftop, parking lot or facility, or mounted to signage, lighting, gates, or fences); or

(2) Located within a previously disturbed or developed area.

(b) Covered actions would be in accordance with applicable requirements (such as land use and zoning requirements) in the proposed project area and the integral elements listed at the start of appendix B of this part, and would be consistent with applicable plans for the management of wildlife and habitat, including plans to maintain habitat connectivity, and incorporate appropriate control technologies and best management practices.

B5.17 Solar thermal systems

The installation, modification, operation, and removal of commercially available small-scale solar thermal systems (including, but not limited to, solar hot water systems) located on or contiguous to a building, and if located on land, generally comprising less than 10 acres within a previously disturbed or developed area. Covered actions would be in accordance with applicable requirements (such as local land use and zoning requirements) in the proposed project area and would incorporate appropriate control technologies and best management practices.

B5.18 Wind turbines

The installation, modification, operation, and removal of a small number (generally not more than 2) of commercially available wind turbines, with a total height generally less than 200 feet (measured from the ground to the maximum height of blade rotation) that (1) Are located within a previously disturbed or developed area; (2) are located more than 10 nautical miles (about 11.5 miles) from an airport or aviation navigation aid; (3) are located more than 1.5 nautical miles (about 1.7 miles) from National Weather Service or Federal Aviation Administration Doppler weather radar; (4) would not have the potential to cause significant impacts on bird or bat populations; and (5) are sited or designed such that the project would not have the potential to cause significant impacts to persons (such as from shadow flicker and other visual effects, and noise). Covered actions would be in accordance with applicable requirements (such as local land use and zoning requirements) in the proposed project area and would incorporate appropriate control technologies and best management practices. Covered actions include only those related to wind turbines to be installed on land.

B5.19 Ground source heat pumps

The installation, modification, operation, and removal of commercially available small-scale ground source heat pumps to support operations in single facilities (such as a school or community center) or contiguous facilities (such as an office complex) (1) Only where (a) major associated activities (such as drilling and discharge) are regulated, and (b) appropriate leakage and contaminant control measures would be in place (including for cross-contamination between aquifers); (2) that would not have the potential to cause significant changes in subsurface temperature; and (3) would be located within a previously disturbed or developed area. Covered actions would be in accordance with applicable requirements (such as local land use and zoning requirements) in the proposed project area and would incorporate appropriate control technologies and best management practices.

B5.20 Biomass power plants

The installation, modification, operation, and removal of small-scale biomass power plants (generally less than 10 megawatts), using commercially available technology (1) Intended primarily to support operations in single facilities (such as a school and community center) or contiguous facilities (such as an office complex); (2) that would not affect the air quality attainment status of the area and would not have the potential to cause a significant increase in the quantity or rate of air emissions and would not have the potential to cause significant impacts to water resources; and (3) would be located within a previously disturbed or developed area. Covered actions would be in accordance with applicable requirements (such as local land use and zoning requirements) in the proposed project area and would incorporate appropriate control technologies and best management practices.

B5.21 Methane gas recovery and utilization systems

The installation, modification, operation, and removal of commercially available methane gas recovery and utilization systems installed within a previously disturbed or developed area on or contiguous to an existing landfill or wastewater treatment plant that would not have the potential to cause a significant increase in the quantity or rate of air emissions. Covered actions would be in accordance with applicable requirements (such as local land use and zoning requirements) in the proposed project area and would incorporate appropriate control technologies and best management practices.

B5.22 Alternative fuel vehicle fueling stations

The installation, modification, operation, and removal of alternative fuel vehicle fueling stations (such as for compressed natural gas, hydrogen, ethanol and other commercially available biofuels) on the site of a current or former fueling station, or within a previously disturbed or developed area within the boundaries of a facility managed by the owners of a vehicle fleet. Covered actions would be in accordance with applicable requirements (such as local land use and zoning requirements) in the proposed project area and would incorporate appropriate control technologies and best management practices.

B5.23 Electric vehicle charging stations

The installation, modification, operation, and removal of electric vehicle charging stations, using commercially available technology, within a previously disturbed or developed area. Covered actions are limited to areas where access and parking are in accordance with applicable requirements (such as local land use and zoning requirements) in the proposed project area and would incorporate appropriate control technologies and best management practices.

B5.24 Drop-in hydroelectric systems

The installation, modification, operation, and removal of commercially available small-scale, drop-in, run-of-the-river hydroelectric systems that would (1) Involve no water storage or water diversion from the stream or river channel where the system is installed and (2) not have the potential to cause significant impacts on water quality, temperature, flow, or volume. Covered systems would be located up-gradient of an existing anadromous fish barrier that is not planned for removal and where fish passage retrofit is not planned and where there would not be the potential for significant impacts to threatened or endangered species or other species of concern (as identified in B(4)(ii) of this appendix). Covered actions would involve no major construction or modification of stream or river channels, and the hydroelectric systems would be placed and secured in the channel without the use of heavy equipment. Covered actions would be in accordance with applicable requirements (such as local land use and zoning requirements) in the proposed project area and would incorporate appropriate control technologies and best management practices.

B5.25 Small-scale renewable energy research and development and pilot projects in aquatic environments

Small-scale renewable energy research and development projects and small-scale pilot projects located in aquatic environments. Activities would be in accordance with, where applicable, an approved spill prevention, control, and response plan, and would incorporate appropriate control technologies and best management practices. Covered actions would not occur (1) Within areas of hazardous natural bottom conditions or (2) within the boundary of an established marine sanctuary or wildlife refuge, a governmentally proposed marine sanctuary or wildlife refuge, or a governmentally recognized area of high biological sensitivity, unless authorized by the agency responsible for such refuge, sanctuary, or area (or after consultation with the responsible agency, if no authorization is required). If the proposed activities would occur outside such refuge, sanctuary, or area and if the activities would have the potential to cause impacts within such refuge, sanctuary, or area, then the responsible agency shall be consulted in order to determine whether authorization is required and whether such activities would have the potential to cause significant impacts on such refuge, sanctuary, or area. Areas of high biological sensitivity include, but are not limited to, areas of known ecological importance, whale and marine mammal mating and calving/pupping areas, and fish and invertebrate spawning and nursery areas recognized as being limited or unique and vulnerable to perturbation; these areas can occur in bays, estuaries, near shore, and far offshore, and may vary seasonally. No permanent facilities or devices would be constructed or installed. Covered actions do not include drilling of resource exploration or extraction wells, use of large-scale vibratory coring techniques, or seismic activities other than passive techniques.

B6. Categorical Exclusions Applicable to Environmental Restoration and Waste Management Activities B6.1 Cleanup actions

Small-scale, short-term cleanup actions, under RCRA, Atomic Energy Act, or other authorities, less than approximately 10 million dollars in cost (in 2011 dollars), to reduce risk to human health or the environment from the release or threat of release of a hazardous substance other than high-level radioactive waste and spent nuclear fuel, including treatment (such as incineration, encapsulation, physical or chemical separation, and compaction), recovery, storage, or disposal of wastes at existing facilities currently handling the type of waste involved in the action. These actions include, but are not limited to:

(a) Excavation or consolidation of contaminated soils or materials from drainage channels, retention basins, ponds, and spill areas that are not receiving contaminated surface water or wastewater, if surface water or groundwater would not collect and if such actions would reduce the spread of, or direct contact with, the contamination;

(b) Removal of bulk containers (such as drums and barrels) that contain or may contain hazardous substances, pollutants, contaminants, CERCLA-excluded petroleum or natural gas products, or hazardous wastes (designated in 40 CFR part 261 or applicable state requirements), if such actions would reduce the likelihood of spillage, leakage, fire, explosion, or exposure to humans, animals, or the food chain;

(c) Removal of an underground storage tank including its associated piping and underlying containment systems in accordance with applicable requirements (such as RCRA, subtitle I; 40 CFR part 265, subpart J; and 40 CFR part 280, subparts F and G) if such action would reduce the likelihood of spillage, leakage, or the spread of, or direct contact with, contamination;

(d) Repair or replacement of leaking containers;

(e) Capping or other containment of contaminated soils or sludges if the capping or containment would not unduly limit future groundwater remediation and if needed to reduce migration of hazardous substances, pollutants, contaminants, or CERCLA-excluded petroleum and natural gas products into soil, groundwater, surface water, or air;

(f) Drainage or closing of man-made surface impoundments if needed to maintain the integrity of the structures;

(g) Confinement or perimeter protection using dikes, trenches, ditches, or diversions, or installing underground barriers, if needed to reduce the spread of, or direct contact with, the contamination;

(h) Stabilization, but not expansion, of berms, dikes, impoundments, or caps if needed to maintain integrity of the structures;

(i) Drainage controls (such as run-off or run-on diversion) if needed to reduce offsite migration of hazardous substances, pollutants, contaminants, or CERCLA-excluded petroleum or natural gas products or to prevent precipitation or run-off from other sources from entering the release area from other areas;

(j) Segregation of wastes that may react with one another or form a mixture that could result in adverse environmental impacts;

(k) Use of chemicals and other materials to neutralize the pH of wastes;

(l) Use of chemicals and other materials to retard the spread of the release or to mitigate its effects if the use of such chemicals would reduce the spread of, or direct contact with, the contamination;

(m) Installation and operation of gas ventilation systems in soil to remove methane or petroleum vapors without any toxic or radioactive co-contaminants if appropriate filtration or gas treatment is in place;

(n) Installation of fences, warning signs, or other security or site control precautions if humans or animals have access to the release; and

(o) Provision of an alternative water supply that would not create new water sources if necessary immediately to reduce exposure to contaminated household or industrial use water and continuing until such time as local authorities can satisfy the need for a permanent remedy.

B6.2 Waste collection, treatment, stabilization, and containment facilities

The siting, construction, and operation of temporary (generally less than 2 years) pilot-scale waste collection and treatment facilities, and pilot-scale (generally less than 1 acre) waste stabilization and containment facilities (including siting, construction, and operation of a small-scale laboratory building or renovation of a room in an existing building for sample analysis), provided that the action (1) Supports remedial investigations/feasibility studies under CERCLA, or similar studies under RCRA (such as RCRA facility investigations/corrective measure studies) or other authorities and (2) would not unduly limit the choice of reasonable remedial alternatives (such as by permanently altering substantial site area or by committing large amounts of funds relative to the scope of the remedial alternatives).

B6.3 Improvements to environmental control systems

Improvements to environmental monitoring and control systems of an existing building or structure (such as changes to scrubbers in air quality control systems or ion-exchange devices and other filtration processes in water treatment systems), provided that during subsequent operations (1) Any substance collected by the environmental control systems would be recycled, released, or disposed of within existing permitted facilities and (2) there are applicable statutory or regulatory requirements or permit conditions for disposal, release, or recycling of any hazardous substance or CERCLA-excluded petroleum or natural gas products that are collected or released in increased quantity or that were not previously collected or released.

B6.4 Facilities for storing packaged hazardous waste for 90 days or less

Siting, construction, modification, expansion, operation, and decommissioning of an onsite facility for storing packaged hazardous waste (as designated in 40 CFR part 261) for 90 days or less or for longer periods as provided in 40 CFR 262.34(d), (e), or (f) (such as accumulation or satellite areas).

B6.5 Facilities for characterizing and sorting packaged waste and overpacking waste

Siting, construction, modification, expansion, operation, and decommissioning of an onsite facility for characterizing and sorting previously packaged waste or for overpacking waste, other than high-level radioactive waste, provided that operations do not involve unpacking waste. These actions do not include waste storage (covered under B6.4, B6.6, B6.10 of this appendix, and C16 of appendix C) or the handling of spent nuclear fuel.

B6.6 Modification of facilities for storing, packaging, and repacking waste

Modification (excluding increases in capacity) of an existing structure used for storing, packaging, or repacking waste other than high-level radioactive waste or spent nuclear fuel, to handle the same class of waste as currently handled at that structure.

B6.7 [Reserved] B6.8 Modifications for waste minimization and reuse of materials

Minor operational changes at an existing facility to minimize waste generation and for reuse of materials. These changes include, but are not limited to, adding filtration and recycle piping to allow reuse of machining oil, setting up a sorting area to improve process efficiency, and segregating two waste streams previously mingled and assigning new identification codes to the two resulting wastes.

B6.9 Measures to reduce migration of contaminated groundwater

Small-scale temporary measures to reduce migration of contaminated groundwater, including the siting, construction, operation, and decommissioning of necessary facilities. These measures include, but are not limited to, pumping, treating, storing, and reinjecting water, by mobile units or facilities that are built and then removed at the end of the action.

B6.10 Upgraded or replacement waste storage facilities

Siting, construction, modification, expansion, operation, and decommissioning of a small upgraded or replacement facility (less than approximately 50,000 square feet in area) within or contiguous to a previously disturbed or developed area (where active utilities and currently used roads are readily accessible) for storage of waste that is already at the site at the time the storage capacity is to be provided. These actions do not include the storage of high-level radioactive waste, spent nuclear fuel or any waste that requires special precautions to prevent nuclear criticality. (See also B6.4, B6.5, B6.6 of this appendix, and C16 of appendix C.)

B7. Categorical Exclusions Applicable to International Activities B7.1 Emergency measures under the International Energy Program

Planning and implementation of emergency measures pursuant to the International Energy Program.

B7.2 Import and export of special nuclear or isotopic materials

Approval of import or export of small quantities of special nuclear materials or isotopic materials in accordance with applicable requirements (such as the Nuclear Non-Proliferation Act of 1978 and the “Procedures Established Pursuant to the Nuclear Non-Proliferation Act of 1978” (43 FR 25326, June 9, 1978)).

[57 FR 15144, Apr. 24, 1992, as amended at 85 FR 78205, Dec. 4, 2020; 89 FR 34093, Apr. 30, 2024; 89 FR 45564, May 23, 2024]
Appendix Appendix C - Appendix C to Subpart D of Part 1021—Classes of Actions that Normally Require EAs but not Necessarily EISs
Table of Contents C1 [Reserved] C2 [Reserved] C3 Electric Power Marketing Rate Changes, Not Within Normal Operating Limits C4 Upgrading, Rebuilding, or Construction of Powerlines C5 Vegetation Management Program C6 Erosion Control Program C7 Contracts, Policies, and Marketing and Allocation Plans for Electric Power C8 Protection of Cultural Resources and Fish and Wildlife Habitat C9 Wetlands Demonstration Projects C10 [Reserved] C11 Particle Acceleration Facilities C12 Energy System Demonstration Actions C13 [Reserved] C14 Water Treatment Facilities C15 Research and Development Incinerators and Nonhazardous Waste Incinerators C16 Large Waste Packaging and Storage Facilities C1 [Reserved] C2 [Reserved] C3 Electric Power Marketing Rate Changes, Not Within Normal Operating Limits

Rate changes for electric power, power transmission, and other products or services provided by Power Marketing Administrations that are based on changes in revenue requirements if the operations of generation projects would not remain within normal operating limits.

C4 Upgrading, Rebuilding, or Construction of Powerlines

(a) Upgrading or rebuilding existing powerlines when the action does not qualify for categorical exclusion B4.13; or construction of powerlines:

(1) More than approximately 10 miles in length outside previously disturbed or developed powerline or pipeline rights-of-way; or

(2) more than approximately 20 miles in length within previously disturbed or developed powerline or pipeline rights-of-way.

C5 Vegetation Management Program

Implementation of a Power Marketing Administration system-wide vegetation management program.

C6 Erosion Control Program

Implementation of a Power Marketing Administration system-wide erosion control program.

C7 Contracts, Policies, and Marketing and Allocation Plans for Electric Power

(a) Establishment and implementation of contracts, policies, and marketing and allocation plans related to electric power acquisition that involve:

(1) The interconnection of, or acquisition of power from, new generation resources that are equal to or less than 50 average megawatts, unless the generation resource is eligible for a categorical exclusion;

(2) Changes in the normal operating limits of generation resources equal to or less than 50 average megawatts; or

(3) Service to discrete new loads of less than 10 average megawatts over a 12-month period.

C8 Protection of Cultural Resources and Fish and Wildlife Habitat

Large-scale activities undertaken to protect cultural resources (such as fencing, labeling, and flagging) or to protect, restore, or improve fish and wildlife habitat, fish passage facilities (such as fish ladders and minor diversion channels), or fisheries.

C9 Wetlands Demonstration Projects

Field demonstration projects for wetlands mitigation, creation, and restoration.

C10 [Reserved] C11 Particle Acceleration Facilities

Siting, construction or modification, operation, and decommissioning of low- or medium-energy (when the primary beam energy exceeds approximately 100 million electron volts and the average beam power exceeds approximately 250 kilowatts or where the average current exceeds 2.5 milliamperes) particle acceleration facilities, including electron beam acceleration facilities, and associated beamlines, storage rings, colliders, and detectors for research and medical purposes, within or contiguous to a previously disturbed or developed area (where active utilities and currently used roads are readily accessible).

C12 Energy System Demonstration Actions

Siting, construction, operation, and decommissioning of energy system demonstration actions (including, but not limited to, wind resource, hydropower, geothermal, fossil fuel, biomass, and solar energy, but excluding nuclear). For purposes of this category, “demonstration actions” means actions that are undertaken at a scale to show whether a technology would be viable on a larger scale and suitable for commercial deployment.

C13 [Reserved] C14 Water Treatment Facilities

Siting, construction (or expansion), operation, and decommissioning of wastewater, surface water, potable water, and sewage treatment facilities with a total capacity greater than approximately 250,000 gallons per day, and of lower capacity wastewater and surface water treatment facilities whose liquid discharges are not subject to external regulation.

C15 Research and Development Incinerators and Nonhazardous Waste Incinerators

Siting, construction (or expansion), operation, and decommissioning of research and development incinerators for any type of waste and of any other incinerators that would treat nonhazardous solid waste (as designated in 40 CFR 261.4(b)).

C16 Large Waste Packaging and Storage Facilities

Siting, construction, modification to increase capacity, operation, and decommissioning of packaging and unpacking facilities (such as characterization operations) and large storage facilities (greater than approximately 50,000 square feet in area) for waste, except high-level radioactive waste, generated onsite or resulting from activities connected to site operations. These actions do not include storage, packaging, or unpacking of spent nuclear fuel. (See also B6.4, B6.5, B6.6, and B6.10 of appendix B.)

[57 FR 15144, Apr. 24, 1992, as amended at 85 FR 78205, Dec. 4, 2020; 89 FR 34094, Apr. 30, 2024]
Appendix Appendix D - Appendix D to Subpart D of Part 1021—Classes of Actions that Normally Require EISs
Table of Contents D1 [Reserved] D2 Nuclear fuel reprocessing facilities D3 Uranium enrichment facilities D4 Reactors D5 [Reserved] D6 [Reserved] D7 Contracts, policies, and marketing and allocation plans for electric power D8 [Reserved] D9 [Reserved] D10 Treatment, storage, and disposal facilities for high-level waste and spent nuclear fuel D11 Waste disposal facilities for transuranic waste D12 Incinerators D1 [Reserved] D2 Nuclear Fuel Reprocessing Facilities

Siting, construction, operation, and decommissioning of nuclear fuel reprocessing facilities.

D3 Uranium Enrichment Facilities

Siting, construction, operation, and decommissioning of uranium enrichment facilities.

D4 Reactors

Siting, construction, operation, and decommissioning of power reactors, nuclear material production reactors, and test and research reactors.

D5 [Reserved] D6 [Reserved] D7 Contracts, Policies, and Marketing and Allocation Plans for Electric Power

(a) Establishment and implementation of contracts, policies, and marketing and allocation plans related to electric power acquisition that involve:

(1) The interconnection of, or acquisition of power from, new generation resources greater than 50 average megawatts, unless the generation resource is eligible for a categorical exclusion or was evaluated in an environmental assessment resulting in a finding of no significant impact;

(2) Changes in the normal operating limits of generation resources greater than 50 average megawatts; or

(3) Service to discrete new loads of 10 average megawatts or more over a 12-month period.

D8 [Reserved] D9 [Reserved] D10 Treatment, Storage, and Disposal Facilities for High-Level Waste and Spent Nuclear Fuel

Siting, construction, operation, and decommissioning of major treatment, storage, and disposal facilities for high-level waste and spent nuclear fuel, including geologic repositories, but not including onsite replacement or upgrades of storage facilities for spent nuclear fuel at DOE sites where such replacement or upgrade would not result in increased storage capacity.

D11 Waste Disposal Facilities for Transuranic Waste

Siting, construction or expansion, and operation of disposal facilities for transuranic (TRU) waste and TRU mixed waste (TRU waste also containing hazardous waste as designated in 40 CFR part 261).

D12 Incinerators

Siting, construction, and operation of incinerators, other than research and development incinerators or incinerators for nonhazardous solid waste (as designated in 40 CFR 261.4(b)).

[57 FR 15144, Apr. 24, 1992, as amended at 85 FR 78205, Dec. 4, 2020; 89 FR 34094, Apr. 30, 2024]
authority: 42 U.S.C. 7101
source: 57 FR 15144, Apr. 24, 1992, unless otherwise noted.
cite as: 10 CFR 1021.410