1. Name of applicant (indicate whether individual, corporation or municipality).
2. Address.
3. Name, title, mailing address, and telephone number of person to be contacted concerning the application.
4. Name of natural gas company from whom service is desired.
5. Are you now rendering gas service? If so, briefly describe operations.
6. Nature of service sought, giving a brief description of proposal, including location of community, population, number of residences and kind of service sought and to be rendered, showing:
(a) Is this an initial connection with the pipe line, or is it an extension or improvement of existing facilities?
(b) Estimate of maximum day requirements for residential, commercial and industrial customers for each of the first three years of proposed operations (Mcf at 14.73 psia), and how the estimates were derived;
(c) Estimate of annual requirements for residential, commercial and industrial customers for each of the first three years of proposed operations (Mcf at 14.73 psia), and how the estimates were derived.
7. Do you have or do you need a franchise to render the proposed service? If you have filed an application for such a franchise, with whom was it filed and what action has been taken on it?
8. Do you have or do you need a state certificate approving the proposed distribution system project? If you have filed an application for such a certificate, with whom was it filed and what action has been taken on it?
9. When do you propose to start construction and when do you estimate it will be completed? When do you propose to start selling gas?
10. How much are the facilities expected to cost? Show separately the estimated cost of the distribution system, the connecting supply lines, legal fees, financing fees and engineering fees, and briefly state how the estimates were derived.
11. Have you used the services of an engineering consultant? If so, the consultant should state his experience in the design of distribution systems, cost data of systems now in service compared with his initial estimates, and the actual rate at which new customers were attached in the new distribution systems.
12. How do you propose to finance the proposed facilities? Submit evidence that the money will be available. (This evidence need not be submitted if you have a state certificate for your project.)
13. For each of the first three years of operation of the proposed facilities, show (a) the estimated gross annual revenues for the natural gas estimated to be sold to residential, commercial and industrial customers as shown in item 6(c) and the rates you propose to charge, and (b) the cost of gas purchased by you (state the rate to be paid to the pipeline supplier and the pipeline's rate schedule under which you will purchase said gas), other operating and maintenance expenses and operating revenue deductions, and (c) the net operating revenues. If you have received a certificate of public convenience and necessity issued by a local regulatory commission, it may be submitted in lieu of this requirement.
14. Municipalities should submit a bond amortization and interest schedule for the life of the bond issue related to the project and computation of the average debt service coverage ratio over the life of the issue. State briefly how all estimates were derived. Exhibits to be furnished:
Exhibit A. A geographical map showing clearly all of the transmission facilities proposed to be installed and operated by you between your distribution system and the transmission pipeline system of the proposed supplier, including:
(a) Location, length and size of your transmission lines;
(b) Location and size (related horsepower) of your transmission compressor stations (if any);
(c) Location and designation of each point of connection of your proposed transmission facilities with proposed pipeline supplier;
(d) And if known, location, length and size of facilities to be installed by the proposed supplier.
Exhibit B. A flow diagram showing the maximum daily capacity of the proposed connecting pipeline to carry gas from the supplier to the community to be served. The diagram should show expected operating pressures on the connecting pipeline at the point of connection with the supplier and at the other terminal of the connecting pipeline flow of gas through the connecting pipeline in Mcf per day; length of the connecting pipeline and its inside and outside diameter.