Regulations last checked for updates: Nov 26, 2024

Title 18 - Conservation of Power and Water Resources last revised: Nov 22, 2024
§ 4.20 - Initial statement.

(a) Notification of Commission. In all cases where licenses are issued for projects already constructed, but which are not subject to the provisions of section 23(a) of the Act (49 Stat. 846; 16 U.S.C. 816), the licensee shall, within 6 months after the date of issuance of license, file with the Commission a letter, in quadruplicate.

(b) Contents of letter. The letter referred to in paragraph (a) of this section shall contain a statement to the effect that an inventory in detail of all property included under the license, as of the effective date of such license, has been completed. The letter shall also include a statement to the effect that actual legitimate original cost, or if not known, the estimated original cost, and accrued depreciation of the property, classified by prime accounts as prescribed in the Commission's Uniform System of Accounts, have been established.

(c) Licensee's books. The licensee's books of account for each project shall be maintained in such a fashion that each year's additions, betterments, and deletions to the project may be readily ascertained.

(d) Availability of information to the public. The information made available to the Commission in accordance with this section must be available for inspection and copying by the public when specifically requested.

(e) Compliance with the Act. Compliance with the provisions of this section satisfies the filing requirements of section 4(b) of the Federal Power Act (16 U.S.C. 797(b)).

[Order 53, 44 FR 61949, Oct. 29, 1979]
§ 4.21 - Reports.

Representatives of the Commission will inspect the project works, engineering reports, and other records of the project, check the inventory and estimated depreciation, make an audit of the books, records, and accounts of the licensee relating to the property under license, and prepare a report of their findings with respect to the inventory, the original cost of the property, and the estimated accrued depreciation thereon.

§ 4.22 - Service of report.

Copies of such report will be served upon said licensees, and copies will also be sent to the State public service commission, or if the State has no regulatory agency, to the Governor of the State where such project is located, and to such other parties as the Commission shall prescribe, and the report will be made available for public inspection at the time of service upon the licensee.

(Administrative Procedure Act, 5 U.S.C. 551-557 (1976); Federal Power Act, as amended, 16 U.S.C. 291-628 (1976 & Supp. V 1981), Dept. of Energy Organization Act 42 U.S.C. 7101-7352 (Supp. V 1981); E.O. 12009, 3 CFR 142 (1978)) [Order 141, 12 FR 8485, Dec. 19, 1947, as amended by Order 344, 48 FR 49010, Oct. 24, 1983; Order 737, 75 FR 43402, July 26, 2010]
§ 4.23 - Time for filing protest.

Thirty days after service thereof will be allowed to such licensee within which to file a protest to such reports. If no protest is filed within the time allowed, the Commission will issue such order as may be appropriate. If a protest is filed, a public hearing will be ordered in accordance with subpart E of part 385 of this chapter.

[Order 141, 12 FR 8485, Dec. 19, 1947, as amended by Order 225, 47 FR 19056, May 3, 1982]
§ 4.24 - Determination of cost.

The Commission, after receipt of the reports, or after the conclusion of the hearing if one is held, will determine the amounts to be included in the electric plant accounts of the licensee as the cost of the property and the accrued depreciation thereon.

§ 4.25 - Findings.

(a) Commission determination. Final action by the Commission will be in the form of an order served upon all parties to the proceeding. One copy of the order shall be furnished to the Secretary of Treasury by the Commission.

(b) Adjustment to licensee's books. The licensee's books of account for the project shall be adjusted to conform to the actual legitimate cost as revised by the order of the Commission. These adjustments and the project may be audited by Commission representatives, as scheduled.

[Order 53, 44 FR 61949, Oct. 29, 1979]
source: Order 141, 12 FR 8485, Dec. 19, 1947, unless otherwise noted.
cite as: 18 CFR 4.22