Regulations last checked for updates: Nov 25, 2024

Title 30 - Mineral Resources last revised: Nov 19, 2024
§ 582.0 - Authority for information collection.

The information collection requirements in this part have been approved by the Office of Management and Budget under 44 U.S.C. 3507 and assigned clearance number 1010-0081. The information is being collected to inform the Bureau of Ocean Energy Management (BOEM) of general mining operations in the Outer Continental Shelf (OCS). The information will be used to ensure that operations are conducted in a safe and environmentally responsible manner in compliance with governing laws and regulations. The requirement to respond is mandatory.

§ 582.1 - Purpose and authority.

(a) The Act authorizes the Secretary to prescribe such rules and regulations as may be necessary to carry out the provisions of the Act (43 U.S.C. 1334). The Secretary is authorized to prescribe and amend regulations that the Secretary determines to be necessary and proper in order to provide for the prevention of waste, conservation of the natural resources of the OCS, and the protection of correlative rights therein. In the enforcement of safety, environmental, and conservation laws and regulations, the Secretary is authorized to cooperate with adjacent States and other Departments and Agencies of the Federal Government.

(b) Subject to the supervisory authority of the Secretary, and unless otherwise specified, the regulations in this part shall be administered by the Director of BOEM.

§ 582.2 - Scope.

The rules and regulations in this part apply as of their effective date to all operations conducted under a mineral lease for OCS minerals other than oil, gas, or sulphur issued under the provisions of section 8(k) of the Act.

§ 582.3 - Definitions.

When used in this part, the following terms shall have the meaning given below:

Act means the OCS Lands Act, as amended (43 U.S.C. 1331 et seq.).

Adjacent State means with respect to any activity proposed, conducted, or approved under this part, any coastal State:

(1) That is, or is proposed to be, receiving for processing, refining, or transshipment OCS mineral resources commercially recovered from the seabed;

(2) That is used, or is scheduled to be used, as a support base for prospecting, exploration, testing, or mining activities; or

(3) In which there is a reasonable probability of significant effect on land or water uses from such activity.

Contingency Plan means a plan for action to be taken in emergency situations.

Data means geological and geophysical (G&G) facts and statistics or samples which have not been analyzed, processed, or interpreted.

Development means those activities which take place following the discovery of minerals in paying quantities including geophysical activities, drilling, construction of offshore facilities, and operation of all onshore support facilities, which are for the purpose of ultimately producing the minerals discovered.

Director means the Director of BOEM of the U.S. Department of the Interior or an official authorized to act on the Director's behalf.

Exploration means the process of searching for minerals on a lease including:

(1) Geophysical surveys where magnetic, gravity, seismic, or other systems are used to detect or imply the presence of minerals;

(2) Any drilling including the drilling of a borehole in which the discovery of a mineral other than oil, gas, or sulphur is made and the drilling of any additional boreholes needed to delineate any mineral deposits; and

(3) The taking of sample portions of a mineral deposit to enable the lessee to determine whether to proceed with development and production.

Geological sample means a collected portion of the seabed, the subseabed, or the overlying waters (when obtained for geochemical analysis) acquired while conducting postlease mining activities.

Governor means the Governor of a State or the person or entity designated by, or pursuant to, State law to exercise the power granted to a Governor.

Information means G&G data that have been analyzed, processed, or interpreted.

Lease means one of the following, whichever is required by the context: Any form of authorization which is issued under section 8 or maintained under section 6 of the Acts and which authorizes exploration for, and development and production of, specific minerals; or the area covered by that authorization.

Lessee means the person authorized by a lease, or an approved assignment thereof, to explore for and develop and produce the leased deposits in accordance with the regulations in this chapter. The term includes all parties holding that authority by or through the lessee.

Major Federal action means any action or proposal by the Secretary which is subject to the provisions of section 102(2)(C) of the National Environmental Policy Act (NEPA) (i.e., an action which will have a significant impact on the quality of the human environment requiring preparation of an Environmental Impact Statement (EIS) pursuant to section 102(2)(C) of NEPA).

Marine environment means the physical, atmospheric, and biological components, conditions, and factors which interactively determine the productivity, state, condition, and quality of the marine ecosystem, including the waters of the high seas, the contiguous zone, transitional and intertidal areas, salt marshes, and wetlands within the coastal zone and on the OCS.

Minerals include oil, gas, sulphur, geopressured-geothermal and associated resources, and all other minerals which are authorized by an Act of Congress to be produced from “public lands” as defined in section 103 of the Federal Land Policy and Management Act of 1976.

OCS mineral means any mineral deposit or accretion found on or below the surface of the seabed but does not include oil, gas, or sulphur; salt or sand and gravel intended for use in association with the development of oil, gas, or sulphur; or source materials essential to production of fissionable materials which are reserved to the United States pursuant to section 12(e) of the Act.

Operator means the individual, partnership, firm, or corporation having control or management of operations on the lease or a portion thereof. The operator may be a lessee, designated agent of the lessee, or holder of rights under an approved operating agreement.

Outer Continental Shelf means all submerged lands lying seaward and outside of the area of lands beneath navigable waters as defined in section 2 of Submerged Lands Act (43 U.S.C. 1301) and of which the subsoil and seabed appertain to the United States and are subject to its jurisdiction and control.

Person means a citizen or national of the United States; an alien lawfully admitted for permanent residency in the United States as defined in 8 U.S.C. 1101(a)(20); a private, public, or municipal corporation organized under the laws of the United States or of any State or territory thereof; an association of such citizens, nationals, resident aliens or private, public, or municipal corporations, States, or political subdivisions of States; or anyone operating in a manner provided for by treaty or other applicable international agreements. The term does not include Federal Agencies.

Secretary means the Secretary of the Interior or an official authorized to act on the Secretary's behalf.

Testing means removing bulk samples for processing tests and feasibility studies and/or the testing of mining equipment to obtain information needed to develop a detailed Mining Plan.

§ 582.4 - Opportunities for review and comment.

(a) In carrying out BOEM's responsibilities under the Act and regulations in this part, the Director shall provide opportunities for Governors of adjacent States, State/Federal task forces, lessees and operators, other Federal Agencies, and other interested parties to review proposed activities described in a Delineation, Testing, or Mining Plan together with an analysis of potential impacts on the environment and to provide comments and recommendations for the disposition of the proposed plan.

(b)(1) For Delineation Plans, the adjacent State Governor(s) shall be notified by the Director within 15 days following the submission of a request for approval of a Delineation Plan. Notification shall include a copy of the proposed Delineation Plan and the accompanying environmental information. The adjacent State Governor(s) who wishes to comment on a proposed Delineation Plan may do so within 30 days of the receipt of the proposed plan and the accompanying information.

(2) In cases where an Environmental Assessment is to be prepared, the Director's invitation to provide comments may allow the adjacent State Governor(s) more than 30 days following receipt of the proposed plan to provide comments.

(3) The Director shall notify Federal Agencies, as appropriate, with a copy of the proposed Delineation Plan and the accompanying environmental information within 15 days following the submission of the request. Agencies that wish to comment on a proposed Delineation Plan shall do so within 30 days following receipt of the plan and the accompanying information.

(c)(1) For Testing Plans, the adjacent State Governor(s) shall be notified by the Director within 20 days following submission of a request for approval of a proposed Testing Plan. Notification shall include a copy of the proposed Testing Plan and the accompanying environmental information. The adjacent State Governor(s) who wishes to comment on a proposed Testing Plan may do so within 60 days of the receipt of a plan and the accompanying information.

(2) In cases where an EIS is to be prepared, the Director's invitation to provide comments may allow the adjacent State Governor(s) more than 60 days following receipt of the proposed plan to provide comments.

(3) The Director shall notify Federal Agencies, as appropriate, with a copy of the proposed Testing Plan and the accompanying environmental information within 20 days following the submission of the request. Agencies that wish to comment on a proposed Testing Plan shall do so within 60 days following receipt of the plan and the accompanying information.

(d)(1) For Mining Plans, the adjacent State Governor(s) shall be notified by the Director within 20 days following the submission of a request for approval of a proposed Mining Plan. Notification shall include a copy of the proposed Mining Plan and the accompanying environmental information. The adjacent State Governor(s) who wishes to comment on a proposed Mining Plan may do so within 60 days of the receipt of a plan and the accompanying information.

(2) In cases where an EIS is to be prepared, the Director's invitation to provide comments may allow the adjacent State Governor(s) more than 60 days following receipt of the proposed plan to provide comments.

(3) The Director shall notify Federal Agencies, as appropriate, with a copy of the proposed Mining Plan and the accompanying environmental information within 20 days following the submission of the request. Agencies that wish to comment on a proposed Mining Plan shall do so within 60 days following receipt of the plan and the accompanying information.

(e) When an adjacent State Governor(s) has provided comments pursuant to paragraphs (b), (c), and (d) of this section, the Governor(s) shall be given, in writing, a list of recommendations which are adopted and the reasons for rejecting any of the recommendations of the Governor(s) or for implementing any alternative means identified during consultations with the Governor(s).

§ 582.5 - Disclosure of data and information to the public.

(a) The Director shall make data, information, and samples available in accordance with the requirements and subject to the limitations of the Act, the Freedom of Information Act (5 U.S.C. 552), and the implementing regulations (43 CFR part 2).

(b) Geophysical data, processed G&G information, interpreted G&G information, and other data and information submitted pursuant to the requirements of this part shall not be available for public inspection without the consent of the lessee so long as the lease remains in effect, unless the Director determines that earlier limited release of such information is necessary for the unitization of operations on two or more leases, to ensure proper Mining Plans for a common orebody, or to promote operational safety. When the Director determines that early limited release of data and information is necessary, the data and information shall be shown only to persons with a direct interest in the affected lease(s), unitization agreement, or joint Mining Plan.

(c) Geophysical data, processed geophysical information, and interpreted geophysical information collected on a lease with high resolution systems (including, but not limited to, bathymetry, side-scan sonar, subbottom profiler, and magnetometer) in compliance with stipulations or orders concerning protection of environmental aspects of the lease may be made available to the public 60 days after submittal to the Director, unless the lessee can demonstrate to the satisfaction of the Director that release of the information or data would unduly damage the lessee's competitive position.

§ 582.6 - Disclosure of data and information to an adjacent State.

(a) Proprietary data, information, and samples submitted to BOEM pursuant to the requirements of this part shall be made available for inspection by representatives of adjacent State(s) upon request by the Governor(s) in accordance with paragraphs (b), (c), and (d) of this section.

(b) Disclosure shall occur only after the Governor has entered into an agreement with the Secretary providing that:

(1) The confidentiality of the information shall be maintained;

(2) In any action commenced against the Federal Government or the State for failure to protect the confidentiality of proprietary information, the Federal Government or the State, as the case may be, may not raise as a defense any claim of sovereign immunity or any claim that the employee who revealed the proprietary information, which is the basis of the suit, was acting outside the scope of the person's employment in revealing the information;

(3) The State agrees to hold the United States harmless for any violation by the State or its employees or contractors of the agreement to protect the confidentiality of proprietary data, information, and samples; and

(c) The data, information, and samples available for inspection by representatives of adjacent State(s) pursuant to an agreement shall be related to leased lands.

§ 582.7 - Jurisdictional controversies.

In the event of a controversy between the United States and a State as to whether certain lands are subject to Federal or State jurisdiction, either the Governor of the State or the Secretary may initiate negotiations in an attempt to settle the jurisdictional controversy. With the concurrence of the Attorney General, the Secretary may enter into an agreement with a State with respect to OCS mineral activities and to payment and impounding of rents, royalties, and other sums and with respect to the issuance or nonissuance of new leases pending settlement of the controversy.

authority: Section 104, Public Law 97-451, 96 Stat. 2451 (30 U.S.C. 1714), Public Law 109-432, Div C, Title I, 120 Stat. 3000; 30 U.S.C. 1751; 31 U.S.C. 9701; 43 U.S.C. 1334; 33 U.S.C. 2704,2716; E.O. 12777, as amended; 43 U.S.C. 1331
source: 76 FR 64623, Oct. 18, 2011, unless otherwise noted.
cite as: 30 CFR 582.4