Regulations last checked for updates: Oct 18, 2024

Title 30 - Mineral Resources last revised: Oct 03, 2024
§ 585.100 - Authority.

The authority for this part derives from section 8 of the Outer Continental Shelf Lands Act (OCS Lands Act) (43 U.S.C. 1337). The Secretary of the Interior delegated to the Bureau of Ocean Energy Management (BOEM) the authority to manage the development of energy on the Outer Continental Shelf (OCS) from sources other than oil and gas, including renewable energy, through the issuance of leases, easements, and right-of-way for activities that produce or support the production, transportation, or transmission of energy.

§ 585.101 - What is the purpose of this part?

The purpose of this part is to:

(a) Establish procedures for issuance and administration of leases, right-of-way (ROW) grants, and right-of-use and easement (RUE) grants for renewable energy production on the OCS;

(b) Inform you and third parties of your obligations when you undertake activities authorized in this part; and

(c) Ensure that renewable energy activities on the OCS are conducted in a safe and environmentally sound manner, in conformance with the requirements of subsection 8(p) of the OCS Lands Act, other applicable laws and regulations, and the terms of your lease, ROW grant, or RUE grant.

(d) This part will not convey access rights for oil, gas, or other minerals.

§ 585.102 - What are BOEM's responsibilities under this part?

(a) BOEM will ensure that any activities authorized in this part are carried out in a manner that provides for and reaches a rational balance among the following goals to the extent they conflict or are otherwise in tension, none of which inherently outweighs or supplants any other:

(1) Safety;

(2) Protection of the environment;

(3) Prevention of waste, including economic waste and physical waste of energy resources from sources other than oil and gas;

(4) Conservation of the natural resources of the OCS;

(5) Coordination with relevant Federal agencies (including, in particular, those agencies involved in planning activities that are undertaken to avoid conflicts among users and to maximize the economic and ecological benefits of the OCS, including multifaceted spatial planning efforts);

(6) Protection of national security interests of the United States;

(7) Protection of the rights of other authorized users of the OCS;

(8) A fair return to the United States;

(9) Prevention of interference with reasonable uses of the exclusive economic zone, the high seas, and the territorial seas (as determined by the Secretary);

(10) Consideration of the location of and any schedule relating to a lease or grant under this part for an area of the OCS, and any other use of the sea or seabed;

(11) Public notice and comment on any proposal submitted for a lease or grant under this part; and

(12) Oversight, research, monitoring, and enforcement of activities authorized by a lease or grant under this part.

(b) BOEM will require compliance with all applicable laws, regulations, other requirements, and the terms of your lease or grant and approved plans under this part. BOEM will approve, disapprove, or approve with conditions any plans, applications, or other documents submitted to BOEM for approval under the provisions of this part.

(c) Unless otherwise provided in this part, BOEM may give oral directives or decisions whenever prior BOEM approval is required under this part. BOEM will document in writing any such oral directives within 10 business days.

(d) BOEM will establish practices and procedures to govern the collection of all payments due to the Federal Government required under the regulations of this part, including any cost recovery fees, rents, operating fees, and other fees or payments. BOEM will do this in accordance with the terms of this part, the leasing notice, the lease or grant under this part, and applicable Office of Natural Resources Revenue (ONRR) regulations or guidance.

(e) BOEM will provide for coordination and consultation with the Governor of any State, the executive of any local government, and the executive of any Indian Tribe that may be affected by a lease, easement, or ROW under this section. BOEM may invite any affected State Governor, representative of an affected Indian Tribe, and affected local government executive to join in establishing a task force or other joint planning or coordination agreement in carrying out our responsibilities under this part.

§ 585.103 - When may BOEM prescribe or approve departures from the regulations in this part?

(a) BOEM may prescribe or approve departures from the provisions of this part when BOEM deems the departure necessary because the applicable provisions as applied to a specific circumstance:

(1) Are impractical or unduly burdensome and the departure is necessary to achieve the intended objectives of the renewable energy program;

(2) Fail to conserve the natural resources of the OCS;

(3) Fail to protect life (including human and wildlife), property, or the marine, coastal, or human environment; or

(4) Fail to protect sites, structures, or objects of historical or archaeological significance.

(b) Any departure approved under this section and its rationale must:

(1) Be consistent with subsection 8(p) of the OCS Lands Act;

(2) Protect the environment and the public health and safety to the same degree as if there was no approved departure from this part;

(3) Not impair the rights of third parties; and

(4) Be documented in writing.

§ 585.104 - Do I need a BOEM lease or other authorization to produce or support the production of electricity or other energy product from a renewable energy resource on the OCS?

Except as otherwise authorized by law, it is unlawful for any person to construct, operate, or maintain any facility to produce, transport, or support generation of electricity or other energy product derived from a renewable energy resource on any part of the OCS, except in accordance with the terms of a lease, easement, or ROW issued under the OCS Lands Act.

§ 585.105 - What are my responsibilities under this part?

As a lessee, applicant, operator, or holder of a ROW or RUE grant, you must:

(a) Design your projects and conduct all activities in a manner that ensures safety and will not cause undue harm or damage to natural resources, including their physical, atmospheric, and biological components to the extent practicable; and take measures to prevent unauthorized discharge of pollutants including marine trash and debris into the offshore environment;

(b) Submit requests, applications, plans, notices, modifications, and supplemental information to BOEM as required by this part;

(c) Follow up, in writing, any oral request or notification you made, within 3 business days;

(d) Comply with all applicable laws and regulations, the terms of your lease or grant under this part, reports, notices, and approved plans prepared under this part, and any conditions imposed by BOEM through its review of any of these reports, notices, and approved plans, as provided in this part;

(e) Make all applicable payments on time;

(f) Comply with the DOI's nonprocurement debarment regulations at 2 CFR part 1400;

(g) Include the requirement to comply with 2 CFR part 1400 in all contracts and transactions related to a lease or grant under this part;

(h) Conduct all activities authorized by the lease or grant in a manner consistent with the provisions of subsection 8(p) of the OCS Lands Act;

(i) Compile, retain, and make available to BOEM representatives, within the time specified by BOEM, any data and information related to the site assessment, design, and operations of your project; and

(j) Respond to requests from the Director in a timely manner.

§ 585.106 - What happens if I fail to comply with this part?

(a) BOEM may take appropriate corrective action under this part if you fail to comply with applicable provisions of Federal law, the regulations in this part, other applicable regulations, any order of the Director, the provisions of a lease or grant issued under this part, or the requirements of an approved plan or other approval under this part.

(b) BOEM may issue to you a notice of noncompliance if we determine that there has been a violation of the regulations in this part, any order of the Director, or any provision of your lease, grant, or other approval issued under this part. When issuing a notice of noncompliance, BOEM will serve you at your last known address.

(c) A notice of noncompliance will tell you how you failed to comply with this part, any order of the Director and/or the provisions of your lease, grant or other approval, and will specify what you must do to correct the noncompliance and the time limits within which you must act.

(d) Failure of a lessee, operator, or grant holder to take the actions specified in a notice of noncompliance issued under this part within the time limit specified provides the basis for issuance of a cessation order by BSEE, as provided in 30 CFR 285.401 and/or cancellation of the lease or grant by the Secretary as provided in § 585.422.

(e) BOEM may assess civil penalties, as authorized by section 24 of the OCS Lands Act and as determined under the procedures set forth in 30 CFR part 550, subpart N, if you fail to comply with any provision of this part or any term of a lease, grant, or order issued under the authority of this part:

(1) After notice of such failure and expiration of any reasonable period allowed for corrective action; or

(2) BOEM determines that the failure constitutes, or constituted, a threat of serious, irreparable, or immediate harm or damage to life (including fish and other aquatic life), property, or the marine, coastal, or human environment.

§ 585.107 - Who can acquire or hold a lease or grant under this part?

(a) You may acquire or hold a lease or grant under this part if you can demonstrate that you have the technical and financial capabilities to conduct the activities authorized by the lease or grant and you are a(n):

(1) Citizen or national of the United States;

(2) Alien lawfully admitted for permanent residence in the United States as defined in 8 U.S.C. 1101(a)(20);

(3) Private, public, or municipal corporations organized under the laws of any State of the United States, the District of Columbia, or any territory or insular possession subject to U.S. jurisdiction;

(4) Association of such citizens, nationals, resident aliens, or corporations;

(5) Executive agency of the United States as defined in 5 U.S.C. 105;

(6) State of the United States; or

(7) Political subdivision of a State of the United States.

(b) You may not acquire or hold a lease or grant under this part or acquire an interest in a lease or grant under this part if:

(1) You or your principals are excluded or disqualified from participating in transactions covered by the Federal nonprocurement debarment and suspension system (2 CFR part 1400), unless BOEM explicitly has approved an exception for this transaction;

(2) BOEM determines or has previously determined after notice and opportunity for a hearing that you or your principals have failed to meet or exercise due diligence under any OCS lease or grant; or

(3) After written notice and your opportunity to be heard, BOEM determines that:

(i) You no longer meet the qualification requirements for acquiring or holding a lease or grant in paragraph (a) of this section.

(ii) You have:

(A) Violated an applicable law, regulation, order, lease or grant provision, approved plan, or the prohibitions prescribed in a final sale notice; or otherwise engaged in illegal activity, anti-competitive or collusive behavior, fraud, or misrepresentation; and

(B) Failed to take timely remedial action as specified in the written notice provided by BOEM of the basis for the disqualification.

(c) As long as a party is excluded or disqualified from acquiring or holding a lease or grant under this part, it is also ineligible to participate in BOEM's competitive and noncompetitive lease or grant issuance processes, including auctions, conducted under this part, even as an agent for another entity. A party can restore its eligibility by completing the remedial action specified in the notice of the proposed disqualification.

(d) You may share ownership interests in a lease with one or more other persons, provided that all interest holders in the lease are eligible to hold a lease pursuant to this section and § 585.108.

§ 585.108 - How do I show that I am qualified to be a lessee or grant holder?

(a) You must demonstrate your technical and financial capability to construct, operate, maintain, and terminate/decommission projects for which you are requesting authorization. Documentation can include:

(1) Descriptions of international or domestic experience with renewable energy projects or other types of electric-energy-related projects; and

(2) Information establishing access to sufficient capital to carry out development.

(b) An individual must submit a written statement of citizenship status attesting to U.S. citizenship. It does not need to be notarized nor give the age of individual. A resident alien may submit a photocopy of the U.S. Citizenship and Immigration Services form issued by the appropriate Federal immigration authority evidencing legal status as a resident alien.

(c) A corporation or association must submit evidence, as specified in the table in paragraph (d) of this section, acceptable to BOEM that:

(1) It is qualified to hold leases or grants under this part;

(2) It is authorized to conduct business under the laws of its State;

(3) It is authorized to hold leases or grants on the OCS under the operating rules of its business; and

(4) The persons holding the titles listed are authorized to bind the corporation or association when conducting business with BOEM.

(d) Acceptable evidence under paragraph (c) of this section includes, but is not limited to the following:

Requirements to qualify to hold leases or grants on the OCS: Corp. Ltd.
prtnsp.
Gen.
prtnsp.
LLC Trust
(1) Original certificate or certified copy from the State of incorporation stating the name of the corporation exactly as it must appear on all legal documentsXX
(2) Certified statement by Secretary/Assistant Secretary over corporate seal, certifying that the corporation is authorized to hold OCS leasesXX
(3) Evidence of authority of titled positions to bind corporation, certified by Secretary/Assistant Secretary over corporate seal, including the following:XX
(i) Certified copy of resolution of the board of directors with titles of officers authorized to bind corporation
(ii) Certified copy of resolutions granting corporate officer authority to issue a power of attorney
(iii) Certified copy of power of attorney or certified copy of resolution granting power of attorney
(4) Original certificate or certified copy of partnership or organization paperwork registering with the appropriate State officialXXXXXX
(5) Copy of articles of partnership or organization evidencing filing with appropriate Secretary of State, certified by Secretary/Assistant Secretary of partnership or member or manager of LLCXXXXXX
(6) Original certificate or certified copy evidencing State where partnership or LLC is registered. Statement of authority to hold OCS leases, certified by Secretary/Assistant Secretary, OR original paperwork registering with the appropriate State officialXXXXXX
(7) Statements from each partner or LLC member indicating the following:XXXXXX
(i) If a corporation or partnership, statement of State of organization and authorization to hold OCS leases, certified by Secretary/Assistant Secretary over corporate seal, if a corporation
(ii) If an individual, a statement of citizenship
(8) Statement from general partner, certified by Secretary/Assistant Secretary that:XX
(i) Each individual limited partner is a U.S. citizen and;
(ii) Each corporate limited partner or other entity is incorporated or formed and organized under the laws of a U.S. State or territory
(9) Evidence of authority to bind partnership or LLC, if not specified in partnership agreement, articles of organization, or LLC regulations, i.e., certificates of authority from Secretary/Assistant Secretary reflecting authority of officersXXXXXX
(10) Listing of members of LLC certified by Secretary/Assistant Secretary or any member or manager of LLCXX
(11) Copy of trust agreement or document establishing the trust and all amendments, properly certified by the trustee with reference to where the original documents are filedXX
(12) Statement indicating the law under which the trust is established and that the trust is authorized to hold OCS leases or grantsXX

(e) A local, State, or Federal executive entity must submit a written statement that:

(1) It is qualified to hold leases or grants under this part; and

(2) The person(s) acting on behalf of the entity is authorized to bind the entity when conducting business with us.

(f) BOEM may require you to submit additional information at any time considering your bid or request for a noncompetitive lease.

§ 585.109 - When must I notify BOEM if an action has been filed alleging that I am insolvent or bankrupt?

You must notify BOEM within 3 business days after you learn of any action filed alleging that you are insolvent or bankrupt.

§ 585.110 - When must I notify BOEM of mergers, name changes, or changes of business form?

You must notify BOEM in writing of any merger, name change, or change of business form. You must notify BOEM as soon as practicable following the merger, name change, or change in business form, but no later than 120 days after the earliest of either the effective date, or the date of filing the change or action with the Secretary of the State or other authorized official in the State of original registry.

§ 585.111 - How do I submit plans, applications, reports, or notices required by this part?

Unless otherwise stated, you must submit one electronic copy of all plans, applications, reports, or notices required by this part to BOEM. BOEM will inform you if it requires paper copies of specific documents. Unless stated otherwise, documents should be submitted to the relevant contacts listed on the BOEM website.

§ 585.112 - When and how does BOEM charge me processing fees on a case-by-case basis?

(a) BOEM will charge a processing fee on a case-by-case basis under the procedures in this section with regard to any application or request under this part if we decide at any time that the preparation of a particular document or study is necessary for the application or request and it will have a unique processing cost, such as the preparation of an Environmental Assessment (EA) or Environmental Impact Statement (EIS).

(1) Processing costs will include contract oversight and efforts to review and approve documents prepared by contractors, whether the contractor is paid directly by the applicant or through BOEM.

(2) We may apply a standard overhead rate to direct processing costs.

(b) We will assess the ongoing processing fee for each individual application or request according to the following procedures:

(1) Before we process your application or request, we will give you a written estimate of the proposed fee based on reasonable processing costs.

(2) You may comment on the proposed fee.

(3) You may:

(i) Ask for our approval to perform, or to directly pay a contractor to perform, all or part of any document, study, or other activity according to standards we specify, thereby reducing our costs for processing your application or request; or

(ii) Ask to pay us to perform, or contract for, all or part of any document, study, or other activity.

(4) We will then give you the final estimate of the processing fee amount with payment terms and instructions after considering your comments and any BOEM-approved work you will do.

(i) If we encounter higher or lower processing costs than anticipated, we will re-estimate our reasonable processing costs following the procedures in paragraphs (b)(1) through (4) of this section, but we will not stop ongoing processing unless you do not pay in accordance with paragraph (b)(5) of this section.

(ii) Once processing is complete, we will refund to you the amount of money that we did not spend on processing costs.

(5) Consistent with the payment and billing terms provided in the final estimate, we will periodically estimate what our reasonable processing costs will be for a specific period and will bill you for that period. Payment is due to us 30 days after you receive your bill. We will stop processing your document if you do not pay the bill by the date payment is due. If a periodic payment turns out to be more or less than our reasonable processing costs for the period, we will adjust the next billing accordingly or make a refund. Do not deduct any amount from a payment without our prior written approval.

(6) You must pay the entire fee before we will issue the final document or take final action on your application or request.

(7) You may appeal our estimated processing costs in accordance with the regulations in § 585.118 and 43 CFR part 4. We will not process the document further until the appeal is resolved, unless you pay the fee under protest while the appeal is pending. If the appeal results in a decision changing the proposed fee, we will adjust the fee in accordance with this section. If we adjust the fee downward, we will not pay interest.

§ 585.113 - Definitions.

Terms used in this part have the meanings as defined in this section:

Affected local government means with respect to any activities proposed, conducted, or approved under this part or 30 CFR part 285, any locality:

(1) That is, or is proposed to be, the site of gathering, transmitting, or distributing electricity or other energy product, or is otherwise receiving, processing, refining, or transshipping product, or services derived from activities approved under this part or 30 CFR part 285;

(2) That is used, or is proposed to be used, as a support base for activities approved under this part or 30 CFR part 285; or

(3) In which there is a reasonable probability of significant effect on land or water uses from activities approved under this part, or 30 CFR part 285.

Affected State means with respect to any activities proposed, conducted, or approved under this part or 30 CFR part 285, any coastal State—

(1) That is, or is proposed to be, the site of gathering, transmitting, or distributing energy or is otherwise receiving, processing, refining, or transshipping products, or services derived from activities approved under this part or 30 CFR part 285;

(2) That is used, or is scheduled to be used, as a support base for activities approved under this part or 30 CFR part 285; or

(3) In which there is a reasonable probability of significant effect on land or water uses from activities approved under this part or 30 CFR part 285.

Archaeological resource means any material remains of human life or activities that are at least 50 years of age and that are of archaeological interest (i.e., which are capable of providing scientific or humanistic understanding of past human behavior, cultural adaptation, and related topics through the application of scientific or scholarly techniques, such as controlled observation, contextual measurement, controlled collection, analysis, interpretation, and explanation).

Best available and safest technology means the best available and safest technologies that BOEM determines to be economically feasible wherever failure of equipment would have a significant effect on safety, health, or the environment.

Best management practices mean practices recognized within their respective industry, or by government, as one of the best for achieving the desired output while reducing undesirable outcomes.

Bidding credits means the value assigned by BOEM, expressed in monetary terms, to the factors or actions demonstrated, or committed to, by a bidder at a BOEM lease auction during the competitive lease award process. The type(s) and value(s) of any bidding credit(s) awarded to any given bidder will be set forth in the Final Sale Notice.

BOEM means Bureau of Ocean Energy Management of the Department of the Interior.

BSEE means Bureau of Safety and Environmental Enforcement of the Department of the Interior.

Certified Verification Agent (CVA) means an individual or organization, experienced in the design, fabrication, and installation of offshore marine facilities or structures, who will conduct specified third-party reviews, inspections, and verifications in accordance with 30 CFR part 285.

Coastal environment means the physical atmospheric, and biological components, conditions, and factors which interactively determine the productivity, state, condition, and quality of the terrestrial ecosystem from the shoreline inward to the boundaries of the coastal zone.

Coastline means the same as the term “coast line” in section 2 of the Submerged Lands Act (43 U.S.C. 1301(c)).

Commercial activities means, under renewable energy leases and grants, all activities associated with the generation, storage, or transmission of electricity or other energy product from a renewable energy project on the OCS, and for which such electricity or other energy product is intended for distribution, sale, or other commercial use, except for electricity or other energy product distributed or sold pursuant to technology-testing activities on a limited lease. This term also includes activities associated with all stages of development, including initial site characterization and assessment, facility construction, and project decommissioning.

Commercial lease means a lease issued under this part that specifies the terms and conditions under which a person can conduct commercial activities.

Commercial operations means the generation of electricity or other energy product for commercial use, sale, transmission, or distribution from a commercial lease.

Critical Safety Systems and Equipment means safety systems and equipment designed to prevent or ameliorate fire, spillages, or other major accidents that could result in harm to health, safety, or the environment in the area of your facilities.

Decommissioning means removing BOEM and BSEE approved facilities and returning the site of the lease or grant to a condition that meets the requirements under subpart I of 30 CFR part 285.

Director means the Director of BOEM, or an official authorized to act on the Director's behalf.

Distance means the minimum great circle distance.

Eligible State means a coastal State having a coastline (measured from the nearest point) no more than 15 miles from the geographic center of a qualified project area.

Fabrication means the cutting, fitting, welding, or other assembly of project elements.

Facility means an installation that is permanently or temporarily attached to the seabed of the OCS. Facilities include any structures; devices; appurtenances; gathering, transmission, and distribution cables; pipelines; and permanently moored vessels. Any group of OCS installations interconnected with walkways, or any group of installations that includes a central or primary installation with one or more satellite or secondary installations, is a single facility. BOEM and BSEE may decide that the complexity of the installations justifies their classification as separate facilities.

Geographic center of a project means the centroid (geometric center point) of a qualified project area. The centroid represents the point that is the weighted average of coordinates of the same dimension, with the weights determined by a density function. For example, in the case of a project area shaped as a rectangle or other parallelogram, the geographic center would be that point where lines between opposing corners intersect. The geographic center of a project could be outside the project area itself if that area is irregularly shaped.

Governor means the Governor of a State or the person or entity lawfully designated by or under State law to exercise the powers granted to a Governor.

Grant means a right-of-way or a right-of-use and easement issued under the provisions of this part.

Human environment means the physical, social, and economic components, conditions, and factors that interactively determine the state, condition, and quality of living conditions, employment, and health of those affected, directly or indirectly, by activities occurring on the OCS.

Lease means an agreement authorizing the use of a designated portion of the OCS for activities allowed under this part. The term also means the area covered by that agreement, when the context requires.

Lease area means an area on the OCS that BOEM has identified for leasing for potential development of renewable energy resources.

Lessee means the holder of a lease, a BOEM-approved assignee, and, when describing the conduct required of parties engaged in activities on the lease, it also refers to the operator and all persons authorized by the holder of the lease or operator to conduct activities on the lease.

Limited lease means a lease issued under this part that specifies the terms and conditions under which a person may conduct activities on the OCS that support the production of energy, but do not result in the production of electricity or other energy product for sale, distribution, or other commercial use exceeding a limit specified in the lease.

Marine environment means the physical, atmospheric, and biological components, conditions, and factors that interactively determine the productivity, state, condition, and quality of the marine ecosystem. These include the waters of the high seas, the contiguous zone, transitional and intertidal areas, salt marshes, and wetlands within the coastal zone and on the OCS.

Miles means nautical miles, as opposed to statute miles.

Multiple factor auction means an auction that involves the use of bidding credits to incentivize goals or actions that support public policy objectives or maximize public benefits through the competitive leasing auction process. For any multiple factor auction, the monetary value of the bidding credits, if any, would be added to the value of the cash bid to determine the highest bidder.

Natural resources include, without limiting the generality thereof, renewable energy, oil, gas, and all other minerals (as defined in section 2(q) of the OCS Lands Act), and marine animal and marine plant life.

Operator means the individual, corporation, or association having control or management of activities on the lease or grant under this part. The operator may be a lessee, grant holder, or a contractor designated by the lessee or holder of a grant issued under this part.

Outer Continental Shelf (OCS) means all submerged lands lying seaward and outside of the area of lands beneath navigable waters, as defined in section 2 of the Submerged Lands Act (43 U.S.C. 1301), whose subsoil and seabed appertain to the United States and are subject to its jurisdiction and control or within the exclusive economic zone of the United States and adjacent to any territory of the United States and does not include any area conveyed by Congress to a territorial government for administration.

Person means, in addition to a natural person, an association (including partnerships and joint ventures); a Federal agency; a State; a political subdivision of a State; a Native American Tribal government; or a private, public, or municipal corporation.

Project, for the purposes of defining the source of revenues to be shared, means a lease, ROW, RUE, or Alternate Use RUE on which the activities authorized under this part and/or 30 CFR part 285 or 586 are conducted on the OCS. The term “project” may be used elsewhere in this part to refer to these same authorized activities, the facilities used to conduct these activities, or to the geographic area of the project, i.e., the project area.

Project area means the geographic surface leased, or granted, for the purpose of a specific project. If OCS acreage is granted for a project under some form of agreement other than a lease (i.e., a ROW or RUE), the Federal acreage granted would be considered the project area. To avoid distortions in the calculation of the geometric center of the project area, project easements issued under this part are not considered part of the qualified project's area.

Project Design Envelope (PDE) means a reasonable range of design parameters proposed in a lessee's plan for components of the project, such as type, dimensions, and number of wind turbine generators; foundation type; location of the export cable route; location of an onshore substation; location of the grid connection point; and construction methods and timing.

Project easement means an easement to which, upon approval of your Construction and Operations Plan (COP) or General Activities Plan (GAP), you are entitled as part of the lease for the purpose of installing, maintaining, repairing and replacing: gathering, transmission, and distribution, and inter-array cables; power and pumping stations; facility anchors; pipelines; and associated facilities and other appurtenances on the OCS as necessary for the full enjoyment of the lease.

Provisional winner means a bidder that BOEM determines at the conclusion of the auction to have submitted the winning bid. The provisional winner becomes the winning bidder after the favorable completion of BOEM's bid review, Department of Justice antitrust review, bidder obligations under § 585.225(b), and any appeals process under § 585.118(c).

Receipt, as used in this part to describe the time when a document is received by any party in the absence of documentation to the contrary, is deemed to have taken place:

(1)(i) Five (5) business days after the date the document was given to the U.S. Postal Service (or deposited in one of its mailboxes), properly addressed and with proper postage affixed, or was given to a delivery service (or deposited in one of its receptacles), properly addressed and with the delivery cost prepaid; or

(ii) On the date on which the document was properly addressed and sent electronically.

(2) This definition also applies to variants of the words “receipt” and “receive” where those terms are used in this part to describe the receipt of a document when the timing of receipt triggers a regulatory time period or consequence.

Renewable Energy means energy resources other than oil and gas and minerals as defined in 30 CFR part 580. Such resources include, but are not limited to, wind, solar, and ocean waves, tides, and current.

Revenues mean bonuses, rents, operating fees, and similar payments made in connection with a project or project area. It does not include administrative fees such as those assessed for cost recovery, civil penalties, and forfeiture of financial assurance.

Right-of-use and easement (RUE) grant means an easement issued by BOEM under this part that authorizes use of a designated portion of the OCS to support activities on a lease or other use authorization for renewable energy activities. The term also means the area covered by the authorization.

Right-of-way (ROW) grant means an authorization issued by BOEM under this part to use a portion of the OCS for the construction and use of a cable or pipeline for the purpose of gathering, transmitting, distributing, or otherwise transporting electricity or other energy product generated or produced from renewable energy, but does not constitute a project easement under this part. The term also means the area c overed by the authorization.

Secretary means the Secretary of the Interior or an official authorized to act on the Secretary's behalf.

Significant archaeological resource means an archaeological resource that meets the criteria of significance for eligibility for listing in the National Register of Historic Places, as defined in 36 CFR 60.4.

Site assessment activities mean those initial activities conducted to assess an area on the OCS, such as resource assessment surveys (e.g., meteorological and oceanographic) or technology testing, involving the installation of bottom-founded facilities.

We, us, and our refer to BOEM, or its possessive, depending on the context.

You and your means an applicant, lessee, the operator, or designated operator, ROW grant holder or RUE grant holder under this part, or the designated agent of any of these, or the possessive of each, depending on the context. The terms you and your also include contractors and subcontractors of the entities specified in the preceding sentence.

§ 585.114 - How will data and information obtained by BOEM under this part be disclosed to the public?

(a) BOEM will make data and information available in accordance with the requirements and subject to the limitations of the Freedom of Information Act (FOIA) (5 U.S.C. 552) and the regulations contained in 43 CFR part 2.

(b) BOEM will not release such data and information that we have determined is exempt from disclosure under exemption 4 of FOIA. We will review such data and information and objections of the submitter by the following schedule to determine whether release at that time will result in substantial competitive harm or disclosure of trade secrets.

If you have a . . . Then BOEM will review data and information for possible
release:
(1) Commercial leaseAt the earlier of:
(i) 3 years after the commencement of commercial operations; or
(ii) 3 years after the lease terminates.
(2) Limited leaseAt 3 years after the lease terminates.
(3) ROW or RUE grantAt the earliest of:
(i) 10 years after the approval of the grant;
(ii) Grant termination; or
(iii) 3 years after the completion of construction activities.

(c) After considering any objections from the submitter, if we determine that release of such data and information will result in:

(1) No substantial competitive harm or disclosure of trade secrets, then the data and information will be released.

(2) Substantial competitive harm or disclosure of trade secrets, then the data and information will not be released at that time but will be subject to further review every 3 years thereafter.

§ 585.115 - Paperwork Reduction Act statements—information collection.

(a) The Office of Management and Budget (OMB) has approved the information collection requirements in this part under 44 U.S.C. 3501, et seq., and assigned OMB Control Number 1010-0176. The table in paragraph (e) of this section lists the subparts in the rule requiring the information and its title, summarizes the reasons for collecting the information, and summarizes how BOEM uses the information.

(b) Respondents are primarily renewable energy applicants, lessees, ROW grant holders, RUE grant holders, Alternate Use RUE grant holders, and operators. The requirement to respond to the information collection in this part is mandated under subsection 8(p) of the OCS Lands Act. Some responses are also required to obtain or retain a benefit or may be voluntary.

(c) The Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.) requires us to inform the public that an agency may not conduct or sponsor, and you are not required to respond to, a collection of information unless it displays a currently valid OMB control number.

(d) Comments regarding any aspect of the collections of information under this part, including suggestions for reducing the burden, should be sent to the Information Collection Clearance Officer, Bureau of Ocean Energy Management, 45600 Woodland Road, Sterling, VA 20166.

(e) BOEM is collecting this information for the reasons given in the following table:

30 CFR 585 subpart and title Reasons for collecting information and how used
(1) Subpart A—General ProvisionsTo inform BOEM of actions taken to comply with general operational requirements on the OCS. To ensure that operations on the OCS meet statutory and regulatory requirements, are safe and protect the environment, and result in diligent development on OCS leases.
(2) Subpart B—The Renewable Energy Leasing ScheduleTo enable BOEM to publish a proposed five-year leasing schedule for the OCS renewable energy program.
(3) Subpart C—Issuance of OCS Renewable Energy LeasesTo provide BOEM with information needed to determine when to use a competitive process for issuing a renewable energy lease, to identify auction formats and bidding systems and variables that we may use when that determination is affirmative, and to determine the terms under which we will issue renewable energy leases.
(4) Subpart D—ROW Grants and RUE Grants for Renewable Energy ActivitiesTo issue ROW grants and RUE grants for OCS renewable energy activities that are not associated with a BOEM-issued renewable energy lease.
(5) Subpart E—Lease and Grant AdministrationTo ensure compliance with regulations pertaining to a lease or grant, including designation of operator, assignment, segregation, consolidation, suspension, renewal, termination, relinquishment, and cancellation.
(6) Subpart F—Payments and Financial Assurance RequirementsTo ensure that payments and financial assurance payments for renewable energy leases comply with subpart E.
(7) Subpart G—Plans and Information RequirementsTo enable BOEM to comply with the National Environmental Policy Act (NEPA) (42 U.S.C. 4321 et seq.), the Coastal Zone Management Act (CZMA) (16 U.S.C. 1451 et seq.), and other Federal laws and to ensure the safety of the environment on the OCS.
§ 585.116 - Requests for information.

BOEM may publish a request for information (RFI) in the Federal Register for the following reasons:

(a) To solicit information from industry, federally recognized Tribes, State and local agencies, and other interested entities for evaluating the offshore renewable energy industry, including the identification of potential challenges or obstacles to its continued development. An RFI may relate to the identification of environmental, technical, regulatory, or economic matters that promote or detract from continued development of renewable energy technologies on the OCS. BOEM may use the information received to refine its renewable energy program, including to facilitate OCS renewable energy development in a safe and environmentally responsible manner and to ensure a fair return to the United States for use of the OCS.

(b) To assess interest in leasing all or part of the OCS for activities authorized in this part.

(c) To determine whether there is competitive interest in a specific OCS renewable energy proposal received by BOEM, such as an unsolicited request for a lease under § 585.231(b) or a RUE or ROW grant under § 585.307(a).

(d) To seek other information that BOEM needs for this program.

§ 585.117 - Severability.

If a court holds any provisions of this part or their applicability to any persons or circumstances invalid, the remainder of the provisions and their applicability to any persons or circumstances will not be affected.

§ 585.118 - What are my appeal rights?

(a) Except as stated in paragraph (c) of this section, any party adversely affected by a final decision issued by BOEM under this part may appeal that decision to the Interior Board of Land Appeals (IBLA), under 30 CFR part 590 and 43 CFR part 4, subpart E.

(b) Any final decision will remain in full force and effect during the pendency of an appeal unless a stay is granted under 43 CFR part 4.

(c) A bidder adversely affected by BOEM's determination of a provisional winner made under this part may appeal to the BOEM Director, but decisions determining a provisional winner may not be appealed to the IBLA.

(1) A bidder that elects to appeal a provisional winner selection decision must file a written appeal with the Director within 15 business days after receipt of the decision.

(2) Such appeal must be accompanied by a statement of reasons. Before reversing a provisional winner selection decision, the Director will provide the provisional winner a reasonable opportunity to respond in writing to the appellant's statement of reasons. The Director will issue a written determination either affirming or reversing the decision. The Director's decision is not appealable to the IBLA under this section.

(3) BOEM will not execute a lease or grant until the 15-business-day appeal period closes and all timely filed appeals are resolved.

(4) The review authority of the Office of Hearings and Appeals does not apply to either the provisional winner selection decisions made under this part or the Director's final determination affirming or reversing a provisional winner selection decision.

§§ 585.119-585.149 - §[Reserved]
authority: 43 U.S.C. 1337.
source: 88 FR 6430, Jan. 31, 2023, unless otherwise noted.
cite as: 30 CFR 585.111