Regulations last checked for updates: Nov 24, 2024
Title 32 - National Defense last revised: Nov 18, 2024
§ 37.615 - What standards do I include for financial systems of for-profit firms?
(a) To avoid causing needless changes in participants' financial management systems, your expenditure-based TIAs will make for-profit participants that currently perform under other expenditure-based Federal procurement contracts or assistance awards subject to the same standards for financial management systems that apply to those other awards. Therefore, if a for-profit participant has expenditure-based DoD assistance awards other than TIAs, your TIAs are to apply the standards in 32 CFR 34.11. You may grant an exception and allow a for-profit participant that has other expenditure-based Federal Government awards to use an alternative set of standards that meets the minimum criteria in paragraph (b) of this section, if there is a compelling programmatic or business reason to do so. For each case in which you grant an exception, you must document the reason in the award file.
(b) For an expenditure-based TIA, you are to allow and encourage each for-profit participant that does not currently perform under expenditure-based Federal procurement contracts or assistance awards (other than TIAs) to use its existing financial management system as long as the system, as a minimum:
(1) Complies with Generally Accepted Accounting Principles.
(2) Effectively controls all project funds, including Federal funds and any required cost share. The system must have complete, accurate, and current records that document the sources of funds and the purposes for which they are disbursed. It also must have procedures for ensuring that project funds are used only for purposes permitted by the agreement (see § 37.625).
(3) Includes, if advance payments are authorized under § 37.805, procedures to minimize the time elapsing between the payment of funds by the Government and the firm's disbursement of the funds for program purposes.
§ 37.620 - What financial management standards do I include for participants that are nonprofit?
So as not to force system changes for any State, local government, institution of higher education, or other nonprofit organization, your expenditure-based TIA's requirements for the financial management system of any nonprofit participant are the same as those that apply to the participant's other Federal assistance awards.
[85 FR 51245, Aug. 19, 2020]
§ 37.625 - What cost principles or standards do I require for for-profit participants?
(a) So as not to require any firm to needlessly change its cost-accounting system, your expenditure-based TIAs are to apply the Government cost principles in 48 CFR parts 31 and 231 to for-profit participants that currently perform under expenditure-based Federal procurement contracts or assistance awards (other than TIAs) and therefore have existing systems for identifying allowable costs under those principles. If there are programmatic or business reasons to do otherwise, you may grant an exception from this requirement and use alternative standards as long as the alternative satisfies the conditions described in paragraph (b) of this section; if you do so, you must document the reasons in your award file.
(b) For other for-profit participants, you may establish alternative standards in the agreement as long as that alternative provides, as a minimum, that Federal funds and funds counted as recipients' cost sharing will be used only for costs that:
(1) A reasonable and prudent person would incur in carrying out the research project contemplated by the agreement. Generally, elements of cost that appropriately are charged are those identified with research and development activities under the Generally Accepted Accounting Principles (see Statement of Financial Accounting Standards Number 2, “Accounting for Research and Development Costs,” October 1974
1
). Moreover, costs must be allocated to DoD and other projects in accordance with the relative benefits the projects receive. Costs charged to DoD projects must be given consistent treatment with costs allocated to the participants' other research and development activities (e.g., activities supported by the participants themselves or by non-Federal sponsors).
1 Copies may be obtained from the Financial Accounting Standards Board (FASB), 401 Merritt 7, P.O. Box 5116, Norwalk, CT 06856-5116. Information about ordering also may be found at the Internet site http://www.fasb.org or by telephoning the FASB at (800) 748-0659.
(2) Are consistent with the purposes stated in the governing Congressional authorizations and appropriations. You are responsible for ensuring that provisions in the award document address any requirements that result from authorizations and appropriations.
§ 37.630 - Must I require a for-profit firm to use Federally approved indirect cost rates?
In accordance with the general policy in § 37.605, you must require a for-profit participant that has Federally approved indirect cost rates for its Federal procurement contracts to use those rates to accumulate and report costs under an expenditure-based TIA. This includes both provisional and final rates that are approved up until the time that the TIA is closed out. You may grant an exception from this requirement if there are programmatic or business reasons to do otherwise (e.g., the participant offers you a lower rate). If you grant an exception, the participant must accumulate and report the costs using an accounting system and practices that it uses for other customers (e.g., its commercial customers). Also, you must document the reason for the exception in your award file.
§ 37.635 - What cost principles do I require a nonprofit participant to use?
So as not to force financial system changes for any nonprofit participant, your expenditure-based TIA will provide that costs to be charged to the research project by any nonprofit participant must be determined to be allowable in accordance with:
(a) Subpart E of OMB guidance in 2 CFR part 200, if the participant is a State, local government, Indian tribe, institution of higher education, or nonprofit organization. In conformance with 2 CFR 200.401(c) of that OMB guidance, a nonprofit organization listed in appendix VIII to 2 CFR part 200 is subject to the cost principles in the Federal Acquisition Regulation (48 CFR subpart 31.2) and Defense Federal Acquisition Regulation Supplement (48 CFR subpart 231.2).
(b) The cost principles identified in appendix IX to the OMB guidance in 2 CFR part 200 (see 45 CFR part 75), if the participant is a hospital.
[85 FR 51245, Aug. 19, 2020]
§ 37.640 - Must I include a provision for audits of for-profit participants?
If your TIA is an expenditure-based award, you must include in it an audit provision that addresses, for each for-profit participant:
(a) Whether the for-profit participant must have periodic audits, in addition to any award-specific audits, as described in § 37.645. Note that the DCAA or the Office of the Inspector General, DoD (OIG, DoD), can provide advice on the types and scope of audits that may be needed in various circumstances.
(b) Whether the DCAA or an independent public accountant (IPA) will perform required audits, as discussed in § 37.650.
(c) How frequently any periodic audits are to be performed, addressed in § 37.655.
(d) Other matters described in § 37.660, such as audit coverage, allowability of audit costs, auditing standards, and remedies for noncompliance.
§ 37.645 - Must I require periodic audits, as well as award-specific audits, of for-profit participants?
You need to consider requirements for both periodic audits and award-specific audits (as defined in § 37.1325 and § 37.1235, respectively). The way that your expenditure-based TIA addresses the two types of audits will vary, depending upon the type of for-profit participant.
(a) For for-profit participants that are audited by the DCAA or other Federal auditors, as described in §§ 37.650(b) and 37.655, you need not add specific requirements for periodic audits because the Federal audits should be sufficient to address whatever may be needed. Your inclusion in the TIA of the standard access-to-records provision for those for-profit participants, as discussed in § 37.915(a), gives the necessary access in the event that you or administrative agreements officers later need to request audits to address award-specific issues that arise.
(b) For each other for-profit participant, you:
(1) Should require that the participant have an independent auditor (i.e., the DCAA or an independent public accountant) conduct periodic audits of its systems if it expends $750,000 or more per year in TIAs and other Federal assistance awards. A prime reason for including this requirement is that the Federal Government, for an expenditure-based award, necessarily relies on amounts reported by the participant's systems when it sets payment amounts or adjusts performance outcomes. The periodic audit provides some assurance that the reported amounts are reliable.
(2) Must ensure that the award provides an independent auditor the access needed for award-specific audits, to be performed at the request of the cognizant administrative agreements officer if issues arise that require audit support. However, consistent with the government-wide policies on single audits that apply to nonprofit participants (see § 37.665), you should rely on periodic audits to the maximum extent possible to resolve any award-specific issues.
[68 FR 47160, Aug. 7, 2003, as amended at 85 FR 51246, Aug. 19, 2020]
§ 37.650 - Who must I identify as the auditor for a for-profit participant?
The auditor that you will identify in the expenditure-based TIA to perform periodic and award-specific audits of a for-profit participant depends on the circumstances, as follows:
(a) You may provide that an IPA will be the auditor for a for-profit participant that does not meet the criteria in paragraph (b) of this section, but only if the participant will not agree to give the DCAA access to the necessary books and records for audit purposes. Note that the allocable portion of the costs of the IPA's audit may be reimbursable under the TIA, as described in § 37.660(b). The IPA should be the one that the participant uses to perform other audits (e.g., of its financial statement), to minimize added burdens and costs. You must document in the award file the participant's unwillingness to give the DCAA access. The DCAA is to be the auditor if the participant grants the necessary access.
(b) Except as provided in paragraph (c) of this section, you must identify the DCAA as the auditor for any for-profit participant that is subject to DCAA audits because it is currently performing under a Federal award that is subject to the:
(1) Cost principles in 48 CFR part 31 of the Federal Acquisition Regulation (FAR) and 48 CFR part 231 of the Defense FAR Supplement; or
(2) Cost Accounting Standards in 48 CFR chapter 99.
(c) If there are programmatic or business reasons that justify the use of an auditor other than the DCAA for a for-profit participant that meets the criteria in paragraph (b) of this section, you may provide that an IPA will be the auditor for that participant if you obtain prior approval from the Office of the Inspector General, DoD. You must submit requests for prior approval to the Assistant Inspector General (Auditing), 4800 Mark Center Drive, Alexandria, VA 22350-1500. Your request must include the name and address of the business unit(s) for which IPAs will be used. It also must explain why you judge that the participant will not give the DCAA the necessary access to records for audit purposes (e.g., you may submit a statement to that effect from the participant). The OIG, DoD, will respond within five working days of receiving the request for prior approval, either by notifying you of the decision (approval or disapproval) or giving you a date by which they will notify you of the decision.
[68 FR 47160, Aug. 7, 2003, as amended at 85 FR 51246, Aug. 19, 2020]
§ 37.655 - Must I specify the frequency of IPAs' periodic audits of for-profit participants?
If your expenditure-based TIA provides for periodic audits of a for-profit participant by an IPA, you must specify the frequency for those audits. You should consider having an audit performed during the first year of the award, when the participant has its IPA do its next financial statement audit, unless the participant already had a systems audit due to other Federal awards within the past two years. The frequency thereafter may vary depending upon the dollars the participant is expending annually under the award, but it is not unreasonable to require an updated audit every two to three years to reverify that the participant's systems are reliable (the audit then would cover the two or three-year period between audits). The DCAA is a source of advice on audit frequencies if your TIA provides for audits by IPAs.
§ 37.660 - What else must I specify concerning audits of for-profit participants by IPAs?
If your expenditure-based TIA provides for audits of a for-profit participant by an IPA, you also must specify:
(a) What periodic audits are to cover. It is important that you specify audit coverage that is only as broad as needed to provide reasonable assurance of the participant's compliance with award terms that have a direct and material effect on the research project. Appendix C to this part provides guidance to for-profit participants and their IPAs that you may use for this purpose. The DCAA and the OIG, DoD, also can provide advice to help you set appropriate limits on audit objectives and scope.
(b) Who will pay for periodic and award-specific audits. The allocable portion of the costs of any audits by IPAs may be reimbursable under the TIA. The costs may be direct charges or allocated indirect costs, consistent with the participant's accounting system and practices.
(c) The auditing standards that the IPA will use. Unless you receive prior approval from the OIG, DoD, to do otherwise, you must provide that the IPA will perform the audits in accordance with the Generally Accepted Government Auditing Standards.
2
2 The electronic document may be accessed at www.gao.gov. Printed copies may be purchased from the U.S. Government Printing Office; for ordering information, call (202) 512-1800 or access the Internet site at www.gpo.gov.
(d) The available remedies for noncompliance. The agreement must provide that the participant may not charge costs to the award for any audit that the agreements officer, with the advice of the OIG, DoD, determines was not performed in accordance with the Generally Accepted Government Auditing Standards or other terms of the agreement. It also must provide that the Government has the right to require the participant to have the IPA take corrective action and, if corrective action is not taken, that the agreements officer has recourse to any of the remedies for noncompliance identified in 32 CFR 34.52(a).
(e) The remedy if it later is found that the participant, at the time it entered into the TIA, was performing on a procurement contract or other Federal award subject to the Cost Accounting Standards at 48 CFR part 30 and the cost principles at 48 CFR part 31. Unless the OIG, DoD, approves an exception (see § 37.650(c)), the TIA's terms must provide that the DCAA will perform the audits for the agreement if it later is found that the participant, at the time the TIA was awarded, was performing under awards described in § 37.650(b) that gave the DCAA audit access to the participant's books and records.
(f) Where the IPA is to send audit reports. The agreement must provide that the IPA is to submit audit reports to the administrative agreements officer and the OIG, DoD. It also must require that the IPA report instances of fraud directly to the OIG, DoD.
(g) The retention period for the IPA's working papers. You must specify that the IPA is to retain working papers for a period of at least three years after the final payment, unless the working papers relate to an audit whose findings are not fully resolved within that period or to an unresolved claim or dispute (in which case, the IPA must keep the working papers until the matter is resolved and final action taken).
(h) Who will have access to the IPA's working papers. The agreement must provide for Government access to working papers.
[68 FR 47160, Aug. 7, 2003, as amended at 85 FR 51246, Aug. 19, 2020]
§ 37.665 - Must I require nonprofit participants to have periodic audits?
Yes, expenditure-based TIAs are assistance instruments subject to the Single Audit Act (31 U.S.C. 7501-7507), so nonprofit participants are subject to their usual requirements under that Act, as implemented by subpart F of 2 CFR part 200. Specifically, the requirements are the same as those in subpart E of 2 CFR part 1128 for grants and cooperative agreements to institutions of higher education, nonprofit organizations, States, local governments, and Indian tribes. Note that those requirements also apply to Federally Funded Research and Development Centers (FFRDCs) and other Government-owned, Contractor-Operated (GOCO) facilities administered by nonprofit organizations, because nonprofit FFRDCs and GOCOs are subject to the Single Audit Act.
[85 FR 51246, Aug. 19, 2020]
§ 37.670 - Must I require participants to flow down audit requirements to subrecipients?
(a) Yes, in accordance with § 37.610, your expenditure-based TIA must require participants to flow down the same audit requirements to a subrecipient that would apply if the subrecipient were a participant.
(b) For example, a for-profit participant that is audited by the DCAA:
(1) Would flow down to a university subrecipient the Single Audit Act requirements that apply to a university participant.
(2) Could enter into a subaward allowing a for-profit participant, under the circumstances described in § 37.650(a), to use an IPA to do its audits.
(c) This policy applies to subawards for substantive performance of portions of the research project supported by the TIA, and not to participants' purchases of goods or services needed to carry out the research.
§ 37.600 - Which administrative matters are covered in this subpart?
This subpart addresses “systemic” administrative matters that place requirements on the operation of a participant's financial management, property management, or purchasing system. Each participant's systems are organization-wide and do not vary with each agreement. Therefore, all TIAs should address systemic requirements in a uniform way for each type of participant organization.
§ 37.605 - What is the general policy on participants' financial, property, and purchasing systems?
The general policy for expenditure-based TIAs is to avoid requirements that would force participants to use different financial management, property management, and purchasing systems than they currently use for:
(a) Expenditure-based Federal procurement contracts and assistance awards in general, if they receive them; or
(b) Commercial business, if they have no expenditure-based Federal procurement contracts and assistance awards.
§ 37.610 - Must I tell participants what requirements they are to flow down for subrecipients' systems?
If it is an expenditure-based award, your TIA must require participants to flow down the same financial management, property management, and purchasing systems requirements to a subrecipient that would apply if the subrecipient were a participant. For example, a for-profit participant would flow down to a university subrecipient the requirements that apply to a university participant. Note that this policy applies to subawards for substantive performance of portions of the research project supported by the TIA, and not to participants' purchases of goods or services needed to carry out the research.
§ 37.685 - May I allow for-profit firms to purchase real property and equipment with project funds?
(a) With the two exceptions described in paragraph (b) of this section, you must require a for-profit firm to purchase real property or equipment with its own funds that are separate from the research project. You should allow the firm to charge to an expenditure-based TIA only depreciation or use charges for real property or equipment (and your cost estimate for a fixed-support TIA only would include those costs). Note that the firm must charge depreciation consistently with its usual accounting practice. Many firms treat depreciation as an indirect cost. Any firm that usually charges depreciation indirectly for a particular type of property must not charge depreciation for that property as a direct cost to the TIA.
(b) In two situations, you may grant an exception and allow a for-profit firm to use project funds, which includes both the Federal Government and recipient shares, to purchase real property or equipment (i.e., to charge to the project the full acquisition cost of the property). The two circumstances, which should be infrequent for equipment and extremely rare for real property, are those in which you either:
(1) Judge that the real property or equipment will be dedicated to the project and have a current fair market value that is less than $5,000 by the time the project ends; or
(2) Give prior approval for the firm to include the full acquisition cost of the real property or equipment as part of the cost of the project (see § 37.535).
(c) If you grant an exception in either of the circumstances described in paragraphs (b)(1) and (2) of this section, you must make the real property or equipment subject to the property management standards in 32 CFR 34.21(b) through (d). As provided in those standards, the title to the real property or equipment will vest conditionally in the for-profit firm upon acquisition. Your TIA, whether it is a fixed-support or expenditure-based award, must specify that any item of equipment that has a fair market value of $5,000 or more at the conclusion of the project also will be subject to the disposition process in 32 CFR 34.21(e), whereby the Federal Government will recover its interest in the property at that time.
§ 37.690 - How are nonprofit participants to manage real property and equipment?
For nonprofit participants, your TIA's requirements for vesting of title, use, management, and disposition of real property or equipment acquired under the award are the same as those that apply to the participant's other Federal assistance awards.
[85 FR 51246, Aug. 19, 2020]
§ 37.695 - What are the requirements for Federally owned property?
If you provide Federally owned property to any participant for the performance of research under a TIA, you must require that participant to account for, use, and dispose of the property in accordance with:
(a) 32 CFR 34.22, if the participant is a for-profit firm.
(b) The requirements that apply to the participant's other Federal awards, if it is an entity other than a for-profit firm. If the other Federal awards of a participant that is a GOCO or FFRDC administered by a nonprofit organization are procurement contracts, it is appropriate for you to specify the same property standards that apply to those Federal procurement contracts.
[68 FR 47160, Aug. 7, 2003, as amended at 85 FR 51246, Aug. 19, 2020]
§ 37.700 - What are the requirements for supplies?
Your expenditure-based TIA's provisions should permit participants to use their existing procedures to account for and manage supplies. A fixed-support TIA should not include requirements to account for or manage supplies.
§ 37.705 - What standards do I include for purchasing systems of for-profit firms?
(a) If your TIA is an expenditure-based award, it should require for-profit participants that currently perform under DoD assistance instruments subject to the purchasing standards in 32 CFR 34.31 to use the same requirements for TIAs, unless there are programmatic or business reasons to do otherwise (in which case you must document the reasons in the award file).
(b) You should allow other for-profit participants under expenditure-based TIAs to use their existing purchasing systems, as long as they flow down the applicable requirements in Federal statutes, Executive orders or Governmentwide regulations (see appendix E to this part for a list of those requirements).
(c) If your TIA is a fixed-support award, you need only require for-profit participants to flow down the requirements listed in appendix F to this part.
§ 37.710 - What standards do I include for purchasing systems of nonprofit organizations?
(a) So as not to force system changes for any nonprofit participant, your expenditure-based TIA will provide that each nonprofit participant's purchasing system comply with standards that conform as much as practicable with requirements that apply to the participant's other Federal awards.
(b) If your TIA is a fixed-support award, you need only require nonprofit participants to flow down the requirements listed in appendix E to this part.
[68 FR 47160, Aug. 7, 2003, as amended at 85 FR 51246, Aug. 19, 2020]
source: 68 FR 47160, Aug. 7, 2003, unless otherwise noted.
cite as: 32 CFR 37.710