§ 39.80 - General requirements for a grant.
(a) For a State or Tribal Organization to obtain a grant for the operation or maintenance of a State or Tribal veterans cemetery:
(1) Its preapplication for the grant must be approved by VA under § 39.81(e);
(2) Its project must be ranked sufficiently high within Priority Group 4 as defined in § 39.3 for the applicable fiscal year so that funds are available for the project, and a grant for the project must not result in payment of more than the $10 million total amount permissible for all Operation and Maintenance Projects in any fiscal year;
(3) Its plans and specifications for the project must be approved by VA under § 39.82;
(4) The State or Tribal Organization must meet the application requirements in § 39.84; and
(5) Other requirements specified in §§ 39.6, 39.10, and 39.83 must be satisfied.
(b) VA may approve under § 39.85 any Operation and Maintenance Project grant application up to the amount of the grant requested once the requirements under paragraph (a) of this section have been satisfied, provided that sufficient funds are available, and that total amount of grants awarded during any fiscal year for Operation and Maintenance Projects does not exceed $10 million. In determining whether sufficient funds are available, VA shall consider the project's ranking in Priority Group 4; the total amount of funds available for cemetery grant awards in Priority Group 4 during the applicable fiscal year; and the prospects of higher-ranking projects being ready for the award of a grant before the end of the applicable fiscal year.
(Authority: 38 U.S.C. 501,2408,June,2010,as,Jan. 30, 2012; 87 FR 80461, Dec. 30, 2022]
§ 39.81 - Preapplication requirements.
(a) A State or Tribal Organization seeking a grant for the operation or maintenance of a State or Tribal veterans cemetery must submit a preapplication to the Director, Veterans Cemetery Grants Service, through http://www.cem.va.gov/cem/scg_grants.asp.
(b) No detailed drawings, plans, or specifications are required with the preapplication. As a part of the preapplication, the State or Tribal Organization must submit each of the following:
(1) Standard Form 424 (Application for Federal Assistance) and Standard Form 424C (Budget Information) signed by the authorized representative of the State or Tribal Organization. These forms document the amount of the grant requested, which may not exceed 100 percent of the estimated cost of the project to be funded with the grant.
(2) VA Form 40-0895-2 (Certification of Compliance with Provisions of the Davis-Bacon Act) to certify that the State or Tribal Organization has obtained the latest prevailing wage rates for Federally funded projects. Any construction project fully or partially funded with Federal dollars must comply with those rates for specific work by trade employees (e.g., electricians, carpenters).
(3) VA Form 40-0895-6 (Certification of State or Tribal Government Matching Architectural and Engineering Funds to Qualify for Group 1 on the Priority List) to provide documentation that the State or Tribal Organization has legal authority to support the project and the resources necessary to initially fund the architectural and engineering portion of the project development. Once the grant is awarded, VA will reimburse the applicant for all allowable architectural and engineering costs.
(4) VA Form 40-0895-7 (Certification Regarding Debarment, Suspension, and Other Responsibility Matters-Primary Covered Transactions (State or Tribal Government)) to ensure that the applicant has not been debarred or suspended, and is eligible to participate in the VA grant process and receive Federal funds.
(5) VA Form 40-0895-8 (Certification Regarding Drug-Free Workplace Requirements for Grantees Other Than Individuals) to ensure that the applicant complies with the Drug-Free Workplace Act of 1988 at the location where the construction will occur.
(6) VA Form 40-0895-9 (Certification Regarding Lobbying) to ensure that the applicant complies with Public Law 101-121 regarding the prohibition against any payments to anyone that influences or attempts to influence an officer or Member of Congress in connection with the award of a grant.
(7) VA Form 40-0895-10 (Certification of Compliance with Federal Requirements-State or Tribal Government Construction Grant) to ensure that the applicant complies with all requirements of part 39.
(8) VA Form 40-0895-15 (Certification of Cemetery Maintained in Accordance with National Cemetery Administration Standards) to ensure that any cemetery operated or maintained through a grant will be operated and maintained in accordance with VA's national shrine standards of appearance.
(9) A gravesite assessment survey documenting the State or Tribal cemetery's performance related to the standards outlined in paragraph (b)(10) of this section for the year in which the preapplication is submitted.
(10) A program narrative describing how the project will assist the State or Tribal Organization in meeting VA's national shrine standards with respect to cleanliness, height and alignment of headstones and markers, leveling of gravesites, or turf conditions. Specifically, the preapplication should explain the need for the grant, how the work is to be accomplished, and the expected improvement in the State or Tribal cemetery's performance related to one or more of the following national shrine standards:
(i) Cleanliness. 90 percent of headstones, markers, and niche covers must be clean and free of debris and objectionable accumulations.
(ii) Height. 90 percent of headstones and markers must be set and maintained at the proper height.
(iii) Alignment. 100 percent of headstones, markers, and niche covers must be properly installed. Upright headstones in active burial sections must be uniform in height (24″-26″ above ground), horizontally and vertically aligned with inscriptions visible, and installed to ensure a pleasing top line while compensating for ground contours. Flat markers must be uniform in height (parallel with the ground and no more than 1″ above grade) and horizontally and vertically aligned. Niche covers must be horizontally and vertically aligned. All inscriptions must be visible.
(iv) Grade. 95 percent of the grade of every gravesite must blend in with adjacent grade levels.
(v) Turf conditions. 100 percent of visually prominent areas must have a well-established, healthy stand of turf that is generally weed free; 95 percent of visually prominent areas with established turf must be generally free of bare areas.
(11) A description of the geographic location of the existing State or Tribal veteran cemetery and any other supporting documentation, as requested by the VCGS Director.
(12) A description of the project including the number and types of headstones and markers that need to be cleaned and aligned, a description of the gravesites that need to be leveled, and a description of the turf conditions that need to be improved to meet VA's national shrine standards.
(c) In addition, the State or Tribal Organization must submit written assurance of each of the following conditions:
(1) Any cemetery in receipt of a grant under this subpart will be used exclusively for the interment or memorialization of eligible persons, as set forth in § 39.10(a), whose interment or memorialization is not contrary to the conditions of the grant (see § 39.10(b) and 38 U.S.C. 2408(d) and 2411).
(2) Title to the site is or will be vested solely in the State or held in trust for the Tribal Organization on trust land.
(3) The State or Tribal Organization possesses legal authority to apply for the grant.
Note to paragraph (c)(3):
In any case where a Tribal Organization is applying for a grant for a cemetery on land held in trust for more than one Indian Tribe, written assurance that the Tribal Organization possesses legal authority to apply for the grant includes certification that the Tribal Organization has obtained the approval of each such Indian Tribe.
(4) The State or Tribal Organization will obtain approval by VA of the final specifications before the project is advertised or placed on the market for bidding; the project will achieve VA's national shrine standards with respect to cleanliness, height and alignment of headstones and markers, leveling of gravesites, or turf conditions in accordance with the application and approved plans and specifications; the State or Tribal Organization will submit to the Director of the Veterans Cemetery Grants Service, for prior approval, changes that alter any cost of the project; and the State or Tribal Organization will not enter into a contract for the project or undertake other activities until all the requirements of the grant program have been met.
(d) Depending on the scope of the project, the VCGS will work with the State or Tribal Organization to determine which, if any, of the following are required:
(1) Compliance with section 106 of the National Historic Preservation Act of 1966, as amended (16 U.S.C. 470), Executive Order 11593 (identification and protection of historic properties), and the Archaeological and Historic Preservation Act of 1974 (16 U.S.C. 469a-1 et seq.).
(2) Compliance with the Federal requirements in 2 CFR parts 180, 200, and 801 and submission of Standard Form 424D (Assurances—Construction Programs).
(3) A site Environmental Assessment to determine whether an Environmental Impact Statement will be necessary as a result of the work to be performed on the headstones and markers, gravesites, or turf conditions.
(e) Upon receipt of a complete preapplication for a grant, including all necessary assurances and all required supporting documentation, VA will determine whether the preapplication conforms to all requirements listed in paragraphs (a) through (d) of this section, including whether it contains sufficient information necessary to establish the project's priority. VA will notify the State or Tribal Organization of any nonconformity. If the preapplication does conform, VA shall notify the State or Tribal Organization that the preapplication has been found to meet the preapplication requirements, and the proposed project will be included in the next scheduled ranking of projects, as indicated in § 39.3(d).
(The Office of Management and Budget has approved the information collection requirements in this section under control numbers 4040-0004, 4040-0008, 4040-0009, and 2900-0559)
(Authority: 25 U.S.C. 450b(l); 38 U.S.C. 501,2408,2411,June,2010,as,Jan. 30, 2012; 80 FR 43322, July 22, 2015]
§ 39.82 - Plan preparation.
(a) The State or Tribal Organization must successfully complete its plan preparation under this section before submitting a grant application for an Operation and Maintenance Project. The State or Tribal Organization may be required to undertake some or all of the following requirements of this section. After submitting all necessary plans and specifications to the VCGS and obtaining approval for the State or Tribal Organization to solicit for the Operation and Maintenance Project contract bids, the State or Tribal Organization shall:
(1) Obtain bids and determine the successful bidder;
(2) Establish procedures for determining that costs are reasonable and necessary and can be allocated in accordance with 2 CFR part 200 and submit documentation of such determinations to VA; and
(3) Comply with the uniform requirements for grants-in-aid to State, Tribal and local governments prescribed by 2 CFR part 200.
(b) Depending on the scope of the project, the VCGS will work with the State or Tribal Organization to determine which of the following will be required prior to submission of an application. As determined by VA, these may include:
(1) A boundary and site survey comprising a survey and legal description of the existing State or Tribal cemetery site;
(2) Project drawings indicating the cemetery section(s) to be impacted by the Operation and Maintenance Project, gravesite section layout with permanent section monument markers and lettering system, and the total number of gravesites to be impacted;
(3) Project specifications (to be used for bid purposes), which shall include the invitation for bid, cover or title sheet, index, general requirements, form of bid bond, form of agreement, performance and payment bond forms, and detailed descriptions of materials and workmanship for the work to be performed to meet VA's national shrine standards;
(4) A detailed estimate of the total cost of the work to be performed under the contract; or
(5) A site Environmental Assessment meeting the provisions of § 39.34(b) to determine if an Environmental Impact Statement is necessary for compliance with section 102(2)(C) of the National Environmental Policy Act of 1969, as amended (42 U.S.C. 4332), as a result of the work to be performed on the headstones and markers, gravesites, or turf conditions.
(c) If VA determines that the project's plans and specifications comply with the terms and conditions prescribed by VA, VA will send the State or Tribal Organization a written letter of approval indicating that the project's plans and specifications comply with the terms and conditions as prescribed by VA. This does not constitute approval of the contract documents. It is the responsibility of the State or Tribal Organization to ascertain that all State and Federal requirements have been met and that the drawings and specifications are acceptable for bid purposes.
(The Office of Management and Budget has approved the information collection requirement in this section under control number 2900-0559)
(Authority: 38 U.S.C. 501,2408,June,2010,as,Jan. 30, 2012; 80 FR 43322, July 22, 2015]
§ 39.83 - Conferences.
(a) Planning conference. The VCGS may require planning conferences for Operation and Maintenance Projects, primarily to ensure that the State or Tribal Organization becomes oriented to VA's national shrine standards, procedures, requirements, and any technical comments pertaining to the project. These conferences will normally occur over the telephone.
(b) Additional conferences. At any time, VA may recommend an additional telephone conference to provide an opportunity for the State or Tribal Organization to discuss with VA officials the requirements for an Operation and Maintenance Project grant.
(Authority: 38 U.S.C. 501,2408,Jan. 30, 2012]
§ 39.84 - Application requirements.
For an Operation and Maintenance Project to be considered for grant funding under this subpart, the State or Tribal Organization must submit an application (as opposed to a preapplication) consisting of the following:
(a) Standard Form 424 (Application for Federal Assistance) with the box labeled “application” marked;
(b) Standard Form 424C (Budget Information), which documents the amount of funds requested based on the construction costs as estimated by the successful construction bid;
(c) A copy of itemized bid tabulations; and
(d) Standard Form 424D (Assurances—Construction Program).
(e) VA Form 40-0895-11 (Memorandum of Agreement for a Grant to Construct or Modify a State or Tribal Government Veterans Cemetery) to identify the parties (VA and applicant), identify the scope of the project, and indicate how the grant award funds will be paid to the applicant.
(f) VA Form 40-0895-12 (Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion-Lower Tier Covered Transactions (Contractor)) to ensure that the contractor has not been debarred or suspended, and is eligible to participate in the VA grant process and receive Federal funds.
(The Office of Management and Budget has approved the information collection requirements in this section under control numbers 4040-0002, 4040-0008, 4040-0009, and 2900-0559)
(Authority: 38 U.S.C. 501,2408,June,2010,as,Jan. 30, 2012]
§ 39.85 - Final review and approval of application.
Following VA approval of bid tabulations and cost estimates, the complete Operation and Maintenance Project grant application will be reviewed for approval in accordance with the requirements of § 39.80. If the application is approved, the grant will be awarded by a Memorandum of Agreement of Federal grant funds.
(Authority: 38 U.S.C. 501,2408
§§ 39.86-39.99 - §[Reserved]
§ 39.100 - Amount of grant.
(a) The amount of an Operation and Maintenance Project grant awarded under this subpart may not exceed 100 percent of the total cost of the project, but may be less than total cost of the project.
(b) The total cost of a project under this subpart may include any or all of the following costs:
(1) Administration and design costs, e.g., architectural and engineering fees, inspection fees, and printing and advertising costs.
(2) Construction costs.
(3) The cost of VA-approved equipment that is necessary for the completion of the project.
(c) The total cost of a project under this subpart may not include the cost of any of the following:
(1) Land acquisition;
(2) Buildings of any type;
(3) Improvements not on cemetery land, such as access roads or utilities;
(4) Office supplies or consumable goods (such as fuel and fertilizer) that are routinely used in a cemetery; or
(5) Project contingency costs.
(d) VA shall certify approved applications to the Secretary of the Treasury in the amount of the grant, and shall designate the appropriation from which it shall be paid. Funds paid for the operation and maintenance of a veterans cemetery must be used solely for carrying out approved projects.
(Authority: 38 U.S.C. 501,2408
§ 39.101 - Payment of grant award.
The amount of an Operation and Maintenance Project grant award will be paid to the State or Tribal Organization or, if designated by the State or Tribal Organization representative, the State or Tribal veterans cemetery for which such project is being carried out, or to any other State or Tribal Organization agency or instrumentality. Such amount shall be paid by way of reimbursement and in installments that are consistent with the progress of the project, as the Director of the Veterans Cemetery Grants Service may determine and certify for payment to the appropriate Federal institution. Funds paid under this section for an approved Operation and Maintenance Project shall be used solely for carrying out such project as approved. As a condition for the final payment, the State or Tribal representative must submit to VA each of the following:
(a) Standard Form 271 (Outlay Report and Request for Reimbursement for Construction Programs);
(b) A report on the project accomplishments in accordance with § 39.120 and a request in writing for the final architectural/engineering inspection, including the name and telephone number of the local point of contact for the project;
(c) The written statement, “It is hereby agreed that the monetary commitment of the Federal government will have been met and the project will be considered terminated upon payment of this voucher.”; and
(d) Evidence that the State or Tribal Organization has met its responsibility for an audit under the Single Audit Act of 1984 (31 U.S.C. 7501 et seq.) and § 39.122.
(The Office of Management and Budget has approved the information collection requirements in this section under control number 0348-0002)
(Authority: 38 U.S.C. 501,2408,June,2010,as,Jan. 30, 2012]