§ 2804.10 - What should I do before I file my application?

§ 2804.11 - Where do I file my grant application?

§ 2804.12 - What must I do when submitting my application?

§ 2804.13 - Will BLM keep my information confidential?

§ 2804.14 - What are the fee categories for cost recovery?

§ 2804.15 - When does the BLM reevaluate the cost recovery fees?

§ 2804.16 - When will the BLM waive cost recovery fees?

§ 2804.17 - What is a Master Agreement (Cost Recovery Category 5) and what information must I provide to the BLM when I request one?

§ 2804.18 - What provisions do Master Agreements contain and what are their limitations?

§ 2804.19 - How will the BLM manage my Category 6 project?

§ 2804.20 - How does the BLM determine reasonable costs for Category 6 right-of-way activities?

§ 2804.21 - What other factors will the BLM consider in determining cost recovery fees?

§ 2804.22 - How will the availability of funds affect the timing of the BLM's processing your application?

§ 2804.23 - What costs am I responsible for when the BLM decides to use a competitive process for lands included in my application?

§ 2804.24 - Do I always have to submit an application for a grant using Standard Form 299?

§ 2804.25 - How will the BLM process my application?

§ 2804.26 - Under what circumstances may the BLM deny my application?

§ 2804.27 - What fees must I pay if the BLM denies my application or if I withdraw my application or relinquish my grant?

§ 2804.28 - What processing fees must I pay for a BLM grant application associated with Federal Energy Regulatory Commission (FERC) licenses or re-license applications under part I of the Federal Power Act (FPA)?

§ 2804.29 - What activities may I conduct on the lands covered by the proposed right-of-way while BLM is processing my application?

§§ 2804.30-2804.31 - §[Reserved]

§ 2804.35 - Application prioritization for solar and wind energy development rights-of-way.

§ 2804.40 - Alternative requirements.

§ 2804.10 - What should I do before I file my application?

(a) Before filing an application with BLM, we encourage you to make an appointment for a preapplication meeting with the appropriate personnel in the BLM field office having jurisdiction over the lands you seek to use. During the preapplication meeting, BLM can:

(1) Identify potential routing and other constraints;

(2) Determine whether the lands are located inside a designated or existing right-of-way corridor or a designated leasing area;

(3) Tentatively schedule the processing of your proposed application; and

(4) Inform you of your financial obligations, such as processing and monitoring costs and rents.

(b) Subject to § 2804.13 of this subpart, BLM may share any information you provide under paragraph (a) of this section with Federal, state, tribal, and local government agencies to ensure that:

(1) These agencies are aware of any authorizations you may need from them; and

(2) We initiate effective coordinated planning as soon as possible.

[70 FR 21058, Apr. 22, 2005, as amended at 81 FR 92207, Dec. 19, 2016; 89 FR 25959, Apr. 12, 2024]
§ 2804.11 - Where do I file my grant application?

(a) You must file the grant application in the BLM field office having jurisdiction over the lands affected by your application.

(b) If your application affects more than one BLM administrative unit, you may file at any BLM office having jurisdiction over any part of the project. BLM will notify you where to direct subsequent communications.

§ 2804.12 - What must I do when submitting my application?

(a) File your application on Standard Form 299, available from any BLM office or at https://www.blm.gov, and fill in the required information. The application must include the applicant's original signature or meet the BLM standards for electronic commerce. Your complete application must include the following:

(1) A description of the project and the scope of the facilities;

(2) The estimated schedule for constructing, operating, maintaining, and terminating the project;

(3) The estimated life of the project and the proposed construction and reclamation techniques;

(4) A map of the project showing its proposed location and existing facilities adjacent to the proposal, and Geographic Information Systems (GIS) shapefiles, or equivalent format, when requested by the BLM;

(5) A statement of your financial and technical capability to construct, operate, maintain, and terminate the project;

(6) Any plans, contracts, agreements, or other information concerning your use of the right-of-way and its effect on competition;

(7) A statement certifying that you are of legal age and authorized to do business in the State(s) where the right-of-way would be located and that you have submitted correct information to the best of your knowledge; and

(8) A schedule for the submission of a plan of development (POD) conforming to the POD template at http://www.blm.gov, should the BLM require you to submit a POD under § 2804.25(c).

(b) When submitting an application for a solar or wind energy development project or for a transmission line project with a capacity of 100 kV or more, in addition to the information required in paragraph (a) of this section, you must:

(1) Include a general description of the proposed project and a schedule for the submission of a POD conforming to the POD template at http://www.blm.gov;

(2) Address all known potential resource conflicts with sensitive resources and values, including special designations or protections, and include applicant-proposed measures to avoid, minimize, and compensate for such resource conflicts, if any;

(3) Initiate early discussions with any grazing permittees that may be affected by the proposed project in accordance with 43 CFR 4110.4-2(b); and

(4) Within 6 months from the time the BLM receives the cost recovery fee under § 2804.14, schedule and hold two preliminary application review meetings as follows:

(i) The first meeting will be with the BLM to discuss the general project proposal, the status of BLM land use planning for the lands involved, potential siting issues or concerns, potential environmental issues or concerns, potential alternative site locations and the right-of-way application process;

(ii) The second meeting will be with appropriate Federal and State agencies and tribal and local governments to facilitate coordination of potential environmental and siting issues and concerns; and

(iii) You and the BLM may agree to hold additional preliminary application review meetings.

(c) You must meet additional requirements when applying for a solar or wind energy development or short-term right-of-way, as follows:

(1) Pay an application filing fee of $2 per acre for short-term right-of-way applications or $15 per acre for solar or wind energy development applications. The BLM will apply the application filing fee toward the processing fees described in §§ 2804.14 through 2804.22. The BLM will refund the balance of any application filing fee at the end of the BLM's application review process if the application filing fee exceeds the amount of the processing fee.

(2) Pay additional reasonable costs in addition to payment of the application filing fee when processing your application, pursuant to § 2804.14. A processing or monitoring Category 6 cost recovery fee may be reduced by the application filing fee paid when submitting an application.

(d) If you are unable to meet a requirement of the application outlined in this section, you may submit a request for an alternative requirement under § 2804.40.

(e) If you are a business entity, you must also submit the following information:

(1) Copies of the formal documents creating the entity, such as articles of incorporation, and including the corporate bylaws;

(2) Evidence that the party signing the application has the authority to bind the applicant;

(3) The name and address of each participant in the business;

(4) The name and address of each shareholder owning 3 percent or more of the shares and the number and percentage of any class of voting shares of the entity which such shareholder is authorized to vote;

(5) The name and address of each affiliate of the business;

(6) The number of shares and the percentage of any class of voting stock owned by the business, directly or indirectly, in any affiliate controlled by the business;

(7) The number of shares and the percentage of any class of voting stock owned by an affiliate, directly or indirectly, in the business controlled by the affiliate; and

(8) If you have already provided the information in paragraphs (b)(1) through (7) of this section to the BLM and the information remains accurate, you need only reference the BLM serial number under which you previously filed it.

(f) The BLM may require you to submit additional information at any time while processing your application. The BLM will identify additional information in a written deficiency notice asking you to provide the information within a specified time pursuant to § 2804.25(c).

(g) If you are a Federal oil and gas lessee or operator and you need a right-of-way for access to your production facilities or oil and gas lease, you may include your right-of-way requirements with your Application for Permit to Drill or Sundry Notice required under parts 3160 through 3190 of this chapter.

(h) If you are filing with another Federal agency for a license, certificate of public convenience and necessity, or other authorization for a project involving a right-of-way on public lands, simultaneously file an application with the BLM for a grant. Include a copy of the materials, or reference all the information, you filed with the other Federal agency.

(i) Inter-agency coordination. You may request, in writing, an exemption from the requirements of this section if you can demonstrate to the BLM that you have satisfied similar requirements by participating in an inter-agency coordination process with another Federal, State, local, or Tribal authority. No exemption is approved until you receive BLM approval in writing.

(j) Your application will not be complete until you have met or addressed the requirements of this section to the satisfaction of the BLM. The BLM will notify you in writing when your application is complete.

[81 FR 92207, Dec. 19, 2016, as amended at 89 FR 25959, Apr. 12, 2024; 89 FR 35678, May 1, 2024]
§ 2804.13 - Will BLM keep my information confidential?

BLM will keep confidential any information in your application that you mark as “confidential” or “proprietary” to the extent allowed by law.

§ 2804.14 - What are the fee categories for cost recovery?

(a) Unless your fees are waived under § 2804.16, you must pay cost recovery fees for the reasonable costs associated with your application and grant. Subject to applicable laws and regulations, if your application involves Federal agencies other than the BLM, your fee may also include the reasonable costs estimated to be incurred by those Federal agencies. Instead of paying the BLM a fee for the reasonable costs incurred by other Federal agencies in processing your application, you may pay other Federal agencies directly. The fees for Categories 1 through 4 (see paragraph (b) of this section) are one-time fees and are not refundable. Reasonable costs are those costs defined in Section 304(b) of FLPMA (43 U.S.C. 1734(b)). The fees are categorized based on an estimate of the amount of time that the Federal Government will expend to process your application, issue a decision granting or denying the application, and monitor that land use authorization.

(b) The BLM bases cost recovery fees on categories. The BLM will update the fee schedule for Categories 1 through 4 each calendar year, based on the previous year's change in the IPD-GDP, as measured second quarter to second quarter rounded to the nearest dollar. The BLM will update Category 5 fees, which may include preliminary application review, processing, and monitoring, as specified in the applicable Master Agreement. Category 6 fees are for situations when a right-of-way activity will require more than 64 hours, or when an environmental impact statement (EIS) is required and may include preliminary application review costs. The cost recovery categories and the estimated range of Federal work hours for each category are:

Table 1 to Paragraph (b)—Cost Recovery Categories

FLPMA right-of-way cost recovery category descriptions Federal work hours involved
Category 1. Processing and monitoring associated with an application or existing grantEstimated Federal work hours are ≤8.
Category 2. Processing and monitoring associated with an application or existing grantEstimated Federal work hours are >8 ≤24.
Category 3. Processing and monitoring associated with an application or existing grantEstimated Federal work hours are >24 ≤40.
Category 4. Processing and monitoring associated with an application or existing grantEstimated Federal work hours are >40 ≤64.
Category 5. Master Agreements *Varies, depending on the agreement.
Category 6. Processing and monitoring associated with an application or existing grant, including preliminary-application reviews *Estimated Federal work hours are >64.

* Preliminary application review costs are those expenses related to meetings held between a Federal agency and the applicant to discuss a right-of-way application. These reviews are required only when an application is for a wind or solar right-of-way but are encouraged for other right-of-way application filings. A Master Agreement may include preliminary application review costs.

(c) You may obtain a copy of the current year's cost recovery fee schedule at https://www.blm.gov, by contacting your local BLM state, district, or field office, or by writing: Attention to the Division of Lands, Realty and Cadastral Survey, U.S. Department of the Interior, Director (HQ-350), Bureau of Land Management, 1849 C Street NW, Mail Stop 2134LM, Washington, DC 20240.

(d) After an initial review of your application, the BLM will notify you of the cost recovery category into which your application fits. You must then submit to the BLM the appropriate payment for that category before the BLM will begin processing your application. Your signature on a cost recovery Master Agreement constitutes your agreement with the cost recovery category decision. If you disagree with the category that the BLM has determined for your application, you may appeal the decision under § 2801.10. For Category 5 and 6 applications or grants, see §§ 2804.17, 2804.18, and 2804.19. If you paid the cost recovery fee and you appeal a Category 1 through 4 or Category 6 determination, the BLM will work on your application or grant while the appeal is pending. If the Interior Board of Land Appeals (IBLA) finds in your favor, you will receive a refund or an adjustment of your cost recovery fee.

(e) In processing your application, the BLM may determine at any time that the application requires preparing an EIS. If this occurs, the BLM will send you a decision changing your cost recovery category to Category 6. You may appeal this decision under § 2801.10.

(f) To expedite processing of your application, you may notify the BLM in writing that you are waiving application of the factors identified in §§ 2804.20(a) and 2804.21 to determine reasonable costs and are electing to pay the actual costs incurred by the BLM in processing your application and monitoring your grant.

[89 FR 25959, Apr. 12, 2024]
§ 2804.15 - When does the BLM reevaluate the cost recovery fees?

BLM reevaluates the processing and monitoring fees (see § 2805.16 of this part) for each category and the categories themselves within 5 years after they go into effect and at 10-year intervals after that. When reevaluating processing and monitoring fees, BLM considers all factors that affect the fees, including, but not limited to, any changes in:

(a) Technology;

(b) The procedures for processing applications and monitoring grants;

(c) Statutes and regulations relating to the right-of-way program; or

(d) The IPD-GDP.

§ 2804.16 - When will the BLM waive cost recovery fees?

(a) The BLM may waive your cost recovery fees if:

(1) You are a State or local government, or an agency of such a government, and the BLM issues the grant for governmental purposes benefitting the general public. However, if you collect revenue from charges you levy on customers for services similar to those of a profit-making corporation or business, or you assess similar fees to the United States for similar purposes, cost recovery fees will not be waived;

(2) Your application under this subpart is associated with a cost-share road or reciprocal right-of-way agreement; or

(3) You are a Federal agency, and your cost recovery category determination is Category 1 to 4.

(b) The BLM will not waive your cost recovery fees if you are in trespass.

[89 FR 25960, Apr. 12, 2024]
§ 2804.17 - What is a Master Agreement (Cost Recovery Category 5) and what information must I provide to the BLM when I request one?

(a) A Master Agreement (Cost Recovery Category 5) is a written agreement covering processing and monitoring fees (see § 2804.14) negotiated between the BLM and you that involves multiple BLM grant approvals and/or monitoring scenarios for projects within defined geographic areas or for a specific common activity for many projects.

(b) Your request for a Master Agreement must:

(1) Describe the geographic area covered by the Agreement and the scope of the activity you plan;

(2) Include a preliminary work plan. This plan must state what work you must do and what work BLM must do to process your application. Both parties must periodically update the work plan, as specified in the Agreement, and mutually agree to the changes;

(3) Contain a preliminary cost estimate and a timetable for processing the application and completing the projects;

(4) State whether you want the Agreement to apply to future applications in the same geographic area that are not part of the same projects; and

(5) Contain any other relevant information that BLM needs to process the application.

[70 FR 21058, Apr. 22, 2005, as amended at 89 FR 25960, Apr. 12, 2024]
§ 2804.18 - What provisions do Master Agreements contain and what are their limitations?

(a) A Master Agreement:

(1) Specifies that you must comply with all applicable laws and regulations;

(2) Describes the work you will do and the work the BLM will do to complete right-of-way activities;

(3) Describes the method of periodic billing, payment, and auditing;

(4) Describes the processes, studies, or evaluations you will pay for;

(5) Explains how the BLM will monitor a grant and how the BLM will receive payment for this work;

(6) Describes existing agreements between the BLM and other Federal agencies for cost reimbursement;

(7) Contains provisions allowing for periodic review and updating, if required;

(8) Contains specific conditions for terminating the Agreement;

(9) May be prepared so that it includes previously granted rights-of-way held by the right-of-way holder; and

(10) Contains any other provisions BLM considers necessary.

(b) BLM will not enter into any Agreement that is not in the public interest.

(c) If you sign a Master Agreement, you waive your right to request a reduction of cost recovery fees.

[70 FR 21058, Apr. 22, 2005, as amended at 81 FR 92209, Dec. 19, 2016; 89 FR 25960, Apr. 12, 2024] [89 FR 25960, Apr. 12, 2024]
§ 2804.19 - How will the BLM manage my Category 6 project?

(a) For Category 6 applications, you and the BLM must enter into a written agreement that describes how the BLM will process your application and monitor your grant. The BLM may require that the final agreement contain a work plan and a financial plan, and a description of any existing agreements you have with other Federal agencies for cost reimbursement associated with your application or grant.

(b) In processing your application, the BLM will:

(1) Determine the issues subject to analysis under NEPA;

(2) Prepare a preliminary work plan, if applicable;

(3) Develop a preliminary financial plan, if applicable, which estimates the reasonable costs of processing your application and monitoring your project;

(4) Collect, in advance and at the BLM's discretion, a deposit for your Category 6 project to initiate processing your application while all of the plans and agreements are being completed;

(5) Discuss with you:

(i) The preliminary plans and data;

(ii) The availability of funds and personnel;

(iii) Your options for the timing of processing and monitoring fee payments; and

(iv) Financial information you must submit; and

(6) Complete final scoping and develop final work and financial plans that reflect any work you have agreed to do. The BLM will also present you with the final estimate of the reasonable costs for which you must reimburse the BLM, including the cost for monitoring the project, using the factors in §§ 2804.20 and 2804.21 of this subpart.

(c) BLM retains the option to prepare any environmental documents related to your application. If BLM allows you to prepare any environmental documents and conduct any studies that BLM needs to process your application, you must do the work following BLM standards. For this purpose, you and BLM may enter into a written agreement. BLM will make the final determinations and conclusions arising from such work.

(d) BLM will periodically, as stated in the agreement, estimate processing costs for a specific work period and notify you of the amount due. You must pay the amount due before BLM will continue working on your application. If your payment exceeds the reasonable costs that BLM incurred for the work, BLM will either adjust the next billing to reflect the excess, or refund you the excess under 43 U.S.C. 1734. You may not deduct any amount from a payment without BLM's prior written approval.

(e) We may collect reimbursement for reasonable costs to the United States for processing applications and other documents under this part relating to the public lands.

[70 FR 21058, Apr. 22, 2005, as amended at 81 FR 92209, Dec. 19, 2016; 89 FR 25961, Apr. 12, 2024]
§ 2804.20 - How does the BLM determine reasonable costs for Category 6 right-of-way activities?

The BLM will consider the factors in paragraph (a) of this section and § 2804.21 of this subpart to determine reasonable costs. Submit to the BLM field office having jurisdiction over the lands covered by your application a written analysis of those factors applicable to your project unless you agree in writing to waive consideration of those factors and elect to pay actual costs (see § 2804.14(f) of this subpart). Submitting your analysis with the application will expedite its handling. The BLM may require you to submit additional information in support of your position. The BLM will continue to work on your application while you are responding to our request, as long as a deposit has been received by the BLM as provided in § 2804.19(a)(4).

(a) FLPMA factors. If the BLM determines that a Category 6 cost recovery fee is appropriate for your project, the BLM will apply the following factors as set forth in Section 304(b) of FLPMA, 43 U.S.C. 1734(b), to determine the amount you owe:

(1) Actual costs to the Federal Government (exclusive of management overhead costs) of processing your application and of monitoring construction, operation, maintenance, and termination of a facility authorized by the right-of-way grant;

(2) Monetary value of the rights or privileges you seek;

(3) BLM's ability to process an application with maximum efficiency and minimum expense, waste, and effort;

(4) Costs incurred for the benefit of the general public interest rather than for the exclusive benefit of the applicant. That is, the costs for studies and data collection that have value to the Federal Government or the general public apart from processing the application;

(5) Any tangible improvements, such as roads, trails, and recreation facilities, which provide significant public service and are expected in connection with constructing and operating the facility;

(6) Existing agreements between the BLM and other Federal agencies for cost reimbursement associated with such application; and

(7) Other factors relevant to the reasonableness of the costs (see § 2804.21 of this subpart).

(b) Fee determination. After considering your analysis and other information, BLM will notify you in writing of what you owe. If you disagree with BLM's determination, you may appeal it under § 2801.10 of this part.

[70 FR 21058, Apr. 22, 2005, as amended at 81 FR 92209, Dec. 19, 2016; 89 FR 25961, Apr. 12, 2024]
§ 2804.21 - What other factors will the BLM consider in determining cost recovery fees?

(a) Other factors. If you include this information in your application, in arriving at your cost recovery fee in any category, the BLM will consider whether:

(1) Payment of actual costs would:

(i) Result in undue financial hardship to your small business, and you would receive little monetary value from your grant as compared to the costs of processing and monitoring; or

(ii) Create such undue financial hardship as to prevent your use and enjoyment of your right-of-way for a non-commercial purpose.

(2) The costs of performing any or all right-of-way activities grossly exceed the costs of constructing the project;

(3) You are a non-profit organization, corporation, or association which is not controlled by or a subsidiary of a profit-making enterprise; and

(i) The studies undertaken in connection with processing the application or monitoring the grant have a public benefit; or

(ii) The facility or project will provide a benefit or special service to the general public or to a program of the Secretary;

(4) You need a grant to prevent or mitigate damages to any lands or property or to mitigate hazards or danger to public health and safety resulting from an act of God, an act of war, or negligence of the United States;

(5) You have a grant and need to secure a new or amended grant in order to relocate an authorized facility to comply with public health and safety and environmental protection laws, regulations, and standards which were not in effect at the time BLM issued your original grant;

(6) You have a grant and need to secure a new grant to relocate facilities which you have to move because a Federal agency or federally-funded project needs the lands and the United States does not pay the costs associated with your relocation; or

(7) For whatever other reason, such as public benefits or public services provided, cost recovery fees would be inconsistent with prudent and appropriate management of public lands and with your equitable interests or the equitable interests of the United States.

(b) Fee determination. With your written application, submit your analysis of how each of the factors, as applicable, in paragraph (a) of this section, pertains to your application. The BLM will notify you in writing of the fee determination. You may appeal this decision under § 2801.10 of this part.

[70 FR 21058, Apr. 22, 2005, as amended at 89 FR 25961, Apr. 12, 2024]
§ 2804.22 - How will the availability of funds affect the timing of the BLM's processing your application?

(a) If the BLM has insufficient funds to process your application, we will not continue to process it until funds become available or you elect to pay full actual costs under § 2804.14(f) of this part.

(b) The BLM may deny your application if we have not received requested reasonable costs for processing your application within 90 days.

(c) If your cost recovery agreement provides that a portion of the funds you pay will be used in the hiring of additional staff or contractors, such funds may not be refundable.

[89 FR 35678, May 1, 2024]
§ 2804.23 - What costs am I responsible for when the BLM decides to use a competitive process for lands included in my application?

If the BLM decides to use a competitive process for lands included in your application and your application is in:

(a) Processing Categories 1 through 4. You must reimburse the Federal Government for processing costs as if the other application or applications had not been filed.

(b) Processing Category 6. You are responsible for processing costs identified in your application. If the BLM cannot readily separate costs, such as costs associated with preparing environmental analyses, you and any competing applicants must pay an equal share, or a proportion agreed to in writing among all applicants and the BLM. If you agree to share the costs that are common to your application and that of a competing applicant, and the competitor does not pay the agreed upon amount, you are liable for the entire amount due. You must pay the entire processing fee in advance. The BLM will not process your application until we receive the advance payments.

[89 FR 35678, May 1, 2024]
§ 2804.24 - Do I always have to submit an application for a grant using Standard Form 299?

You do not have to file an application using Standard Form 299 if:

(a) The BLM offers lands competitively under § 2804.23(c) and you have already submitted an application for the facility or system;

(b) The BLM offers lands for competitive lease under subpart 2809 of this part; or

(c) You are an oil and gas operator. You may include your right-of-way requirements for a FLPMA grant as part of your Application for Permit to Drill or Sundry Notice under the regulations in parts 3160 through 3190 of this chapter.

[70 FR 21058, Apr. 22, 2005, as amended at 81 FR 92209, Dec. 19, 2016]
§ 2804.25 - How will the BLM process my application?

(a) The BLM will notify you in writing when it receives your application. This notification will also:

(1) Identify your cost recovery fee described at § 2804.14, unless you are exempt from paying fees; and

(2) Inform you of any other grant applications which involve all or part of the lands for which you applied.

(b) The BLM will not process your application if you have any:

(1) Outstanding unpaid debts owed to the Federal Government. Outstanding debts are those currently unpaid debts owed to the Federal Government after all administrative collection actions have occurred, including any appeal proceedings under applicable Federal regulations and the Administrative Procedure Act; or

(2) Trespass action pending against you for any activity on BLM-administered lands (see § 2808.12), except those to resolve the trespass with a right-of-way as authorized in this part, or a lease or permit under the regulations found at 43 CFR part 2920, but only after outstanding unpaid debts are paid.

(c) The BLM may require you to submit additional information necessary to process the application. This information may include a detailed construction, operation, rehabilitation, and environmental protection plan (i.e., a POD), and any needed cultural resource surveys or inventories for threatened or endangered species. If the BLM needs more information, the BLM will identify this information in a written deficiency notice asking you to provide the additional information within a specified period of time. The failure to provide additional information requested by the BLM under this section may result in the BLM denying your application pursuant to § 2804.26.

(d) Customer service standard. The BLM will process your complete application as follows:

Table 1 to Paragraph (d)

Processing
category
Processing time Conditions
1-460 calendar daysIf processing your application will take longer than 60 calendar days, the BLM will notify you in writing of this fact prior to the 30th calendar day and inform you of when you can expect a final decision on your application.
5As specified in the Master AgreementThe BLM will process applications as specified in the Master Agreement.
6Over 60 calendar daysThe BLM will notify you in writing within the initial 60-day processing period of the estimated processing time.

(e) In processing an application, the BLM will:

(1) Hold public meetings if sufficient public interest exists to warrant their time and expense. The BLM will publish a notice in the Federal Register and may use other notification methods, such as a newspaper of general circulation in the vicinity of the lands involved in the area affected by the potential right-of-way or the Internet, to announce in advance any public hearings or meetings;

(2) If your application is for solar or wind energy development;

(i) Hold a local public meeting if there is no other public meeting or opportunity for early engagement on the project, such as those completed when complying with the National Environmental Policy Act (NEPA).

(ii) Prioritize the application in accordance with § 2804.35; and

(iii) Evaluate the application based on the information provided by the applicant and input from other parties, such as Federal, State, Tribal, and local government agencies, as well as comments received in preliminary application review meetings held under § 2804.12(b)(4) and any public meeting held under paragraph (e)(1) of this section. Based on these evaluations, the BLM will either deny your application or continue processing it.

(3) Determine whether a POD schedule submitted with your application meets the development schedule or other requirements described by the BLM, such as in § 2804.12(b);

(4) Complete appropriate NEPA compliance for the application, as required by 43 CFR part 46 and 40 CFR chapter V, subchapter A;

(5) Determine whether your proposed use complies with applicable Federal laws;

(6) If your application is for a road, determine whether it is in the public interest to require you to grant the United States an equivalent authorization across lands that you own;

(7) Consult, as necessary, on a government-to-government basis with tribes and other governmental entities; and

(8) Take any other action necessary to fully evaluate and decide whether to approve or deny your application.

(f)(1) The BLM may segregate, if it finds it necessary for the orderly administration of the public lands, lands included in a right-of-way application under this subpart for the generation of electrical energy from wind or solar sources. In addition, the BLM may also segregate lands that it identifies for potential rights-of-way for electricity generation from wind or solar sources when initiating a competitive process for solar or wind development on particular lands. Upon segregation, such lands would not be subject to appropriation under the public land laws, including location under the Mining Law of 1872 (30 U.S.C. 22 et seq.), but would remain open under the Mineral Leasing Act of 1920 (30 U.S.C. 181 et seq.) or the Materials Act of 1947 (30 U.S.C. 601 et seq.). The BLM would effect a segregation by publishing a Federal Register notice that includes a description of the lands being segregated. The BLM may effect segregation in this way for both pending and new right-of-way applications.

(2) The effective date of segregation is the date of publication of the notice in the Federal Register. Consistent with 43 CFR 2091-3.2, the segregation terminates and the lands automatically open on the date that is the earliest of the following:

(i) When the BLM issues a decision granting, granting with modifications, or denying the application for a right-of-way;

(ii) Automatically at the end of the segregation period stated in the Federal Register notice initiating the segregation; or

(iii) Upon publication of a Federal Register notice terminating the segregation and opening the lands.

(3) The segregation period may not exceed 2 years from the date of publication in the Federal Register of the notice initiating the segregation, unless the state director determines and documents in writing, prior to the expiration of the segregation period, that an extension is necessary for the orderly administration of the public lands. If the state director determines an extension is necessary, the BLM will extend the segregation for up to 2 years by publishing a notice in the Federal Register, prior to the expiration of the initial segregation period. A segregation will not be extended unless the application is complete and cost recovery has been received. Segregations under this part may only be extended once and the total segregation period may not exceed 4 years.

[81 FR 92209, Dec. 19, 2016, as amended at 89 FR 25961, Apr. 12, 2024; 89 FR 35678, May 1, 2024]
§ 2804.26 - Under what circumstances may the BLM deny my application?

(a) BLM may deny your application if:

(1) The proposed use is inconsistent with the purpose for which BLM manages the public lands described in your application;

(2) The proposed use would not be in the public interest;

(3) You are not qualified to hold a grant;

(4) Issuing the grant would be inconsistent with FLPMA, other laws, or these or other regulations;

(5) You do not have or cannot demonstrate the technical or financial capability to construct the project or operate facilities within the right-of-way.

(i) Applicants must have or be able to demonstrate technical and financial capability to construct, operate, maintain, and terminate a project throughout the application process and authorization period. You can demonstrate your financial and technical capability to construct, operate, maintain, and terminate a project by:

(A) Documenting any previous successful experience in construction, operation, and maintenance of similar facilities on either public or non-public lands;

(B) Providing information on the availability of sufficient capitalization to carry out development, including the preliminary study stage of the project and the environmental review and clearance process; or

(C) Providing written copies of conditional commitments of Federal and other loan guarantees; confirmed power purchase agreements; engineering, procurement, and construction contracts; and supply contracts with credible third-party vendors for the manufacture or supply of key components for the project facilities.

(ii) Failure to demonstrate and sustain technical and financial capability is grounds for denying an application or terminating an authorization;

(6) The PODs required by §§ 2804.25(e)(3) and 2804.12(a)(8) and (c)(1) do not meet the development schedule or other requirements in the POD template and the applicant is unable to demonstrate why the POD should be approved;

(7) Failure to commence necessary surveys and studies, or plans for permit processing as required by § 2804.25(c); or

(8) The BLM's evaluation of your solar or wind application made under § 2804.25(e)(2)(iii) provides a basis for a denial.

(9) You do not comply with a deficiency notice (see § 2804.25(c) of this subpart) within the time specified in the notice.

(10) You fail to pay costs for processing your application within 90 days of receiving the BLM's request for funds under § 2804.22(b).

(b) If BLM denies your application, you may appeal this decision under § 2801.10 of this part.

[70 FR 21058, Apr. 22, 2005, as amended at 81 FR 92211, Dec. 19, 2016; 89 FR 25962, Apr. 12, 2024; 89 FR 35679, May 1, 2024]
§ 2804.27 - What fees must I pay if the BLM denies my application or if I withdraw my application or relinquish my grant?

If the BLM denies or you withdraw your application, or you relinquish your grant, you owe the current fees for the applicable cost recovery category as set forth at § 2804.14, unless you have a Category 5 or 6 application, in which case, the following conditions apply:

(a) If the BLM denies your Category 5 or 6 right-of-way application, you are liable for all reasonable costs that the United States incurred in processing it. The money you have not paid is due within 30 calendar days after receiving a bill for the amount due;

(b) You may withdraw your Category 5 or 6 application in writing before the BLM issues a grant. If you do so, you are liable for all reasonable processing costs the United States has incurred up to the time you withdraw the application and for the reasonable costs of terminating your application. Any money you have not paid is due within 30 calendar days after receiving a bill for the amount due. Any money you paid that is not used to cover costs the United States incurred as a result of your application will be refunded to you; and

(c) You may relinquish your grant in writing. If you do so, you are liable for all reasonable costs the United States has incurred up to the time you relinquish the grant and for the reasonable costs of closing your grant. Any cost recovery fees you have not previously paid are due within 30 calendar days after receiving a bill for the amount due. The BLM will refund any cost recovery fees you paid in Categories 5 or 6 that were not used to cover costs the United States incurred as a result of your grant.

[89 FR 25962, Apr. 12, 2024]
§ 2804.28 - What processing fees must I pay for a BLM grant application associated with Federal Energy Regulatory Commission (FERC) licenses or re-license applications under part I of the Federal Power Act (FPA)?

(a) You must reimburse BLM for the costs which the United States incurs in processing your grant application associated with a FERC project, other than those described at § 2801.6(b)(7) of this part. BLM also requires reimbursement for processing a grant application associated with a FERC project licensed before October 24, 1992, that involves the use of additional public lands outside the original area reserved under section 24 of the FPA.

(b) BLM will determine the amount you must pay by using the processing fee categories described at § 2804.14 of this subpart and bill you for the costs. FERC will address other costs associated with processing a FERC license or relicense (see 18 CFR chapter I).

§ 2804.29 - What activities may I conduct on the lands covered by the proposed right-of-way while BLM is processing my application?

(a) You may conduct casual use activities on the BLM lands covered by the application, as may any other member of the public. BLM does not require a grant for casual use on BLM lands.

(b) For any activities on BLM lands that are not casual use, you must obtain prior BLM approval.

§§ 2804.30-2804.31 - §[Reserved]
§ 2804.35 - Application prioritization for solar and wind energy development rights-of-way.

(a) The BLM will prioritize the processing of applications to ensure that agency resources are allocated to applications with the greatest potential for approval and implementation. The BLM's prioritization of an application is not a decision and is not subject to appeal under 43 CFR part 4.

(b) The BLM will consider relevant criteria when prioritizing applications, including the following:

(1) Whether the proposed project is located within an area preferred for solar or wind energy development, such as designated leasing areas, which include solar energy zones, development focus areas, and renewable energy development areas;

(2) Whether the proposed project is likely to avoid adverse impacts to or conflicts with known resources or uses on or adjacent to public lands, and includes specific measures designed to further mitigate impacts or conflicts;

(3) Whether the proposed project is in conformance with the governing BLM land use plans;

(4) Whether the proposed project is consistent with relevant State, Tribal, and local government laws, plans, or priorities;

(5) Whether the proposed project incorporates the best management practices set forth in the applicable BLM land use plans and other BLM plans and policies; and

(6) Any other circumstances or prioritization criteria identified by the BLM in subsequent policy guidance or management direction through land use planning.

(c) The BLM will prioritize your complete application based on all available information, including information you provide to the BLM in the application or in response to deficiency notices, and information provided to the BLM in public meetings or consultations.

(d) The BLM may re-prioritize your application at any time.

[89 FR 35679, May 1, 2024]
§ 2804.40 - Alternative requirements.

If you are unable to meet any of the application requirements in this subpart, you may request approval for an alternative requirement from the BLM. Any such request is not approved until you receive BLM approval in writing. Your request to the BLM must:

(a) Show good cause for your inability to meet a requirement;

(b) Suggest an alternative requirement and explain why that requirement is appropriate; and

(c) Be received in writing by the BLM in a timely manner, before the deadline to meet a particular requirement has passed.

[81 FR 92212, Dec. 19, 2016, as amended at 89 FR 35679, May 1, 2024]
source: 70 FR 21058, Apr. 22, 2005, unless otherwise noted.
cite as: 43 CFR 2804.23