Regulations last checked for updates: Nov 22, 2024
Title 45 - Public Welfare last revised: Nov 19, 2024
§ 900.401 - Notice of intent and scoping.
(a) The Commission shall publish a NOI, as described in 40 CFR 1508.22, in the Federal Register as soon as practicable after a decision is made to prepare an EIS, in accordance with 40 CFR 1501.7. If there will be a lengthy period of time between the Commission's decision to prepare an EIS and its actual preparation, the Commission may defer publication of the NOI until a reasonable time before preparing the EIS, provided that the Commission allows a reasonable opportunity for interested parties to participate in the EIS process. Consistent with § 900.201(b), the Commission and the applicant will coordinate during the time period prior to the publication of the NOI to identify: the scope of the action, potential modifications to the proposal, potential alternatives, environmental constraints, potential timeframes for the environmental review, and federal, state, or tribal entities that could be interested in the project, including those with the potential to become cooperating agencies. Through the NOI, the Commission shall invite comments and suggestions on the scope of the EIS.
(b) Publication of the NOI in the Federal Register shall begin the public scoping process. The public scoping process for a Commission EIS shall allow a minimum of 30 days for the receipt of public comments.
§ 900.402 - Preparation and filing of draft and final EISs.
(a) General. Except for proposals for legislation as provided for in 40 CFR 1506.8, EISs shall be prepared in two stages and may be supplemented.
(b) Format. The EIS format recommended by 40 CFR 1502.10 shall be used unless a determination is made on a particular project that there is a compelling reason to do otherwise. In such a case, the EIS format must meet the minimum requirements prescribed in 40 CFR 1502.10, as further described in 40 CFR 1502.11 through 1502.18.
(c) Applicant role. The draft or final EIS shall be prepared by the Commission with assistance from the applicant under appropriate guidance and direction from the Approving Official.
(d) Third-party consultants. A third-party consultant selected by the Commission or in cooperation with a cooperating agency may prepare the draft or final EIS.
(e) Commission responsibility. The Commission shall provide a schedule with time limits, guidance, participate in the preparation, independently evaluate, and take responsibility for the content of the draft and final EIS.
(f) Filing. After a draft or final EIS has been prepared, the Commission shall file the EIS with the Environmental Protection Agency (EPA). The EPA will publish a notice of availability in accordance with 40 CFR 1506.9 and 1506.10.
(g) Draft to final EIS. When a final EIS does not require substantial changes from the draft EIS, the Commission may document required changes in errata sheets, insertion pages, and revised sections. The Commission will then circulate such changes together with comments on the draft EIS, responses to comments, and other appropriate information as its final EIS. The Commission will not circulate the draft EIS again; however, the Commission will post the EIS on its Web site and provide the draft EIS if requested.
(h) Record of decision. A record of decision (ROD) will be prepared in accordance with 40 CFR 1505.2.
§ 900.403 - Supplemental EIS.
(a) Supplements to either draft or final EISs shall be prepared, as prescribed in 40 CFR 1502.9, when the Commission finds that there are substantial changes are proposed in a project that are relevant to environmental concerns; or when there are significant new circumstances or information relevant to environmental concerns and bearing on the proposed action or its impacts.
(b) Where Commission action remains to be taken and the EIS is more than three years old, the Commission will review the EIS to determine whether it is adequate or requires supplementation.
(c) The Commission shall prepare, circulate and file a supplement to an EIS in the same fashion (exclusive of scoping) as a draft and final EIS. In addition, the supplement and accompanying administrative record shall be included in the administrative record for the proposal. When an applicant is involved, the applicant shall, under the direction of the approving official, provide assistance.
(d) An NOI to prepare a supplement to a final EIS will be published in those cases where a ROD has already been issued.
§ 900.404 - Adoption.
(a) The Commission may adopt a draft or final EIS or portion thereof (see 40 CFR 1506.3), including a programmatic EIS, prepared by another agency.
(b) If the actions covered by the original EIS and the proposal are substantially the same, the Commission shall recirculate it as a final statement. Otherwise, the Commission shall treat the statement as a draft and recirculate it except as provided in paragraph (c) of this section.
(c) Where the Commission is a cooperating agency, it may adopt the EIS of the lead agency without recirculating it when, after an independent review of the EIS, the Commission concludes that its comments and suggestions have been satisfied.
(d) When the Commission adopts an EIS which is not final within the agency that prepared it, or when the action it assesses is the subject of a referral under 40 CFR part 1504, or when the EIS's adequacy is the subject of a judicial action which is not final, the Commission shall so specify.
§ 900.405 - Proposals normally requiring an EIS.
An EIS will normally be required for:
(a) Large scale infrastructure construction efforts such as the relocation of an entire community;
(b) A project that requires a formal consultation under Section 7 of the Endangered Species Act; or
(c) Where implementation of the proposal may directly cause or induce changes that significantly:
(1) Displace population;
(2) Alter the character of existing residential areas; or
(3) Adversely affect a floodplain.
source: 81 FR 53033, Aug. 11, 2016, unless otherwise noted.
cite as: 45 CFR 900.402