(a) NASA has waived the requirement for the submission of certified cost or pricing data when contracting with the Canadian Commercial Corporation (CCC). This waiver applies to the CCC and its subcontractors. The CCC will provide assurance of the fairness and reasonableness of the proposed price. This assurance should be relied on; however, contracting officers shall ensure that the appropriate level of data other than certified cost or pricing data is submitted by subcontractors to support any required proposal analysis, including a technical analysis and a cost realism analysis. The CCC also will provide for follow-up audit activity to ensure that any excess profits are found and refunded to NASA.
(b) NASA has waived the requirement for the submission of certified cost or pricing data when contracting for Small Business Innovation Research (SBIR) program Phase II contracts. However, contracting officers shall ensure that the appropriate level of data other than certified cost or pricing data is submitted to determine price reasonableness and cost realism.
[80 FR 12936, Mar. 12, 2015]
NASA's policy is to pay profit or fee only on definitized contracts.
[65 FR 12485, Mar. 9, 2000]
(e)(1) Make-or-buy programs should not include items or work efforts estimated to cost less than $500,000.
(a) The contracting officer shall insert the provision at 1852.215-78, Make-or-Buy Program Requirements, in solicitations requiring make-or-buy programs as provided in FAR 15.407-2(c). This provision shall be used in conjunction with the clause at FAR 52.215-9, Changes or Additions to Make-or-Buy Program. The contracting officer may add additional paragraphs identifying any other information required in order to evaluate the program.
(b) The contracting officer shall insert the clause at 1852.215-79, Price Adjustment for “Make-or-Buy” Changes, in contracts that include FAR 52.215-9 with its Alternate I or II. Insert in the appropriate columns the items that will be subject to a reduction in the contract value.
(c) When the solicitation requires the submission of certified cost or pricing data, the contracting officer shall include 1852.215-85, Proposal Adequacy Checklist, in the solicitation to facilitate submission of a thorough, accurate, and complete proposal.
[63 FR 9954, Feb. 27, 1998, as amended at 79 FR 10687, Feb. 26, 2014; 81 FR 24501, Apr. 26, 2016]