(1) Higher-level contract quality requirements are used in addition to a standard inspection requirement.
(2) Higher-level contract quality requirements, including nongovernment quality system standards adopted to meet DoD needs, are listed in the DoD Index of Specifications and Standards.
[60 FR 33145, June 27, 1995. Redesignated and amended at 60 FR 61599, Nov. 30, 1995]
This section implements section 807 of the National Defense Authorization Act for Fiscal Year 2010 (Pub. L. 111-84). It establishes policies and procedures intended to ensure the safety and habitability of facilities, infrastructure, and equipment acquired for use by DoD military or civilian personnel during military operations performed outside the United States, Guam, Puerto Rico, and the Virgin Islands.
[75 FR 66685, Oct. 29, 2010]
(a) Contracts (including task and delivery orders) for the construction, installation, repair, maintenance, or operation of facilities, infrastructure, and equipment configured for occupancy, including but not limited to, existing host nation facilities, new construction, and relocatable buildings acquired for use by DoD military or civilian personnel, shall require a pre-occupancy safety and habitability inspection.
(b) To minimize safety and health risks, each contract covered by this policy shall require the contractor's compliance with the Unified Facilities Criteria (UFC) 1-200-01 and its referenced standards for—
(1) Fire protection;
(2) Structural integrity;
(3) Electrical systems;
(4) Plumbing;
(5) Water treatment;
(6) Waste disposal; and
(7) Telecommunications networks.
(c) Existing host nation facilities constructed to standards equivalent to or more stringent than UFC 1-200-01 are acceptable upon a written determination of the acceptability of the standards by the Discipline Working Group.
(d) Inspections to ensure compliance with UFC 1-200-01 standards shall be conducted in accordance with the inspection clause of the contract.
[75 FR 66685, Oct. 29, 2010]
The combatant commander may waive compliance with the foregoing standards when it is impracticable to comply with such standards under prevailing operational conditions.
[75 FR 66685, Oct. 29, 2010]
Use the clause at 252.246-7004, Safety of Facilities, Infrastructure, and Equipment for Military Operations, in solicitations and contracts, including solicitations and contracts using FAR part 12 procedures for the acquisition of commercial products and commercial services, for the construction, installation, repair, maintenance, or operation of facilities, infrastructure, or for equipment configured for occupancy, planned for use by DoD military or civilian personnel during military operations.
[75 FR 66685, Oct. 29, 2010, as amended at 78 FR 37989, June 25, 2013; 88 FR 6588, Jan. 31, 2023]