Regulations last checked for updates: Nov 22, 2024

Title 48 - Federal Acquisition Regulations System last revised: Nov 15, 2024
836.500 - 836.500 Scope of subpart.

The clauses and provisions prescribed in this subpart are set forth for use in fixed-price construction contracts in addition to those prescribed in FAR subpart 36.5.

[84 FR 9972, Mar. 19, 2019]
836.501 - 836.501 Performance of work by the contractor.

The contracting officer shall insert the clause at 852.236-72, Performance of Work by the Contractor, in solicitations and contracts for construction that contain the FAR clause at 52.236-1, Performance of Work by the Contractor, except those awarded pursuant to subpart 819.70. When the solicitations or contracts include a section entitled “Network Analysis System (NAS),” the contracting officer shall use the clause with its Alternate I.

[84 FR 9972, Mar. 19, 2019]
836.521 - 836.521 Specifications and drawings for construction.

The contracting officer shall insert the clause at 852.236-71, Specifications and Drawings for Construction, in solicitations and contracts for construction that include the FAR clause at 52.236-21, Specifications and Drawings for Construction.

[84 FR 9972, Mar. 19, 2019]
836.573 - 836.573 Contractor production report.

The contracting officer shall insert the clause at 852.236-79, Contractor Production Report, in solicitations and contracts for construction expected to exceed the simplified acquisition threshold. The contracting officer may, when in the best interest of the Government, insert the clause in solicitations and contracts for construction when the contract amount is expected to be at or below the simplified acquisition threshold.

[84 FR 9972, Mar. 19, 2019]
836.574 - 836.574 Subcontracts and work coordination.

The contracting officer shall insert the clause at 852.236-80, Subcontracts and Work Coordination, in invitations for bids and contracts for construction expected to exceed the micro-purchase threshold for construction. When the solicitations or contracts are for new construction work with complex mechanical-electrical work, the contracting officer may use the clause with its Alternate I.

[84 FR 9972, Mar. 19, 2019]
836.580 - 836.580 Notice to bidders—additive or deductive bid line items.

The contracting officer may include the provision 852.236-92, Notice to Bidders—Additive or Deductive Bid Line Items, in invitations for bids when the contracting officer determines that funds may not be available for all the desired construction features at contract award.

[84 FR 9972, Mar. 19, 2019]
authority: 40 U.S.C. 121(c); 41 U.S.C. 1121(c)(3), 1303(a)(2) and 1702; and 48 CFR 1.301-1.304
source: 73 FR 2717, Jan. 15, 2008, unless otherwise noted.
cite as: 48 CFR 836.521