Regulations last checked for updates: Nov 22, 2024

Title 49 - Transportation last revised: Nov 18, 2024
§ 271.101 - Risk reduction programs.

(a) Program required. Each railroad shall establish and fully implement an RRP meeting the requirements of this part. An RRP shall systematically evaluate railroad safety hazards on a railroad's system and manage the resulting risks to reduce the number and rates of railroad accidents/incidents, injuries, and fatalities. An RRP is an ongoing program that supports continuous safety improvement. A railroad shall design its RRP so that it promotes and supports a positive safety culture at the railroad. An RRP shall include the following:

(1) A risk-based hazard management program, as described in § 271.103;

(2) A safety performance evaluation component, as described in § 271.105;

(3) A safety outreach component, as described in § 271.107;

(4) A technology analysis and technology implementation plan, as described in § 271.109;

(5) RRP implementation and support training, as described in § 271.111;

(6) Involvement of railroad employees in the establishment and implementation of an RRP, as described in § 271.113; and

(7) An FRMP as described in § 271.607.

(b) RRP plans. A railroad's RRP shall be supported by an FRA-approved RRP plan meeting the requirements of subpart C of this part.

(c) Host railroads and system safety programs. (1) If a railroad subject to this part (RRP railroad) hosts passenger train service for a railroad subject to the system safety program requirements in part 270 of this title (system safety program (SSP) railroad), the RRP railroad shall communicate with the SSP railroad to coordinate the portions of the system safety program applicable to the RRP railroad hosting the passenger train service.

(2) The RRP railroad shall incorporate its communication and coordination with the SSP railroad into its own RRP.

(d) Persons that perform or utilize significant safety-related services. Under § 271.205(a)(3), a railroad's RRP plan shall identify persons that enter into a contractual relationship with the railroad to either perform significant safety-related services on the railroad's behalf or to utilize significant safety-related services provided by the railroad for railroad operations purposes. For example, a railroad's RRP plan shall identify entities such as host railroads, contract operators, shared track/corridor operators, or other contractors utilizing or performing significant safety-related services. A railroad shall identify such persons even if the persons are not required to comply with this part (e.g., a railroad shall identify a tourist railroad that operates over the railroad's track even though the tourist railroad is exempt from this rule under § 271.3(b)(2)). A railroad shall ensure persons performing or utilizing significant safety-related services support and participate in its RRP.

[85 FR 9314, Feb. 18, 2020, as amended at 87 FR 35673, June 13, 2022]
§ 271.103 - Risk-based hazard management program.

(a) General. (1) An RRP shall include an integrated, system-wide, and ongoing risk-based HMP that proactively identifies hazards and mitigates the risks resulting from those hazards.

(2) A risk-based HMP shall be fully implemented (i.e., activities initiated) within 36 months after FRA approves a railroad's RRP plan pursuant to § 271.301(d).

(b) Risk-based hazard analysis. As part of its risk-based HMP, a railroad shall conduct a risk-based hazard analysis that addresses, at a minimum, the following aspects of a railroad's system: Infrastructure; equipment; employee levels and work schedules; operating rules and practices; management structure; employee training; and other areas impacting railroad safety that are not covered by railroad safety laws or regulations or other Federal laws or regulations. A railroad shall make the results of its risk-based hazard analysis available to FRA upon request. At a minimum, a risk-based hazard analysis shall:

(1) Identify hazards by analyzing:

(i) Aspects of the railroad's system, including any operational changes, system extensions, or system modifications; and

(ii) Accidents/incidents, injuries, fatalities, and other known indicators of hazards;

(2) Calculate risk by determining and analyzing the likelihood and severity of potential events associated with identified risk-based hazards; and

(3) Compare and prioritize the identified risks for mitigation purposes.

(c) Mitigation strategies. (1) As part of its risk-based HMP, a railroad shall design and implement mitigation strategies that improve safety by:

(i) Mitigating or eliminating aspects of a railroad's system that increase risks identified in the risk-based hazard analysis; and

(ii) Enhancing aspects of a railroad's system that decrease risks identified in the risk-based hazard analysis.

(2) A railroad may use pilot projects, including pilot projects conducted by other railroads, to determine whether quantitative data suggests that a particular mitigation strategy has potential to succeed on a full-scale basis.

§ 271.105 - Safety performance evaluation.

(a) General. As part of its RRP, a railroad shall develop and maintain ongoing processes and systems for evaluating the safety performance of its system and identifying and analyzing its safety culture. A railroad's safety performance evaluation shall consist of both a safety monitoring and a safety assessment component.

(b) Safety monitoring. A railroad shall monitor the safety performance of its system by, at a minimum, establishing processes and systems to acquire safety data and information from the following sources:

(1) Continuous monitoring of operational processes and systems (including any operational changes, system extensions, or system modifications);

(2) Periodic monitoring of the operational environment to detect changes that may generate new hazards;

(3) Investigations of accidents/incidents, injuries, fatalities, and other known indicators of hazards;

(4) Investigations of reports regarding potential non-compliance with Federal railroad safety laws or regulations, railroad operating rules and practices, or mitigation strategies established by the railroad; and

(5) A reporting system through which employees can report safety concerns (including, but not limited to, hazards, issues, occurrences, and incidents) and propose safety solutions and improvements.

(c) Safety assessment. To assess the need for changes to a railroad's mitigation strategies or overall RRP, a railroad shall establish processes to analyze the data and information collected pursuant to paragraph (b) of this section (as well as any other relevant data regarding its operations, products, and services). At a minimum, this assessment shall:

(1) Evaluate the overall effectiveness of the railroad's RRP in reducing the number and rates of railroad accidents/incidents, injuries, and fatalities;

(2) Evaluate the effectiveness of the railroad's RRP in meeting the goals described by its RRP plan (see § 271.203(c));

(3) Evaluate the effectiveness of risk mitigations in reducing the risk associated with an identified hazard. Any hazards associated with ineffective mitigation strategies shall be reevaluated through the railroad's risk-based HMP, as described in § 271.103; and

(4) Identify new, potential, or previously unknown hazards, which shall then be evaluated by the railroad's risk-based HMP, as described in § 271.103.

§ 271.107 - Safety outreach.

(a) Outreach. An RRP shall include a safety outreach component that communicates RRP safety information to railroad personnel (including contractors) as that information is relevant to their positions. At a minimum, a safety outreach program shall:

(1) Convey safety-critical information;

(2) Explain why RRP-related safety actions are taken; and

(3) Explain why safety procedures are introduced or changed.

(b) Reporting to management. The status of risk-based HMP activities shall be reported to railroad senior management on an ongoing basis.

§ 271.109 - Technology analysis and technology implementation plan.

(a) General. As part of its RRP, a Class I railroad shall conduct a technology analysis and develop and adopt a technology implementation plan no later than February 17, 2023. A railroad with inadequate safety performance shall conduct a technology analysis and develop and adopt a technology implementation plan no later than three years after receiving final written notification from FRA to comply with this part, pursuant to § 271.13(d), or no later than February 17, 2023, whichever is later. A railroad that the STB reclassifies or newly classifies as a Class I railroad shall conduct a technology analysis and develop and adopt a technology implementation plan no later than three years following the effective date of the classification or reclassification or no later than April 18, 2023, whichever is later. A voluntarily-compliant railroad shall conduct a technology analysis and develop and adopt a technology implementation plan no later than three years after FRA approves the railroad's RRP plan.

(b) Technology analysis. A technology analysis shall evaluate current, new, or novel technologies that may mitigate or eliminate hazards and the resulting risks identified through the risk-based HMP. The railroad shall analyze the safety impact, feasibility, and costs and benefits of implementing technologies that will mitigate or eliminate hazards and the resulting risks. At a minimum, the technologies a railroad shall consider as part of its technology analysis are: Processor-based technologies, positive train control systems, electronically-controlled pneumatic brakes, rail integrity inspection systems, rail integrity warning systems, switch position monitors and indicators, trespasser prevention technology, and highway-rail grade crossing warning and protection technology.

(c) Technology implementation plan. A railroad shall develop, and periodically update as necessary, a technology implementation plan that contains a prioritized implementation schedule describing the railroad's plan for development, adoption, implementation, maintenance, and use of current, new, or novel technologies on its system over a 10-year period to reduce safety risks identified in the railroad's risk-based HMP.

(d) Positive train control. Except as required by subpart I of part 236 of this chapter, if a railroad decides to implement positive train control systems as part of its technology analysis and implementation plan, the railroad shall set forth and comply with a schedule for implementation of the positive train control system consistent with the deadlines in the Positive Train Control Enforcement and Implementation Act of 2015, Public Law 114-73, 129 Stat. 576-82 (Oct. 29, 2015), and 49 CFR 236.1005(b)(7).

§ 271.111 - Implementation and support training.

(a) A railroad shall provide RRP training to each employee, including an employee of any person identified by the railroad's RRP plan pursuant to § 271.205(a)(3) as performing significant safety-related services on the railroad's behalf or utilizing significant safety-related services provided by the railroad, who has significant responsibility for implementing and supporting the railroad's RRP. This training shall help ensure that all personnel with significant responsibility for implementing and supporting the RRP understand the goals of the program, are familiar with the elements of the railroad's program, and have the requisite knowledge and skills to fulfill their responsibilities under the program.

(b) A railroad shall keep a record of training conducted under this section and update that record as necessary. A railroad shall make training records available for inspection and copying upon the request of representatives of FRA or States participating under part 212 of this chapter.

(c) Training under this section may include, but is not limited to, interactive computer-based training, video conferencing, or formal classroom training.

§ 271.113 - Involvement of railroad employees.

(a) An RRP shall involve a railroad's directly affected employees in the establishment and implementation of the RRP.

(b) For example, a railroad must have a process for involving directly affected employees when identifying hazards, developing and implementing mitigation strategies, conducting internal annual assessments, or otherwise performing actions required by this part.

source: 85 FR 9314, Feb. 18, 2020, unless otherwise noted.
cite as: 49 CFR 271.111