§ 217.300 - Specified activity and specified geographical region.

(a) This subpart applies to activities associated with the Atlantic Shores South Project (hereafter referred to as the “Project”) by Atlantic Shores Offshore Wind Project 1, LLC (i.e., Project Company 1), a joint venture between EDF-RE Offshore Development LLC (a wholly owned subsidiary of EDF Renewables, Inc.) and Shell New Energies US LLC (and a subsidiary of Atlantic Shores Offshore Wind LLC), collectively and hereafter referred to as the Letter of Authorization Holder, or “LOA Holder”, and those persons it authorizes or funds to conduct activities on its behalf in the area outlined in paragraph (b) of this section. Requirements imposed on LOA Holder must be implemented by those persons it authorizes or funds to conduct activities on its behalf.

(b) The specified geographical region is the Mid-Atlantic Bight, which includes, but is not limited to, the Bureau of Ocean Energy Management (hereafter, “BOEM”) lease areas on the Outer Continental Shelf (hereafter, “OCS”)-A-0499 and OCS-A-0570 Commercial Lease of Submerged Lands for Renewable Energy Development (hereafter, “Lease Areas”), two export cable routes, and two sea-to-shore transition points located at the Atlantic City and the Monmouth landfall locations.

(c) The specified activities are impact pile driving of wind turbine generators (hereafter, “WTG”), offshore substations (hereafter, “OSS”), and a meteorological tower (hereafter, “Met Tower”); vibratory pile driving (installation and subsequent removal) of cofferdams; fishery and ecological monitoring surveys; placement of scour protection; trenching, laying, and burial activities associated with the installation of the export cable from OSSs to shore-based converter stations and inter-array cables between turbines; high-resolution geophysical (hereafter, “HRG”) site characterization surveys; vessel transit within the specified geographical region to transport crew, supplies, and materials; and WTG operation.

§ 217.301 - Effective dates.

This subpart is effective from January 1, 2025, through December 31, 2029.

§ 217.302 - Permissible methods of taking.

Under the LOA, issued pursuant to §§ 216.106 and 217.306, LOA Holder and those persons it authorizes or funds to conduct activities on its behalf may incidentally, but not intentionally, take marine mammals within BOEM Lease Areas, along export cable routes, and the two sea-to-shore transition points located in New Jersey at Atlantic City and Monmouth in the following ways, provided LOA Holder is in complete compliance with all terms, conditions, and requirements of the regulations in this subpart and the appropriate LOA:

(a) By Level B harassment associated with the acoustic disturbance resulting from impact pile driving of WTG, OSS, and Met Tower foundations, vibratory pile driving of temporary cofferdams, and HRG site characterization surveys; and

(b) By Level A harassment associated with the acoustic injury of marine mammals by impact pile driving WTG, OSS, and Met Tower foundations.

(c) Take by mortality (death) or serious injury of any marine mammal species is not authorized.

(d) The incidental take of marine mammals by the activities listed in paragraphs (a) and (b) of this section is limited to the following stocks:

Table 1 to Paragraph (d)

Marine mammal species Scientific name Stock
North Atlantic right whaleEubalaena glacialisWestern North Atlantic.
Fin whaleBalaenoptera physalusWestern North Atlantic.
Humpback whaleMegaptera novaeangliaeGulf of Maine.
Minke whaleBalaenoptera acutorostrataCanadian Eastern Coastal.
Sei whaleBalaenoptera borealisNova Scotia.
Sperm whalePhyseter macrocephalusNorth Atlantic.
Atlantic spotted dolphinStenella frontalisWestern North Atlantic.
Atlantic white-sided dolphinLagenorhynchus acutusWestern North Atlantic.
Bottlenose dolphinTursiops truncatusWestern North Atlantic—Offshore.
Northern Migratory Coastal.
Common dolphinDelphinus delphisWestern North Atlantic.
Long-finned pilot whaleGlobicephala melasWestern North Atlantic.
Short-finned pilot whaleGlobicephala macrorhynchusWestern North Atlantic.
Risso's dolphinGrampus griseusWestern North Atlantic.
Harbor porpoisePhocoena phocoenaGulf of Maine/Bay of Fundy.
Gray sealHalichoerus grypusWestern North Atlantic.
Harbor sealPhoca vitulinaWestern North Atlantic.
§ 217.303 - Prohibitions.

Except for the takings described in § 217.302 and authorized by LOA issued under § 217.306 or § 217.307, it is unlawful for any person to do any of the following in connection with the activities described in this subpart:

(a) Violate, or fail to comply with, the terms, conditions, and requirements of this subpart or LOA issued under § 217.306 or § 217.307;

(b) Take any marine mammal not specified in § 217.302(d);

(c) Take any marine mammal specified in the LOA in any manner other than as specified in the LOA; or

(d) Take any marine mammal specified in § 217.302(d), after NMFS determines such taking results in more than a negligible impact on the species or stocks of such marine mammals.

§ 217.304 - Mitigation requirements.

When conducting the activities identified in § 217.300(c) within the area described in § 217.300(b), LOA Holder must implement the mitigation measures contained in this section and any LOA issued under §§ 217.306 or 217.307. These mitigation measures include, but are not limited to:

(a) General conditions. LOA Holder must comply with the following general measures:

(1) A copy of any issued LOA must be in the possession of LOA Holder and its designees, all vessel operators, visual protected species observers (PSOs), passive acoustic monitoring (PAM) operators, pile driver operators, and any other relevant designees operating under the authority of the issued LOA;

(2) LOA Holder must conduct training for construction, survey, vessel personnel, and the marine mammal monitoring team (PSO and PAM operators) prior to the start of all in-water activities in order to explain responsibilities, communication procedures, marine mammal detection and identification, mitigation, monitoring, and reporting requirements, safety and operational procedures, and authorities of the marine mammal monitoring team(s). This training must be repeated for new personnel who join the work during the Project. A description of the training program must be provided to NMFS at least 60 calendar days prior to the initial training before in-water activities begin. NMFS Office of Protected Resources will review, provide comments (if warranted) and approve the training program prior to on-water construction beginning. Confirmation of all required training must be documented on a training course log sheet and reported to NMFS Office of Protected Resources prior to initiating Project activities;

(3) Prior to and when conducting any in-water specified activities and vessel operations, LOA Holder personnel and contractors (e.g., vessel operators, PSOs) must use available sources of information on North Atlantic right whale presence in or near the Project Area including daily monitoring of the Right Whale Sightings Advisory System, NMFS' website at: https://www.fisheries.noaa.gov/national/endangered-species-conservation/reducing-vessel-strikes-north-atlantic-right-whales, and monitoring the U.S. Coast Guard's VHF Channel 16 throughout the day to receive notification of any sightings and/or information associated with any Slow Zones (i.e., Dynamic Management Areas (DMAs) and/or acoustically-triggered Slow Zones) to provide situational awareness for both vessel operators, PSO(s) and PAM operator(s) teams. The marine mammal monitoring team must monitor these systems no less than every 4 hours every day;

(4) Any marine mammal observed by Project personnel must be immediately communicated to any on-duty PSO(s), PAM operator(s), and all vessel captains. Any large whale observation or acoustic detection by a PSO(s) or a PAM operator(s) must be conveyed to all vessel captains;

(5) For North Atlantic right whales, any visual detection by a PSO or acoustic detection by a PAM operator at any distance (where applicable for the specified activities) within the PAM Clearance/Shutdown Zone must trigger a delay to the commencement of pile driving and HRG surveys;

(6) In the event that a large whale is sighted or acoustically detected that cannot be confirmed as a non-North Atlantic right whale, it must be treated as if it were a North Atlantic right whale for purposes of mitigation;

(7) Any PSO has the authority to call for a delay or shutdown of Project activities. If a delay to commencing an activity is called for by a PSO, LOA Holder must take the required mitigative action. If a shutdown of an activity is called for by a PSO, LOA Holder must take the required mitigative action unless shutdown would result in imminent risk of injury or loss of life to an individual(s), pile refusal, or pile instability. Any disagreements between the Lead PSO and the activity operator or between the Lead PSO and another PSO/PAM operator regarding delays or shutdowns must only be discussed after the mitigative action has occurred;

(8) Any marine mammals observed within a clearance or shutdown zone must leave (of their own volition) prior to commencing pile driving activities or HRG surveys;

(9) If an individual from a species for which authorization has not been granted, or a species for which authorization has been granted but the authorized take number has been met, is observed entering or within the relevant clearance zone prior to beginning a specified activity, the activity must be delayed. If an activity is ongoing and an individual from a species for which authorization has not been granted, or a species for which authorization has been granted but the authorized take number has been met, is observed entering or within the relevant shutdown zone, the activity must be shut down (i.e., cease) immediately, unless shutdown would result in imminent risk of injury or loss of life to an individual(s), pile refusal, or pile instability. The activity must not commence or resume until the animal(s) has been confirmed to have left the clearance or shutdown zones and is on a path away from the applicable zone or after 15 minutes with no further sightings for small odontocetes and pinnipeds or 30 minutes with no further sightings for all other species;

(10) For in-water construction heavy machinery activities listed in § 217.300(c), if a marine mammal is on a path towards or comes within 10 meters (m) (32.8 feet (ft)) of equipment, LOA Holder must cease operations until the marine mammal has moved more than 10 m on a path away from the activity to avoid direct interaction with equipment;

(11) All vessels must be equipped with a properly installed, operational Automatic Identification System (AIS) device and LOA Holder must report all Maritime Mobile Service Identity (MMSI) numbers to NMFS Office of Protected Resources ([email protected]) prior to initial vessel transit;

(12) By accepting the LOA, LOA Holder consents to on-site observation and inspections by Federal agency personnel (including NOAA personnel) during activities described in this subpart, for the purposes of evaluating the implementation and effectiveness of measures contained within the LOA and this subpart; and

(13) It is prohibited to assault, harm, harass (including sexually harass), oppose, impede, intimidate, impair, or in any way influence or interfere with a PSO, PAM Operator, or vessel crew member acting as an observer, or attempt the same. This prohibition includes, but is not limited to, any action that interferes with an observer's responsibilities, or that creates an intimidating, hostile, or offensive environment. Personnel may report any violations to the NMFS Office of Law Enforcement.

(b) Vessel strike avoidance measures. LOA Holder must comply with the following vessel strike avoidance measures while in the specific geographic region, unless a deviation is necessary to maintain safe maneuvering speed and justified because the vessel is in an area where oceanographic, hydrographic, and/or meteorological conditions severely restrict the maneuverability of the vessel; an emergency situation presents a threat to the health, safety, or life of a person(s); or when a vessel is actively engaged in emergency rescue or response duties, including vessel-in distress or environmental crisis response. An emergency is defined as a serious event that occurs without warning and requires immediate action to avert, control, or remedy harm. Speed over ground will be used to measure all vessel speeds:

(1) Prior to the start of the Project's activities involving vessels, all vessel personnel must receive a protected species training that covers, at a minimum, identification of marine mammals that have the potential to occur where vessels would be operating; detection and observation methods in both good weather conditions (i.e., clear visibility, low winds, low sea states) and bad weather conditions (i.e., fog, high winds, high sea states, with glare); sighting communication protocols; all vessel speed and approach limit mitigation requirements (e.g., vessel strike avoidance measures); and information and resources available to the Project personnel regarding the applicability of Federal laws and regulations for protected species. This training must be repeated for any new vessel personnel who join the Project. Confirmation of the vessel personnel's training and understanding of the Incidental Take Authorization (hereafter, “ITA”) requirements must be documented on a training course log sheet and reported to NMFS within 30 calendar days of completion of training;

(2) All vessel operators, operating at any speed and regardless of their vessel's size, must slow down, stop their vessel, or alter course to avoid striking any marine mammal;

(3) While in transit, all vessels, regardless of their size, must have a dedicated visual observer aboard and on duty at all times whose sole responsibility (i.e., must not have duties other than observing) is to monitor for marine mammals within a 180 degrees (hereafter, “°”) direction of the forward path of the vessel (90° port to 90° starboard) located at an appropriate vantage point for ensuring vessels are maintaining appropriate separation distances. Visual observers must be equipped with alternative monitoring technology (e.g., night vision devices, infrared cameras) for periods of low visibility (e.g., darkness, rain, fog, etc.). The dedicated visual observer must receive prior training on protected species detection and identification, vessel strike minimization procedures, how and when to communicate with the vessel captain, and reporting requirements in this subpart. These visual observers may be third-party observers (i.e., NMFS-approved PSOs; see § 217.305(a)) or trained crew members (see paragraph (b)(1) of this section);

(4) At the onset of transiting and continuously thereafter, vessel operators must monitor the U.S. Coast Guard's VHF Channel 16, over which North Atlantic right whale sightings are broadcasted. At the onset of transiting and at least once every 4 hours, vessel operators and/or trained crew member(s) must also monitor the Project's Situational Awareness System (if applicable), WhaleAlert, NMFS' website at: https://www.fisheries.noaa.gov/national/endangered-species-conservation/reducing-vessel-strikes-north-atlantic-right-whales, and relevant NOAA information systems such as the Right Whale Sighting Advisory System (hereafter, “RWSAS”) for the presence of North Atlantic right whales;

(5) Any large whale sighting by any Project-personnel, including any LOA Holder staff, contractors, or vessel crew, must be immediately communicated to all Project-associated vessel operators, PSOs, and PAM operators for situational awareness. Conversely, any large whale observation or detection via a sighting network (e.g., Mysticetus or similar software) by PSOs or PAM operators must be conveyed to vessel operator(s) and crew. An ongoing large whale sighting log sheet must be maintained on each vessel and retained for vessel operator(s) review each day prior to first day's transit for awareness of recent sightings;

(6) All vessel operators must abide by existing applicable vessel speed regulations (see 50 CFR 224.105). Nothing in this subpart exempts vessels from any other applicable marine mammal speed or approach regulations;

(7) Vessels must transit at 10 kn (11.5 mph) or less within any active North Atlantic right whale Slow Zone (i.e., Dynamic Management Areas (hereafter, “DMA”) or acoustically triggered slow zone);

(8) All vessel operators, regardless of their vessel's size, must immediately reduce vessel speed to 10 kn (11.5 mph) or less for at least 24 hours when a North Atlantic right whale is sighted at any distance by any Project-related personnel or acoustically detected by any Project-related PAM system. Each subsequent observation or acoustic detection in the Project Area shall trigger an additional 24-hour period. If a North Atlantic right whale is reported by Project personnel or via any of the monitoring systems (refer back to paragraph (b)(4) of this section) that vessel must operate at 10 kn (11.5 mph) or less for 24 hours following the reported detection;

(9) All vessels, regardless of size, must immediately reduce speed to 10 kn (11.5 mph) or less when any large whale, mother/calf pairs, or large assemblages of cetaceans are observed within 500 m (1,640 ft) of an underway vessel;

(10) If vessel(s) are traveling at speeds greater than 10 kn (11.5 mph) (i.e., during periods where no other speed restrictions are enacted) in the transit corridor (defined as from a port to the Lease Areas or return), in addition to the required dedicated visual observer, LOA Holder must monitor the transit corridor in real-time with PAM prior to and during transits. If a North Atlantic right whale is detected via visual observation or PAM detection within or approaching the transit corridor, all vessels in the transit corridor must travel at 10 kn (11.5 mph) or less for 24 hours following the detection. Each subsequent detection shall trigger a 24-hour reset. A slowdown in the transit corridor expires when there has been no further visual or acoustic detection in the transit corridor in the past 24 hours;

(11) All vessels must maintain a minimum separation distance of 500 m (1,640 ft) from North Atlantic right whales. If underway, all vessels must steer a course away from any sighted North Atlantic right whale at 10 kn (11.5 mph) or less such that the 500-m (1,640-ft) minimum separation distance requirement is not violated. If a North Atlantic right whale is sighted within 500 m (1,640 ft) of an underway vessel, that vessel operator must reduce speed and shift the engine to neutral. Engines must not be engaged until the whale has moved outside of the vessel's path and beyond 500 m (1,640 ft). If a large whale is observed but cannot be confirmed as a species other than a North Atlantic right whale, the vessel operator must assume that it is a North Atlantic right whale and take the vessel strike avoidance measures described in this paragraph;

(12) All vessels must maintain a minimum separation distance of 500 m (1,640 ft) from all ESA-listed large whales (i.e., sperm whales, fin whales, sei whales). If one of these species is sighted within 500 m (1,640 ft) of a transiting vessel, the vessel must shift the engine(s) to neutral. Engines must not be engaged until the whale has moved outside of the vessel's path and beyond 500 m (1,640 ft);

(13) All vessels must maintain a minimum separation distance of 100 m (328 ft) from all non-ESA-listed large whales (i.e., humpback whales and minke whales). If one of these species is sighted within 100 m (328 ft) of a transiting vessel, the vessel must shift the engine(s) to neutral. Engines must not be engaged until the whale has moved outside of the vessel's path and beyond 100 m (328 ft);

(14) All vessels must maintain a minimum separation distance of 50 m (164 ft) from all delphinid cetaceans and pinnipeds with an exception made for those that approach the vessel (i.e., bow-riding dolphins). If a delphinid cetacean or pinniped is sighted within 50 m (164 ft) of a transiting vessel, the vessel must shift the engine to neutral, with an exception made for those that approach the vessel (e.g., bow-riding dolphins). Engines must not be engaged until the animal(s) has moved outside of the vessel's path and beyond 50 m (164 ft);

(15) When a marine mammal(s) is sighted while the vessel(s) is transiting, the vessel must take action as necessary to avoid violating the relevant separation distances (e.g., attempt to remain parallel to the animal's course, slow down, and avoid abrupt changes in direction until the animal has left the area). This measure does not apply to any vessel towing gear or any situation where respecting the relevant separation distance would be unsafe (i.e., any situation where the vessel is navigationally constrained);

(16) All vessels underway must not divert or alter course to approach any marine mammal;

(17) Vessel operators must check, daily, for information regarding the establishment of mandatory or voluntary vessel strike avoidance areas (i.e., Dynamic Management Areas (DMAs), Seasonal Management Areas (SMAs), Slow Zones) and any information regarding North Atlantic right whale sighting locations; and

(18) LOA Holder must submit a North Atlantic Right Whale Vessel Strike Avoidance Plan (hereafter, “VSAP”) to NMFS Office of Protected Resources for review and approval at least 180 calendar days prior to the planned start of vessel activity. The VSAP must provide details on the vessel-based observer and PAM protocols for transiting vessels in the vessel transit corridor. If the VSAP is not submitted and approved by NMFS prior to vessel operations, all Project vessels must travel at speeds of 10 kn (11.5 mph) or less. LOA Holder must comply with any approved VSAP.

(c) WTG, OSS, and Met Tower foundation installation. LOA Holder must comply with the following WTG, OSS, and Met Tower foundation installation measures unless doing so could result in imminent risk of injury or loss of life to an individual or risk of damage to a vessel that creates risk of injury or loss of life for individuals, or the lead engineer determines there is risk of pile refusal or pile instability:

(1) Foundation installation via impact pile driving must not occur December 1st through April 30th, annually, wherein foundation installation via impact pile driving must be avoided in December unless necessary to complete Project 1 or Project 2 in a given year and after receipt of prior approval by NMFS. Before any December pile driving may occur, and for NMFS Office of Protected Resources to fully evaluate this request, LOA Holder is required to provide a written request by October 15th, which must include, but is not limited to the following information: the installation schedule and types of piles to be installed, the maximum number of piles anticipated to be installed in December, and any planned or additional practicable mitigative measures that could be implemented to further reduce activities to North Atlantic right whales and other marine mammal species;

(2) Monopiles must be no larger than 15-m in diameter, representing the larger end of the planned monopile design. During all monopile installation, the minimum amount of hammer energy necessary to effectively and safely install and maintain the integrity of the piles must be used. Hammer energies must not exceed 4,400 kilojoules (kJ) for monopile installation. No more than two monopiles may be installed per day;

(3) Pin piles must be no larger than 5-m in diameter. During all pin pile installation, the minimum amount of hammer energy necessary to effectively and safely install and maintain the integrity of the piles must be used. Hammer energies must not exceed 2,500 kJ for pin pile installation. No more than four pin piles may be installed per day;

(4) LOA Holder must only perform foundation pile driving during daylight hours, defined as no earlier than 1 hour prior to civil sunset or later than 1.5 hours prior to civil sunrise, and may only continue pile driving into darkness if stopping operations represents a risk to human health, safety, and/or pile stability, unless the LOA Holder submits, and NMFS approves, an Alternative Monitoring Plan, which would allow pile driving to begin after daylight hours have ended. Until this is submitted, reviewed, and approved by NMFS, LOA Holder may not begin any new pile driving outside of the daylight hours previously defined in this subsection;

(5) Soft-start must occur at the beginning of impact driving and at any time following a cessation of impact pile driving of 30 minutes or longer;

(6) Monitoring of the clearance zones must begin 60 minutes immediately prior to initiation of pile driving. The shutdown zones must be monitored during all pile driving. If a marine mammal is detected within or about to enter the applicable clearance zones 30 minutes prior to the beginning of pile driving (including soft-start if impact pile driving) or during pile driving, pile driving must be delayed or shutdown until the animal has been visually observed exiting the clearance zone or until a specific time period has elapsed with no further sightings. The specific time periods are 15 minutes for small odontocetes and pinnipeds, and 30 minutes for all other species;

(7) For North Atlantic right whales, any visual observation by a PSO or acoustic detection within 10 km (6.21 mi) must trigger a delay to the commencement of pile driving. Pile driving may only commence if no North Atlantic right whale visual or acoustic detections have occurred within the clearance zones during the 60-minute monitoring period;

(8) LOA Holder must deploy at least two fully functional noise abatement systems during all foundation pile driving;

(i) A single bubble curtain must not be used;

(ii) Any bubble curtain(s) must distribute air bubbles using an air flow rate of at least 0.5 m 3/(minute*m). The bubble curtain(s) must surround 100 percent of the piling perimeter throughout the full depth of the water column. In the unforeseen event of a single compressor malfunction, the offshore personnel operating the bubble curtain(s) must adjust the air supply and operating pressure such that the maximum possible sound attenuation performance of the bubble curtain(s) is achieved;

(iii) The lowest bubble ring must be in contact with the seafloor for the full circumference of the ring, and the weights attached to the bottom ring must ensure 100-percent seafloor contact;

(iv) No parts of the ring or other objects may prevent full seafloor contact with a bubble curtain ring;

(v) A full maintenance check (e.g., manually clearing holes) must occur prior to each pile being installed;

(vi) LOA Holder must inspect and carry out appropriate maintenance on the noise attenuation system prior to every pile driving event and prepare and submit a Noise Attenuation System (NAS) inspection/performance report. For piles for which thorough SFV is carried out, this report must be submitted as soon as it is available, but no later than when the interim SFV report is submitted for the respective pile. Performance reports for piles monitoring with abbreviated SFV must be submitted with the weekly pile driving reports;

(vii) Corrections to the bubble ring(s) to meet the performance standards in paragraph (c)(9) of this section must occur prior to impact pile driving of foundation piles; and

(viii) For any noise mitigation device used in addition to the double bubble curtain, LOA Holder must inspect and carry out maintenance on the system and ensure the system is functioning properly prior to every pile driving event.

(9) LOA Holder must utilize PAM systems, as described in a NMFS-approved PAM Plan. The PAM system components (i.e., acoustic buoys) must not be placed closer than 1 km (0.6 mi) to the pile being driven so that the activities do not mask the PAM system. LOA Holder must demonstrate and prove the detection range of the system they plan to deploy while considering potential masking from pile-driving and vessel noise. The PAM system must be able to:

(i) Detect all marine mammals;

(ii) Maximize baleen whale detections; and

(iii) Must be capable of detecting North Atlantic right whales at 10 km (6.21 mi).

(10) Concurrently, LOA Holder must utilize PSO(s) and PAM operator(s), as described in § 217.305(c). PAM operators must be deployed and monitoring for marine mammals in accordance with a NMFS-approved PAM Plan. If a marine mammal is detected (visually or acoustically entering or within the respective shutdown zone after pile driving has begun, the PSO must call for a shutdown of pile driving and LOA Holder must stop pile driving immediately. If pile driving is not shut down due to a safety or pile instability/refusal situation, LOA Holder must reduce hammer energy to the lowest level practicable and the reason(s) for not shutting down must be documented and reported to NMFS Office of Protected Resources within the applicable monitoring reports (e.g., weekly, monthly);

(11) If a marine mammal is detected (visually or acoustically) entering or within the respective shutdown zone after pile driving has begun, the PSO must call for a shutdown of pile driving and LOA Holder must stop pile driving immediately. If pile driving is not shut down due to a safety or pile instability/refusal situation, LOA Holder must reduce hammer energy to the lowest level practicable and the reason(s) for not shutting down must be documented and reported to NMFS Office of Protected Resources within the applicable monitoring reports (e.g., weekly, monthly) (see § 217.305(g));

(12) A visual observation at any distance from a PSO or an acoustic detection of a North Atlantic right whale within the 10 km (6.21 mi) PAM Clearance/Shutdown Zone triggers shutdown requirements under paragraph (c)(11) of this section. If pile driving has been shut down due to the presence of a North Atlantic right whale, pile driving may not restart until the North Atlantic right whale has neither been visually nor acoustically detected for 30 minutes;

(13) If pile driving has been shut down due to the presence of a marine mammal other than a North Atlantic right whale, pile driving must not restart until either the marine mammal(s) has voluntarily left the specific clearance zones and has been visually or acoustically confirmed beyond that clearance zone, or when specific time periods have elapsed with no further sightings or acoustic detections have occurred. The specific time periods are 15 minutes for small odontocetes and pinnipeds, and 30 minutes for all other marine mammal species. In cases where these criteria are not met, pile driving may restart only if necessary to maintain pile stability or avoid refusal, during which time LOA Holder must use the lowest hammer energy practicable;

(14) LOA Holder must conduct thorough sound field verification (hereafter, “SFV”) measurements during pile driving activities associated with the installation of, at minimum, the first three monopile foundations installed each calendar year and the first three jacket foundations (inclusive of all pin piles installed for a given jacket foundation). For all thorough SFV, measurements must continue until at least three monopiles and three jacket foundations demonstrate distances to harassment thresholds are at or below those modeled, assuming 10 decibels (hereafter, “dB”) of attenuation. Subsequent thorough SFV measurements are also required should larger piles be installed or if additional foundations are driven that may produce louder sound fields than those previously measured (e.g., higher hammer energy, greater number of strikes, etc.). All thorough SFV measurements must be conducted as follows:

(i) Measurements must be made at a minimum of four distances from the foundation(s) being driven, along a single transect, in the direction of lowest transmission loss, including, but not limited to, 750 m (2,460 ft) and three additional ranges, including, at least, the applicable modeled Level B harassment isopleth, assuming 10 dB attenuation. At least one additional measurement at an azimuth 90 degrees from the array at 750 m (2,460 ft) must be made. At each location, there must be a near bottom and mid-water column hydrophone;

(ii) The recordings must be continuous throughout the duration of all pile driving of each pile for a given foundation;

(iii) The SFV measurement systems must have a sensitivity appropriate for the expected sound levels from pile driving received at the nominal ranges throughout the installation of the pile(s). The frequency range of SFV measurement systems must cover the range of at least 20 hertz (hereafter, “Hz”) to 20 kilohertz (hereafter, “kHz”). The SFV measurement systems must be designed to have omnidirectional sensitivity so that the broadband received level of all pile driving exceeds the system noise floor by at least 10 dB. The dynamic range of the SFV measurement system must be sufficient such that, at each piling location, the signals must avoid poor signal-to-noise ratios for low amplitude signals and avoid clipping, nonlinearity, and saturation for high amplitude signals;

(iv) All hydrophones used in SFV measurements systems are required to have undergone a full system, traceable laboratory calibration conforming to International Electrotechnical Commission (hereafter, “IEC”) 60565, or an equivalent standard procedure, from a factory or accredited source to ensure the hydrophone receives accurate sound levels, at a date not to exceed 2 years before deployment. Additional in-situ calibration checks using a pistonphone are required to be performed before and after each hydrophone deployment. If the measurement system employs filters via hardware or software (e.g., high-pass, low-pass, etc.), which are not already accounted for by the calibration, the filter performance (i.e., the filter's frequency response) must be known, reported, and the data corrected before analysis;

(v) LOA Holder must be prepared with additional equipment (e.g., hydrophones, recording devices, hydrophone calibrators, cables, batteries, etc.), which exceeds the amount of equipment necessary to perform the measurements, such that technical issues can be mitigated before measurement; and

(vi) LOA Holder must submit interim thorough SFV reports within 48 hours after each foundation is measured (see § 217.305(g) for interim reporting requirements).

(15) For thorough SFV on monopile and jacket foundations:

(i) If any of the thorough SFV measurements from any foundation (monopile or jacket) indicate the distances to NMFS' marine mammal Level A harassment or Level B harassment thresholds, assuming 10-dB attenuation, are greater than those modeled, before the next foundation is installed, LOA Holder must identify and propose for review and concurrence: additional, modified, and/or alternative noise attenuation measures or operational changes that present a reasonable likelihood of reducing sound levels to the modeled distances on subsequent foundations; provide a written explanation to NMFS Office of Protected Resources supporting that determination and requesting concurrence to proceed; and, following NMFS Office of Protected Resource's concurrence, deploy those additional measure or modifications on any subsequent foundation that are installed;

(A) LOA Holder must also increase clearance and shutdown zone sizes to those identified by NMFS Office of Protected Resources. For every 1,500 m (4,921.3 ft) that a marine mammal clearance or shutdown zone is expanded, additional PSOs must be deployed from additional platforms/vessels to ensure adequate and complete monitoring of the expanded shutdown and/or clearance zone;

(B) Following installation of the foundation with additional, alternative, or modified noise attenuation measures/operational changes, SFV must be conducted on two additional foundations. If the SFV results from all three of those foundations are within the distances to isopleths of concern modeled assuming 10 dB attenuation, LOA Holder must continue to implement the approved additional, alternative, or modified sound attenuation measures/operational changes;

(C) If, after all practicable measures that could be taken to reduce noise levels have been successfully implemented and exhausted, thorough SFV measurements continue to indicate that the distances to the marine mammal harassment thresholds are greater than those modeled assuming 10 dB attenuation, LOA Holder must consult with NMFS Office of Protected Resources to evaluate the circumstances before additional piles are installed; and

(ii) If, through SFV indicate that ranges to isopleths corresponding to the Level A harassment and/or Level B harassment thresholds are less than those predicted by modeling (assuming 10-dB attenuation), LOA Holder may request a modification of the minimum visibility, clearance, and shutdown zones from NMFS Office of Protected Resources. For NMFS Office of Protected Resources to consider a modification request for reduced zone sizes, LOA Holder must have conducted thorough SFV measurements on three foundations and ensure that subsequent foundations would be installed under conditions that are predicted to produce smaller harassment zones than those modeled assuming 10-dB of attenuation, provided LOA Holder continue to implement the approved additional, alternative, or modified sound attenuation measures/operational changes.

(16) LOA Holder must conduct abbreviated SFV monitoring, consisting of a single acoustic recorder with a bottom and midwater hydrophone, placed at an appropriate distance from each pile driven foundation installations, on all foundations for which thorough SFV monitoring, as described in paragraph (c)(15) of this section, is not performed. Results of abbreviated SFV monitoring must be included in the weekly pile driving reports;

(i) Abbreviated SFV monitoring duration and equipment must comply with the conditions specified in paragraphs (c)(14)(ii) through (v) of this section; and

(ii) If the results of abbreviated SFV monitoring indicate that distances to the identified Level A and Level B harassment thresholds for marine mammals may have been exceeded during the pile driving event, LOA Holder must notify NMFS Office of Protected Resources as soon as possible after receiving such results, and include an explanation of suspected or identified factors that contributed to the potential exceedance and corrective actions that were taken, or planned to be taken, to avoid potential exceedance on subsequent piles. Additional actions may include: adjustments or additions to the noise attenuation system or pile driving operations and/or additional thorough SFV monitoring.

(17) LOA Holder must conduct SFV measurements during turbine operations to estimate turbine operational source levels and transmission loss rates in accordance with an NMFS-approved SFV Plan;

(18) LOA Holder must submit a SFV Plan to NMFS Office of Protected Resources for review and approval at least 180 calendar days prior to planned start of foundation installation activities and abide by the SFV Plan, if approved. At minimum, the SFV Plan must describe how thorough and abbreviated SFV would be conducted, and if the first three monopile foundation/first three entire jacket foundations (inclusive of all pin piles for a given jacket foundation) installation sites selected for thorough SFV measurements are representative of the remainder of the monopile and jacket foundation installation sites or include information in the SFV Plan on which additional sites/scenarios would be selected for thorough SFV measurements. This SFV Plan must also describe approaches that LOA Holder could take to adjust noise attenuation systems or add systems in the case that any SFV measurements obtained demonstrate that noise levels are above those modeled (assuming 10 dB of attenuation). Prior to operations for each Project, the SFV Plan must also include how operational noise would be monitored. Operational parameters (e.g., direct drive information, turbine rotation rate) as well as sea state conditions and information on nearby anthropogenic activities (e.g., vessels transiting or operating in the area) must be reported. Additionally, the SFV Plan must also include methodology for collecting, analyzing, and preparing thorough and abbreviated SFV measurement data for submission to NMFS Office of Protected Resources and describe how the effectiveness of the sound attenuation methodology would be evaluated based on the results. Pile driving may not occur until NMFS approves the SFV Plan;

(19) LOA Holder must submit a Foundation Installation Pile Driving Marine Mammal Monitoring Plan to NMFS Office of Protected Resources for review and approval at least 180 calendar days prior to planned start of foundation pile driving and abide by the Foundation Installation Pile Driving Marine Mammal Monitoring Plan if approved. LOA Holder must obtain both NMFS Office of Protected Resources and NMFS Greater Atlantic Regional Fisheries Office Protected Resources Division's concurrence with this Plan prior to the start of any pile driving. The Plan must include, but is not limited to, the following: the final pile driving Project design (e.g., number and type of piles, hammer type, noise abatement systems, anticipated start date, etc.) and a description of all monitoring equipment and PAM operator and PSO protocols (including number and location of PSOs and PAM operators) for all foundation pile driving. No foundation pile installation can occur without NMFS' approval of the Foundation Installation Pile Driving Marine Mammal Monitoring Plan. More information on what this Plan must include can be found in the LOA; and

(20) LOA Holder must submit a Passive Acoustic Monitoring Plan (hereafter, “PAM Plan”) to NMFS Office of Protected Resources for review and approval at least 180 calendar days prior to the planned start of foundation installation activities and abide by the PAM Plan, if approved. The PAM Plan must include a description of all proposed PAM equipment, address how the proposed passive acoustic monitoring must follow standardized measurement, processing methods, reporting metrics, and metadata standards for offshore wind. The PAM Plan must describe all proposed PAM equipment, procedures, and protocols including proof that vocalizing North Atlantic right whales will be detected within the clearance and shutdown zones. No pile installation can occur if LOA Holder's PAM Plan does not receive approval from NMFS Office of Protected Resources and NMFS Greater Atlantic Regional Fisheries Office Protected Resources Division.

(d) Cofferdam installation and removal. The following requirements apply to the installation and removal of cofferdams at the cable landfall construction sites:

(1) Installation of cofferdams must not occur during nighttime hours (defined as the hours between 1.5 hours prior to civil sunset and 1 hour after civil sunrise);

(2) LOA Holder must establish and implement clearance zones for the installation and removal of cofferdams using visual monitoring. These zones must be measured using the radial distance from the cofferdam being installed and/or removed;

(3) LOA Holder must utilize PSO(s), as described in § 217.305(d). At least two on-duty PSOs must monitor for marine mammals at least 30 minutes before, during, and 30 minutes after vibratory pile driving associated with cofferdam installation;

(4) If a marine mammal(s) is observed entering or is observed within the clearance zones, before vibratory pile driving has begun, the activity must not commence until the animal(s) has exited the zone or a specific amount of time has elapsed since the last sighting. The specific time periods are 15 minutes for small odontocetes and pinnipeds and 30 minutes for all other marine mammal species;

(5) If a marine mammal is observed entering or within the respective shutdown zone after vibratory pile driving has begun, the PSO must call for a shutdown of vibratory pile driving. LOA Holder must stop pile driving immediately unless shutdown is not practicable due to imminent risk of injury or loss of life to an individual or if there is a risk of damage to the vessel that would create a risk of injury or loss of life for individuals or if the lead engineer determines there is refusal or instability. In any of these situations, LOA Holder must document the reason(s) for not shutting down and report the information to NMFS Office of Protected Resources in the annual report (as described in § 217.305(h)). In cases where shutdown is not feasible, pile driving may restart only if necessary to maintain pile stability at which time LOA Holder must use the lowest energy practicable to maintain stability; and

(6) Vibratory pile driving must not restart until either the marine mammal(s) has voluntarily left the specific clearance zones and has been visually confirmed beyond that clearance zone or when specific time periods have elapsed with no further sightings or acoustic detections have occurred. The specific time periods are 15 minutes for small odontocetes and pinnipeds and 30 minutes for all other marine mammal species.

(e) HRG surveys. The following requirements apply to HRG surveys operating sub-bottom profilers (hereinafter, “acoustic sources”) (i.e., sparkers and Compressed High Intensity Radiated Pulse (CHIRPs)):

(1) LOA Holder must establish and implement clearance and shutdown zones for HRG surveys using visual monitoring, as described in paragraph (c) of this section;

(2) LOA Holder must utilize PSO(s), as described in § 217.305(e);

(3) LOA Holder must abide by the relevant Project Design Criteria (hereafter, “PDCs”; specifically, PDCs 4, 5, and 7) of the programmatic consultation completed by NMFS' Greater Atlantic Regional Fisheries Office on June 29, 2021 (revised September 2021), pursuant to section 7 of the Endangered Species Act (hereafter, “ESA”). To the extent that any relevant Best Management Practices (hereafter, “BMPs”) described in these PDCs are more stringent than the requirements herein, those BMPs supersede these requirements and must be implemented;

(4) Acoustic sources must be deactivated when not acquiring data or preparing to acquire data, except as necessary for testing. Acoustic sources must be used at the lowest practicable source level to meet the survey objective, when in use, and must be turned off when they are not necessary for the survey;

(5) Prior to starting the survey and after receiving confirmation from the PSOs that the clearance zone is clear of any marine mammals, LOA Holder is required to ramp-up acoustic sources to half power for 5 minutes prior to commencing full power, unless the equipment operates on a binary on/off switch (in which case ramp-up is not required). LOA Holder must also ensure visual clearance zones are fully visible (e.g., not obscured by darkness, rain, fog, etc.) and clear of marine mammals, as determined by the Lead PSO, for at least 30 minutes immediately prior to the initiation of survey activities using acoustic sources;

(6) Ramp-up and activation must be delayed if a marine mammal(s) enters its respective shutdown zone. Ramp-up and activation may only be reinitiated if the animal(s) has been observed exiting its respective shutdown zone or until 15 minutes for small odontocetes and pinnipeds, and 30 minutes for all other species, has elapsed with no further sightings;

(7) Prior to a ramp-up procedure starting or activating acoustic sources, the acoustic source operator (operator) must notify a designated PSO of the planned start of ramp-up as agreed upon with the Lead PSO. The notification time should not be less than 60 minutes prior to the planned ramp-up or activation in order to allow the PSOs time to monitor the clearance zone(s) for 30 minutes prior to the initiation of ramp-up or activation (pre-start clearance). During this 30-minute pre-start clearance period, the entire applicable clearance zones must be visible, except as indicated in paragraph (f)(12) of this section;

(8) Ramp-ups must be scheduled so as to minimize the time spent with the source activated;

(9) A PSO conducting pre-start clearance observations must be notified again immediately prior to reinitiating ramp-up procedures and the operator must receive confirmation from the PSO to proceed;

(10) LOA Holder must implement a 30-minute clearance period of the clearance zones immediately prior to the commencing of the survey or when there is more than a 30-minute break in survey activities or PSO monitoring. A clearance period is a period when no marine mammals are detected in the relevant zone;

(11) If a marine mammal is observed within a clearance zone during the clearance period, ramp-up and acoustic surveys may not begin until the animal(s) has been observed voluntarily exiting its respective clearance zone or until a specific time period has elapsed with no further sighting. The specific time period is 15 minutes for small odontocetes and pinnipeds, and 30 minutes for all other species;

(12) In any case when the clearance process has begun in conditions with good visibility, including via the use of night vision equipment (i.e., infrared (IR)/thermal camera), and the Lead PSO has determined that the clearance zones are clear of marine mammals, survey operations may commence (i.e., no delay is required) despite periods of inclement weather and/or loss of daylight. Ramp-up may occur at times of poor visibility, including nighttime, if appropriate visual monitoring has occurred with no detections of marine mammals in the 30 minutes prior to beginning ramp-up;

(13) Once the survey has commenced, LOA Holder must shut down acoustic sources if a marine mammal enters a respective shutdown zone, except in cases when the shutdown zones become obscured for brief periods due to inclement weather, survey operations may continue (i.e., no shutdown is required) so long as no marine mammals have been detected. The shutdown requirement does not apply to small delphinids of the following genera: Delphinus, Stenella, Lagenorhynchus, and Tursiops. If there is uncertainty regarding the identification of a marine mammal species (i.e., whether the observed marine mammal belongs to one of the delphinid genera for which shutdown is waived), the PSOs must use their best professional judgment in making the decision to call for a shutdown. Shutdown is required if a delphinid that belongs to a genus other than those specified in paragraph (e)(13) of this section is detected in the shutdown zone;

(14) If an acoustic source has been shut down due to the presence of a marine mammal, the use of an acoustic source may not commence or resume until the animal(s) has been confirmed to have left the Level B harassment zone or until a full 15 minutes (for small odontocetes and seals) or 30 minutes (for all other marine mammals) have elapsed with no further sighting; and

(15) If an acoustic source is shut down for a period longer than 30 minutes, all clearance and ramp-up procedures must be initiated. If an acoustic source is shut down for reasons other than mitigation (e.g., mechanical difficulty) for less than 30 minutes, acoustic sources may be activated again without ramp-up only if PSOs have maintained constant observation and no additional detections of any marine mammal occurred within the respective shutdown zones.

(f) Fisheries monitoring surveys. The following measures apply to fishery monitoring surveys:

(1) All captains and crew conducting fishery surveys must be trained in marine mammal detection and identification. Marine mammal monitoring will be conducted by the captain and/or a member of the scientific crew within 1 nautical mile (nmi) (1.85 km; 1.2 mi) and 15 minutes prior to deploying gear), during, and for 15 minutes after haul back;

(2) Survey gear must be deployed as soon as possible once the vessel arrives on station. Gear must not be deployed if there is a risk of interaction with marine mammals. Gear may be deployed after 15 minutes of no marine mammal sightings within 1 nmi (1,852 m) of the sampling station;

(3) LOA Holder and/or its cooperating partners, contracted vessels, or commercially hired captains must implement the following “move-on” rule: if marine mammals are sighted within 1 nmi (1.2 mi) of the planned location and 15 minutes before gear deployment, then LOA Holder and/or its cooperating partners, contracted vessels, or commercially hired captains, as appropriate, must move the vessel away from the marine mammal to a different section of the sampling area. If, after moving on, marine mammals are still visible from the vessel, LOA Holder and its cooperating partners, contracted vessels, or commercially hired captains must move again or skip the station;

(4) If a marine mammal is at risk of interacting with deployed gear, all gear must be immediately removed from the water. If marine mammals are sighted before the gear is fully removed from the water, LOA Holder must take the most appropriate action to avoid marine mammal interaction and the vessel must slow its speed and maneuver the vessel away from the animals to minimize potential interactions with the observed animal;

(5) Unless using ropeless gear, LOA Holder must maintain visual marine mammal monitoring effort during the entire period of time that gear is in the water (i.e., throughout gear deployment, fishing, and retrieval);

(6) All fisheries monitoring gear must be fully cleaned and repaired (if damaged) before each use/deployment;

(7) LOA Holder's fixed gear must comply with the Atlantic Large Whale Take Reduction Plan regulations at 50 CFR 229.32 during fisheries monitoring surveys;

(8) Trawl tows must be limited to a maximum of a 20-minute trawl time at 3.0 kn (3.45 mph);

(9) All gear must be emptied as close to the deck/sorting area and as quickly as possible after retrieval;

(10) During trawl surveys, vessel crew must open the codend of the trawl net close to the deck in order to avoid injury to animals that may be caught in the gear;

(11) All fishery survey-related lines must include the breaking strength of all lines being less than 1,700 pounds (lbs) (771 kilograms (kg)). This may be accomplished by using whole buoy line that has a breaking strength of 1,700 lbs (771 kg); or buoy line with weak inserts that result in line having an overall breaking strength of 1,700 lbs (771 kg);

(12) During any survey that uses vertical lines, buoy lines must be weighted and must not float at the surface of the water and all groundlines must be composed entirely of sinking lines. Buoy lines must utilize weak links. Weak links must break cleanly leaving behind the bitter end of the line. The bitter end of the line must be free of any knots when the weak link breaks. Splices are not considered to be knots. The attachment of buoys, toggles, or other floatation devices to groundlines is prohibited;

(13) All in-water survey gear, including buoys, must be properly labeled with the scientific permit number or identification as LOA Holder's research gear. All labels and markings on the gear, buoys, and buoy lines must also be compliant with the applicable regulations, and all buoy markings must comply with instructions received by the NOAA Greater Atlantic Regional Fisheries Office Protected Resources Division;

(14) All survey gear must be removed from the water whenever not in active survey use (i.e., no wet storage);

(15) All reasonable efforts, that do not compromise human safety, must be undertaken to recover gear; and

(16) All lost gear associated with the fishery surveys must be reported to the NOAA Greater Atlantic Regional Fisheries Office Protected Resources Division ([email protected]) within 24 hours of the documented time of missing or lost gear. This report must include information on any markings on the gear and any efforts undertaken or planned to recover the gear.

§ 217.305 - Monitoring and reporting requirements.

(a) Protected species observer (PSO) and passive acoustic monitoring (PAM) operator qualifications. LOA Holder must implement the following measures applicable to PSOs and PAM operators:

(1) LOA Holder must use independent, NMFS-approved PSOs and PAM operators (i.e., the PSOs and PAM operators must be employed by a third-party observer provider) must have no tasks other than to conduct observational effort, collect data, and communicate with and instruct relevant crew with regard to the presence of protected species and mitigation requirements;

(2) All PSOs and PAM operators must have successfully attained a bachelor's degree in one of the natural sciences. The educational requirements may be waived if the PSO or PAM operator has acquired the relevant skills through a suitable amount of alternate experience. Requests for such a waiver must be submitted to NMFS Office of Protected Resources and must include written justification containing alternative experience. Alternate experiences that may be considered include but are not limited to: previous work experience conducting academic, commercial, or government-sponsored marine mammal visual and/or acoustic surveys; or previous work experience as a PSO/PAM operator. All PSOs and PAM operators should demonstrate good standing and consistently good performance of all assigned duties;

(3) PSOs must have visual acuity in both eyes (with correction of vision being permissible) sufficient enough to discern moving targets on the water's surface with the ability to estimate the target size and distance (binocular use is allowable); ability to conduct field observations and collect data according to the assigned protocols; sufficient training, orientation, or experience with the construction operation to provide for personal safety during observations; writing skills sufficient to document observations, including but not limited to, the number and species of marine mammals observed, the dates and times of when in-water construction activities were conducted, the dates and time when in-water construction activities were suspended to avoid potential incidental take of marine mammals from construction noise within a defined shutdown zone, and marine mammal behavior; and the ability to communicate orally, by radio, or in-person, with Project personnel to provide real-time information on marine mammals observed in the area;

(4) All PSOs must be trained in northwestern Atlantic Ocean marine mammal identification and behaviors and must be able to conduct field observations and collect data according to assigned protocols. Additionally, PSOs must have the ability to work with all required and relevant software and equipment necessary during observations (as described in paragraphs (b)(5) and (6) of this section);

(5) All PSOs and PAM operators must successfully complete a relevant training course within the last 5 years, including obtaining a certificate of course completion;

(6) PSOs are responsible for obtaining NMFS' approval. NMFS may approve PSOs as conditional or unconditional. A conditionally approved PSO may be one who has completed training in the last 5 years but has not yet attained the requisite field experience. An unconditionally approved PSO is one who has completed training within the last 5 years and attained the necessary experience (i.e., demonstrate experience with monitoring for marine mammals at clearance and shutdown zone sizes similar to those produced during the respective activity);

(7) At least one PSO for each activity (e.g., foundation installation, cable landfall construction, and HRG surveys) on each vessel must be designated as the Lead PSO. The Lead PSO must meet the minimum requirements described in paragraphs (a)(2) through (5) of this section and have a minimum of 90 days of at-sea experience visually monitoring marine mammals, including baleen whales, and no more than 18 months may have elapsed since the conclusion of their last at-sea experience;

(8) PSOs for cable landfall construction (i.e., vibratory pile installation and removal) and HRG surveys may be unconditionally or conditionally approved. A conditionally approved PSO must be paired with an unconditionally approved PSO. PSOs for foundation installation must be unconditionally approved;

(9) PAM operators are responsible for obtaining NMFS approval. To be approved as a PAM operator, the person must meet the following qualifications. The PAM operator must: demonstrate that they have prior experience with relevant acoustic software and equipment and real-time acoustic detection systems and/or have completed specialized training for operating PAM systems and detecting and identifying Atlantic Ocean marine mammals sounds, in particular: North Atlantic right whale sounds, humpback whale sounds, and how to deconflict them from similar North Atlantic right whale sounds, and other co-occurring species' sounds in the area including sperm whales; be able to distinguish between whether a marine mammal or other species sound is detected, possibly detected, or not detected; be able to review and classify acoustic detections in real-time (prioritizing North Atlantic right whales and noting detection of other cetaceans) during the real-time monitoring periods where localization of sounds or deriving bearings and distance are possible and demonstrate experience in using this technique; have the qualifications and relevant experience/training to safely deploy and retrieve equipment and program the software, as necessary; and must be able to test software and hardware functionality prior to operation;

(10) LOA Holder must submit previously approved PSOs and PAM operators to NMFS Office of Protected Resources for review and confirmation of their approval for specific roles at least 30 business days prior to commencement of the activities requiring PSOs/PAM operators or 15 business days prior to when new PSOs/PAM operators are required after activities have commenced;

(11) For prospective PSOs and PAM operators not previously approved, or for PSOs and PAM operators whose approval is not current, LOA Holder must submit resumes for approval at least 60 business days prior to PSO and PAM operator use. Resumes must include information related to relevant education, experience, and training, including dates, duration, location, and description of prior PSO or PAM operator experience. Resumes must be accompanied by relevant documentation of successful completion of necessary training;

(12) PSOs may work as PAM operators and vice versa, pending NMFS-approval; however, they may only perform one role at any single time and must not exceed work time restrictions, which must be tallied cumulatively; and

(13) All PSOs and PAM operators must complete a Permits and Environmental Compliance Plan training and a 2-day refresher session that must be held with the PSO/PAM operator provider and Project compliance representative(s) prior to the start of in-water Project activities requiring PSOs and PAM operators.

(b) General PSO and PAM operator requirements. The following measures apply to PSOs and PAM operators and must be implemented by LOA Holder:

(1) PSOs must monitor for marine mammals prior to, during, and following all impact pile driving, vibratory pile driving, and HRG surveys that use sub-bottom profilers (with specific monitoring durations and needs described in paragraphs (c) through (f) of this section, respectively). Monitoring must be done while free from distractions and in a consistent, systematic, and diligent manner;

(2) All PSOs must be located at the best vantage point(s) on any platform, as determined by the Lead PSO. PAM operators may be located on a vessel or remotely on-shore, but must have the appropriate equipment (i.e., computer station equipped with a data collection software system and acoustic data analysis software) available wherever they are stationed, and data or data products must be streamed in real-time or in near real-time;

(3) All on-duty PSOs must remain in real-time contact with the on-duty PAM operator(s). PAM operator(s) must immediately communicate all acoustic detections of marine mammals to PSOs, including any determination regarding species identification, distance, and bearing (where relevant) relative to the pile being driven and the degree of confidence (e.g., possible, probable detection) in the determination. All on-duty PSOs and PAM operator(s) must remain in contact with the on-duty construction personnel responsible for implementing mitigations (e.g., delay to pile driving) to ensure communication on marine mammal observations can easily, quickly, and consistently occur between all on-duty PSOs, PAM operator(s), and on-water Project personnel;

(4) The PAM operator must inform the Lead PSO(s) on duty of animal detections, including any determination regarding species identification, distance, bearing, and degree of confidence in the determinations, approaching or within applicable ranges of interest to the activity occurring via the data collection software system, (e.g., Mysticetus or similar system) who must be responsible for requesting that the designated crewmember implement the necessary mitigation procedures (i.e., delay);

(5) PSOs must use high magnification (25x) binoculars, standard handheld (7x) binoculars, and the naked eye to search continuously for marine mammals. During foundation installation, at least two PSOs on the pile driving-dedicated PSO vessel(s) must be equipped with functional Big Eye binoculars (e.g., 25 × 150; 2.7 view angle; individual ocular focus; height control); these must be pedestal mounted on the deck at the best vantage point that provides for optimal sea surface observation and PSO safety;

(6) During periods of low visibility (e.g., darkness, rain, fog, poor weather conditions, etc.), PSOs must use alternative technology (i.e., infrared or thermal cameras) to monitor the clearance and shutdown zones as approved by NMFS;

(7) PSOs and PAM operators must not exceed 4 consecutive watch hours on duty at any time, must have a 2-hour (minimum) break between watches, and must not exceed a combined watch schedule of more than 12 hours in a 24-hour period. If the schedule includes PSOs and PAM operators on-duty for 2-hour shifts, a minimum 1-hour break between watches must be allowed; and

(8) During daylight hours when equipment is not operating, LOA Holder must ensure that visual PSOs conduct, as rotation schedules allow, observations for comparison of sighting rates and behavior with and without use of the specified acoustic sources. Off-effort PSO monitoring must be reflected in the monthly PSO monitoring reports.

(c) PSO and PAM operator requirements during WTG, OSS, and Met Tower foundation installation. The following measures apply to PSOs and PAM operators during WTG, OSS, and Met Tower foundation installation and must be implemented by LOA Holder:

(1) At least three on-duty PSOs must be stationed and observing from the pile driving activity platform. Additionally, LOA Holder must use two dedicated-PSO vessels and each vessel must have at least three PSOs on duty. LOA Holder may request NMFS approval to use alternative technology in lieu of one or two of the dedicated PSO vessels that provide similar marine mammal detection capabilities. If NMFS approves the use of alternative technology in lieu of the additional PSO vessels, LOA Holder must abide by any conditions of approved, as specified by NMFS;

(2) PSOs and PAM operator(s), using a NMFS-approved PAM system, must monitor for marine mammals 60 minutes prior to, during, and 30 minutes following all pile-driving. If PSOs cannot visually monitor the minimum visibility zone for the 60 minutes prior to and during pile driving, pile-driving operations must not commence or must shutdown if they are currently active; and

(3) LOA Holder must conduct PAM for at least 24 hours prior to pile driving activities. The PAM operator(s) must review all detections from the previous 24-hour period prior to starting foundation pile driving.

(d) PSO requirements during cable landfall construction. The following measures apply to PSOs during cofferdam installation and removal and must be implemented by LOA Holder:

(1) At least two PSOs must be on active duty during all activities related to the installation and removal of cofferdams; and

(2) PSOs must monitor the clearance zone for the presence of marine mammals for 30 minutes before, throughout the installation of the sheet piles, and for 30 minutes after all vibratory pile driving activities have ceased. Sheet pile installation and removal must only commence when visual clearance zones are fully visible (e.g., not obscured by darkness, rain, fog, etc.) and clear of marine mammals, as determined by the Lead PSO, for at least 30 minutes immediately prior to the initiation of vibratory pile driving.

(e) PSO requirements during HRG surveys. The following measures apply to PSOs during HRG surveys using CHIRPs and sparkers and must be implemented by LOA Holder:

(1) Between four and six PSOs must be present on every 24-hour survey vessel and two to three PSOs must be present on every 12-hour survey vessel;

(2) At least one PSO must be on active duty monitoring 30 minutes before, during, and 30 minutes after HRG surveys conducted during daylight (i.e., from 30 minutes prior to civil sunrise through 30 minutes following civil sunset) and at least two PSOs must be on active duty monitoring 30 minutes before, during, and 30 minutes after HRG surveys conducted at night;

(3) PSOs on HRG vessels must begin monitoring 30 minutes prior to activating acoustic sources, during the use of these acoustic sources, and for 30 minutes after use of these acoustic sources has ceased;

(4) Any observations of marine mammals must be communicated to PSOs on all nearby survey vessels during concurrent HRG surveys; and

(5) During daylight hours when survey equipment is not operating, LOA Holder must ensure that visual PSOs conduct, as rotation schedules allow, observations for comparison of sighting rates and behavior with and without use of the specified acoustic sources. Off-effort PSO monitoring must be reflected in the monthly PSO monitoring reports.

(f) Monitoring requirements during fisheries monitoring surveys. The following measures apply during fisheries monitoring surveys and must be implemented by LOA Holder:

(1) All captains and crew conducting fishery surveys must be trained in marine mammal detection and identification; and

(2) Marine mammal monitoring must be conducted within 1 nmi from the planned survey location by the trained captain and/or a member of the scientific crew for 15 minutes prior to deploying gear, throughout gear deployment and use (unless using ropeless gear), and for 15 minutes after haul back.

(g) Reporting. LOA Holder must comply with the following reporting measures:

(1) Prior to initiation of any specified activities, LOA Holder must demonstrate, in a report submitted to NMFS Office of Protected Resources, that all required training for LOA Holder personnel (including the vessel crews, vessel captains, PSOs, and PAM operators) has been completed;

(2) LOA Holder must use a standardized reporting system during the effective period of the LOA. All data collected related to the Project must be recorded using industry-standard software that is installed on field laptops and/or tablets. Unless stated otherwise, all reports must be submitted to NMFS Office of Protected Resources ([email protected]), dates must be in MM/DD/YYYY format, and location information must be provided in Decimal Degrees with the coordinate system information (e.g., North American Datum of 1983 (NAD83), World Geodetic System 1984 (WGS84), etc.);

(3) For all visual monitoring efforts and marine mammal sightings, the following information must be collected and reported to NMFS Office of Protected Resources: the date and time that monitored activity begins or ends; the construction activities occurring during each observation period; the watch status (i.e., sighting made by PSO on/off effort, opportunistic, crew, alternate vessel/platform); the PSO who sighted the animal; the time of sighting; the weather parameters (e.g., wind speed, percent cloud cover, visibility); the water conditions (e.g., Beaufort sea state, tide state, water depth); all marine mammal sightings, regardless of distance from the activity; species (or lowest possible taxonomic level possible); the pace of the animal(s); the estimated number of animals (minimum/maximum/high/low/best); the estimated number of animals by cohort (e.g., adults, yearlings, juveniles, calves, group composition, etc.); the description (i.e., as many distinguishing features as possible of each individual seen, including length, shape, color, pattern, scars or markings, shape and size of dorsal fin, shape of head, and blow characteristics); the description of any marine mammal behavioral observations (e.g., observed behaviors such as feeding or traveling) and observed changes in behavior, including an assessment of behavioral responses thought to have resulted from the specific activity; the animal's closest distance and bearing from the pile being driven or specified HRG equipment and estimated time entered or spent within the Level A harassment and/or Level B harassment zone(s); the activity at time of sighting (e.g., impact pile driving, vibratory pile driving, construction surveys); use of any noise attenuation device(s); and specific phase of activity (e.g., ramp-up of HRG equipment, HRG acoustic source on/off, soft-start for pile driving, active pile driving, etc.); the marine mammal occurrence in Level A harassment or Level B harassment zones; the description of any mitigation-related action implemented, or mitigation-related actions called for but not implemented, in response to the sighting (e.g., delay, shutdown, etc.) and time and location of the action; other human activity in the area; and other applicable information, as required in any LOA issued under § 217.306;

(4) If a marine mammal is acoustically detected during PAM, the following information must be recorded and reported to NMFS: location of hydrophone (latitude and longitude; in decimal degrees) and site name; bottom depth and depth of recording unit (in meters); recorder (model & manufacturer) and platform type (i.e., bottom-mounted, electric glider, etc.), and instrument ID of the hydrophone and recording platform (if applicable); time zone for sound files and recorded date/times in data and metadata (in relation to Universal Coordinated Time (UTC); i.e., Eastern Standard Time (EST) time zone is UTC-5); duration of recordings (start/end dates and times; in International Organization for Standardization (ISO) 8601 format, yyyy-mm-ddTHH:MM:SS.sssZ); deployment/retrieval dates and times (in ISO 8601 format); recording schedule (must be continuous); hydrophone and recorder sensitivity (in dB re. 1 microPascal (µPa)); calibration curve for each recorder; bandwidth/sampling rate (in Hz); sample bit-rate of recordings; and detection range of equipment for relevant frequency bands (in meters):

(i) For each detection, the following information must be noted: species identification (if possible); call type and number of calls (if known); temporal aspects of vocalization (date, time, duration, etc.; date times in ISO 8601 format); confidence of detection (detected, or possibly detected); comparison with any concurrent visual sightings; location and/or directionality of call (if determined) relative to acoustic recorder or construction activities; location of recorder and construction activities at time of call; name and version of detection or sound analysis software used, with protocol reference; minimum and maximum frequencies viewed/monitored/used in detection (in Hz); and name of PAM operator(s) on duty.

(ii) [Reserved]

(5) LOA Holder must compile and submit weekly reports during foundation installation to NMFS Office of Protected Resources that document the daily start and stop of all pile driving associated with the Project; the start and stop of associated observation periods by PSOs and PAM operators; details on the deployment of PSOs and PAM operators; a record of all observations/detections of marine mammals (acoustic and visual); any mitigation actions (or if mitigation actions could not be taken, provide reasons why); details on the noise attenuation system(s) used and its performance; and all abbreviated SFV results, including any indications that distances to the identified Level A harassment and Level B harassment thresholds for marine mammals were exceeded and an explanation of factors that contributed to each exceedance (if found) and corrective actions that were taken to avoid exceedance on subsequent piles. The weekly report must also identify which turbines become operational and when (a map must be provided). Once all foundation pile installation is completed, weekly reports are no longer required by LOA Holder;

(6) LOA Holder must compile and submit monthly reports to NMFS Office of Protected Resources during foundation installation that include a summary of all information in the weekly reports, including Project activities carried out in the previous month, vessel transits (number, type of vessel, MMIS number, and route), number of piles installed, all detections of marine mammals, and any mitigative action taken. The monthly report must also identify which turbines become operational and when (a map must be provided). Once all foundation pile installation is completed, monthly reports are no longer required by LOA Holder;

(7) LOA Holder must submit a draft annual report to NMFS Office of Protected Resources following completion of activities each year. LOA Holder must provide a final report within 30 calendar days following resolution of NMFS' comments on the draft report. The draft and final reports must detail the following: the total number of marine mammals of each species/stock detected and how many were within the designated Level A harassment and Level B harassment zone(s) with comparison to authorized take of marine mammals for the associated activity type; marine mammal detections and behavioral observations before, during, and after each activity; what mitigation measures were implemented (i.e., number of shutdowns or clearance zone delays, etc.) or, if no mitigative actions were taken, why not; operational details (i.e., days and duration of impact and vibratory pile driving, days and amount of HRG survey effort, etc.); any PAM systems used; the results, effectiveness, and which noise attenuation systems were used during relevant activities (i.e., foundation impact pile driving); summarized information related to situational reporting; and any other important information relevant to the Project, including additional information that may be identified through the adaptive management process;

(8) LOA Holder must submit its draft 5-year report to NMFS Office of Protected Resources on all visual and acoustic monitoring conducted within 90 calendar days of the completion of activities occurring under the LOA. A 5-year report must be prepared and submitted within 60 calendar days following receipt of any NMFS Office of Protected Resources comments on the draft report. The draft and final 5-year report must include, but is not limited to, the following: the total number (annually and across all 5 years) of marine mammals of each species/stock detected and how many were detected within the designated Level A harassment and Level B harassment zone(s) with comparison to authorized take of marine mammals for the associated activity; summary table(s) indicating the amount of each activity type (e.g., pile installation, HRG) completed in each of the 5 years and total; Environmental Systems Research Institute, Inc. (ESRI) vector Geographic Information System (GIS) shapefile(s) of the final location of all piles, cable routes, and other permanent structures including an indication of what year it was installed and began operating; ESRI vector GIS shapefile of all North Atlantic right whale sightings, including dates and group sizes; a 5- year summary and evaluation of all SFV data collected; a 5-year summary and evaluation of all PAM data collected; a 5-year summary and evaluation of marine mammal behavioral observations; a 5-year summary and evaluation of mitigation and monitoring implementation and effectiveness; and a list of recommendations to inform environmental compliance assessments for future offshore wind actions;

(9) LOA Holder must provide the initial results of the thorough SFV measurements (see § 217.304(c)(15)) to NMFS Office of Protected Resources in an interim report after each foundation installation event as soon as they are available and prior to any subsequent foundation installation, but no later than 48 hours after each completed foundation installation event. The report must include, at minimum: hammer energies and schedule used during pile driving, including the total number of strikes and the maximum hammer energy; the model-estimated acoustic ranges (R95%) to compare with the real-world sound field measurements; peak sound pressure level (SPLpk), root-mean-square sound pressure level that contains 90 percent of the acoustic energy (SPLrms), and sound exposure level (SEL, in single strike for pile driving, SELss,), for each hydrophone, including at least the maximum, arithmetic mean, minimum, median (L50) and L5 (95 percent exceedance) statistics for each metric; estimated marine mammal Level A harassment and Level B harassment acoustic isopleths, calculated using the maximum-over-depth L5 (95 percent exceedance level, maximum of both hydrophones) of the associated sound metric; comparison of modeled results assuming 10-dB attenuation against the measured marine mammal Level A harassment and Level B harassment acoustic isopleths; estimated transmission loss coefficients; pile identifier name, location of the pile and each hydrophone array in latitude/longitude; depths of each hydrophone; one-third-octave band single strike SEL spectra; full filter characteristics (if filtering is applied); and hydrophone specifications including the type, model, and sensitivity. LOA Holder must also report any immediate observations which are suspected to have a significant impact on the results including but not limited to: observed noise mitigation system issues, obstructions along the measurement transect, and technical issues with hydrophones or recording devices. If any in-situ calibration checks for hydrophones reveal a calibration drift greater than 0.75 dB, pistonphone calibration checks are inconclusive, or calibration checks are otherwise not effectively performed, LOA Holder must indicate full details of the calibration procedure, results, and any associated issues in the 48-hour interim reports;

(10) LOA Holder must conduct abbreviated SFV for all foundation installations for which the thorough SFV monitoring is not carried out, whereas a single acoustic recorder must be placed at an appropriate distance from the pile. All results must be included in the weekly reports. Any indications that distances to the identified Level A harassment and Level B harassment thresholds for marine mammals were exceeded must be addressed by LOA Holder, including an explanation of factors that contributed to the exceedance and corrective actions that were taken to avoid exceedance on subsequent piles;

(11) The final results of all SFV measurements from all foundation installations must be submitted no later than 90 calendar days following completion of all annual SFV measurements. The final reports must include all details included in the interim report and descriptions of any notable occurrences, explanations for results that were not anticipated, or actions taken during foundation installation. The final report must also include at least the maximum, mean, minimum, median (L50) and L5 (95 percent exceedance) statistics for each metric; the SEL and SPL power spectral density and/or one-third octave band levels (usually calculated as decidecade band levels) at the receiver locations should be reported; range of transmission loss coefficients; the local environmental conditions, such as wind speed, transmission loss data collected on-site (or the sound velocity profile); baseline pre-activity and post-activity ambient sound levels (broadband and/or within frequencies of concern); a description of depth and sediment type, as documented in the Construction and Operation Plan (COP), at the recording and foundation installation locations; the extents of the measured Level A harassment and Level B harassment zone(s); hammer energies required for pile installation and the number of strikes per pile; the hydrophone equipment and methods (i.e., recording device, bandwidth/sampling rate; distance from the pile where recordings were made; the depth of recording device(s)); a description of the SFV measurement hardware and software, including software version used, calibration data, bandwidth capability and sensitivity of hydrophone(s), any filters used in hardware or software, any limitations with the equipment, and other relevant information; the spatial configuration of the noise attenuation device(s) relative to the pile; a description of the noise abatement system and operational parameters (e.g., bubble flow rate, distance deployed from the pile, etc.), and any action taken to adjust the noise abatement system. A discussion which includes any observations which are suspected to have a significant impact on the results including but not limited to: observed noise mitigation system issues, obstructions along the measurement transect, and technical issues with hydrophones or recording devices;

(12) If at any time during the Project LOA Holder becomes aware of any issue or issues which may (to any reasonable subject-matter expert, including the persons performing the measurements and analysis) call into question the validity of any measured Level A harassment or Level B harassment isopleths to a significant degree, which were previously transmitted or communicated to NMFS Office of Protected Resources, LOA Holder must inform NMFS Office of Protected Resources within 1 business day of becoming aware of this issue or before the next pile is driven, whichever comes first;

(13) Full PAM detection data, metadata, and location of recorders (or GPS tracks, if applicable) must be submitted within 90 calendar days following completion of foundation installation pile driving each season and every 90 calendar days for transit lane PAM using the International Organization for Standardization (ISO) standard metadata forms and instructions available on the NMFS Passive Acoustic Reporting System website at: https://www.fisheries.noaa.gov/resource/document/passive-acoustic-reporting-system-templates. Concurrently, the full acoustic recordings from real-time systems must also be sent to the National Centers for Environmental Information (NCEI) at: https://www.ncei.noaa.gov/products/passive-acoustic-data for archiving;

(14) Inclusive of all instances wherein an exemption to a measure is taken (which must be reported to NMFS Office of Protected Resources within 24 hours), LOA Holder must submit situational reports if the following circumstances occur, including but not limited to the following:

(i) If a North Atlantic right whale is sighted with no visible injuries or entanglement at any time by project PSOs or project personnel, the LOA Holder must, as soon as possible but within 24 hours, download and complete the Real-Time North Atlantic Right Whale Reporting Template spreadsheet found at: https://www.fisheries.noaa.gov/resource/document/template-datasheet-real-time-north-atlantic-right-whale-acoustic-and-visual and save the completed spreadsheet as a .csv file and email it to NMFS NEFSC-PSD ([email protected]), NMFS GARFO-PRD ([email protected]), and NMFS OPR ([email protected]). If unable to report a sighting through the spreadsheet within 24 hours, call the relevant regional hotline (Greater Atlantic Region's (Maine to Virginia/North Carolina border) Hotline at 866-755-6622 or the Southeast Region's (North Carolina through the Gulf of Mexico) Hotline at 877-WHALE-HELP (877-942-5343)). Report the following information: the time (note time format), date (MM/DD/YYYY), location (latitude/longitude in decimal degrees; coordinate system used) of the observation, number of whales, animal description/certainty of observation (follow up with photos/video if taken), reporter's contact information, and Lease Areas number/project name, PSO/personnel name who made the observation, and PSO provider company (if applicable) (PAM detections are not reported to the Hotlines). If unable to report via the template or the regional hotline, enter the sighting via the WhaleAlert app (http://www.whalealert.org/). If this is not possible, report the sighting to the U.S. Coast Guard via channel 16. The report to the Coast Guard must include the same information as would be reported to the Hotline;

(ii) If a North Atlantic right whale is detected via real-time PAM, data must be submitted using the NMFS Passive Acoustic Reporting System Metadata and Detection data spreadsheets and instructions available at: https://www.fisheries.noaa.gov/resource/document/passive-acoustic-reporting-system-templates, as soon as feasible but no longer than 24 hours after the detection;

(iii) If a large whale other than a North Atlantic right whale is observed at any time by PSOs or Project personnel, LOA Holder must report the sighting to the WhaleAlert app at: http://www.whalealert.org/;

(iv) In the event that personnel involved in the Project discover a stranded, entangled, injured, or dead marine mammal, the LOA Holder must immediately report the observation to NMFS. If in the Greater Atlantic Region (Maine through Virginia), call the NMFS Greater Atlantic Stranding Hotline (866-755-6622), and if in the Southeast Region (North Carolina through Florida), call the NMFS Southeast Stranding Hotline (877-WHALE-HELP (877-942-5343)). Separately, the LOA Holder must report, within 24 hours, the incident to NMFS Office of Protected Resources ([email protected]) and, if in the Greater Atlantic Region, to the NMFS Greater Atlantic Regional Fisheries Office (GARFO; [email protected]) or, if in the Southeast Region, to the NMFS Southeast Regional Office (SERO; [email protected]). The report must include contact (e.g., name, phone number, etc.), time, date, and location (i.e., specify coordinate system) of the first discovery (and updated location information, if known and applicable); species identification (if known) or description of the animal(s) involved; condition of the animal(s) (including carcass condition if the animal is dead); observed behaviors of the animal(s) (if alive); photographs or video footage of the animal(s) (if available); and general circumstances under which the animal was discovered; and

(v) In the event of a suspected or confirmed vessel strike of a marine mammal by any vessel associated with the Project or other means by which Project activities caused a non-auditory injury or death of a marine mammal, the LOA Holder must immediately report the incident to NMFS. If in the Greater Atlantic Region (Maine through Virginia), call the NMFS Greater Atlantic Stranding Hotline (866-755-6622), and if in the Southeast Region (North Carolina through Florida) call the NMFS Southeast Stranding Hotline (877-WHALE-HELP (877-942-5343)). Separately, the LOA Holder must immediately report the incident to NMFS Office of Protected Resources ([email protected]) and, if in the Greater Atlantic Region, to the NMFS Greater Atlantic Regional Fisheries Office (GARFO; [email protected]) or, if in the Southeast Region, to the NMFS Southeast Regional Office (SERO; [email protected]). The report must include time, date, and location (i.e., specify coordinate system) of the incident; species identification (if known) or description of the animal(s) involved (i.e., identifiable features including animal color, presence of dorsal fin, body shape and size, etc.); vessel strike reported information (e.g., name, affiliation, email for person completing the report); vessel strike witness (if different than the reporter) information (e.g., name, affiliation, phone number, platform for person witnessing the event, etc.); vessel name and/or MMSI number; vessel size and motor configuration (inboard, outboard, jet propulsion); vessel's speed leading up to and during the incident; vessel's course/heading and what operations were being conducted (if applicable); part of vessel that struck marine mammal (if known); vessel damage notes; status of all sound sources in use at the time of the strike; if the marine mammal was seen before the strike event; description of behavior of the marine mammal before the strike event (if seen) and behavior immediately following the strike; description of avoidance measures/requirements that were in place at the time of the strike and what additional measures were taken, if any, to avoid strike; environmental conditions (e.g., wind speed and direction, Beaufort sea state, cloud cover, visibility, etc.) immediately preceding the strike; estimated (or actual, if known) size and length of marine mammal that was struck; if available, description of the presence and behavior of any other marine mammals immediately preceding the strike; other animal-specific details, if known (e.g., length, sex, age class); behavior or estimated fate of the marine mammal post-strike (e.g., dead, injured but alive, injured and moving, external visible wounds (linear wounds, propeller wounds, non-cutting blunt-force trauma wounds), blood or tissue observed in the water, status unknown, disappeared); to the extent practicable, any photographs or video footage of the marine mammal(s); and, any additional notes the witness may have from the interaction. For any numerical values provided (i.e., location, animal length, vessel length, etc.), please provide if values are actual or estimated. The LOA Holder must immediately cease activities until the NMFS Office of Protected Resources is able to review the circumstances of the incident and determine what, if any, additional measures are appropriate to ensure compliance with the terms of the LOA. NMFS Office of Protected Resources may impose additional measures to minimize the likelihood of further prohibited take and ensure MMPA compliance. The LOA Holder may not resume their activities until notified by NMFS Office of Protected Resources.

(15) Any lost gear associated with the fishery surveys will be reported to the NOAA Greater Atlantic Regional Fisheries Office Protected Resources Division ([email protected]) as soon as possible or but no later than 24 hours of the documented time of missing or lost gear. This report must include information on any markings on the gear and any efforts undertaken or planned to recover the gear. All reasonable efforts, that do not compromise human safety, must be undertaken to recover gear.

§ 217.306 - Letter of Authorization.

(a) To incidentally take marine mammals pursuant to this subpart, LOA Holder must apply for and obtain a LOA;

(b) LOA, unless suspended or revoked, may be effective for a period of time not to exceed December 31, 2029, the expiration date of this subpart;

(c) In the event of projected changes to the activity or to mitigation and monitoring measures required by the LOA, LOA Holder must apply for and obtain a modification of the LOA as described in § 217.307;

(d) The LOA must set forth:

(1) Permissible methods of incidental taking;

(2) Means of effecting the least practicable adverse impact (i.e., mitigation) on the species, its habitat, and on the availability of the species for subsistence uses; and

(3) Requirements for monitoring and reporting.

(e) Issuance of the LOA must be based on a determination that the level of taking must be consistent with the findings made for the total taking allowable under the regulations of this subpart; and

(f) Notice of issuance or denial of the LOA must be published in the Federal Register within 30 calendar days of a determination.

§ 217.307 - Modifications of Letter of Authorization.

(a) Any LOA issued under §§ 217.302 and 217.306 or this section for the activities identified in § 217.300(a) may be modified upon request by LOA Holder, provided that:

(1) The specified activity and mitigation, monitoring, and reporting measures, as well as the anticipated impacts, are the same as those described and analyzed for this subpart (excluding changes made pursuant to the adaptive management provision in paragraph (c)(1) of this section); and

(2) NMFS Office of Protected Resources determines that the mitigation, monitoring, and reporting measures required by the previous LOA under this subpart were implemented.

(b) For any modification request to the LOA by the applicant that includes changes to the activities or the mitigation, monitoring, or reporting (excluding changes made pursuant to the adaptive management provision in paragraph (c)(1) of this section), the LOA may be modified, provided that:

(1) NMFS Office of Protected Resources determines that the changes to the activity or the mitigation, monitoring, or reporting do not change the findings made for the regulations in this subpart and do not result in more than a minor change in the maximum annual or total estimated number of takes of any species or stock; and

(2) NMFS Office of Protected Resources may, if appropriate, publish a notice of proposed modified LOA in the Federal Register, including the associated analysis of the change, and solicit public comment before issuing the LOA.

(c) LOA issued under §§ 217.302 and 217.306 or this section for the activities identified in § 217.300(a) may be modified by NMFS under the following circumstances:

(1) Through adaptive management, NMFS Office of Protected Resources may modify (e.g., delete, modify, or add to) the existing mitigation, monitoring, or reporting measures (after consulting with the LOA Holder regarding the practicability of the modifications), if doing so creates a reasonable likelihood of more effectively accomplishing the goals of the mitigation and monitoring;

(i) Possible sources of data that could contribute to the decision to modify the mitigation, monitoring, or reporting measures in the LOA include, but are not limited to:

(A) Results from LOA Holder's monitoring;

(B) Results from other marine mammals and/or sound research or studies; and

(C) Any information that reveals marine mammals may have been taken in a manner, extent, or number not allowed by the regulations in this subpart or subsequent LOA.

(ii) If, through adaptive management, the modifications to the mitigation, monitoring, or reporting measures are substantial, NMFS Office of Protected Resources shall publish a notice of proposed LOA in the Federal Register and solicit public comment.

(2) If NMFS Office of Protected Resources determines that an emergency exists that poses a significant risk to the well-being of the species or stocks of marine mammals specified in the LOA issued pursuant to §§ 217.302 and 217.306 or this section, any LOA may be modified without prior notice or opportunity for public comment. Notice would be published in the Federal Register within 30 calendar days of the issuance of a LOA under this subpart.

§§ 217.308-217.309 - §[Reserved]
authority: 16 U.S.C. 1361
source: 74 FR 35143, July 20, 2009, unless otherwise noted.