§ 990.40 - General adverse action appeal process.

(a) Persons who believe they are adversely affected by the denial of a license application under the USDA hemp production program may appeal such decision to the AMS Administrator.

(b) Persons who believe they are adversely affected by the denial of a license renewal under the USDA hemp production program may appeal such decision to the AMS Administrator.

(c) Persons who believe they are adversely affected by the revocation or suspension of a USDA hemp production license may appeal such decision to the AMS Administrator.

(d) States and Indian Tribes that believe they are adversely affected by the denial of a proposed State or Tribal hemp plan may appeal such decision to the AMS Administrator.

§ 990.41 - Appeals under the USDA hemp production plan.

(a) Appealing a denied USDA-plan license application. A license applicant may appeal the denial of a license application.

(1) If the AMS Administrator grants an applicant's appeal of a licensing denial, the applicant will be issued a USDA hemp production license.

(2) If the AMS Administrator denies an appeal, the applicant's license application will be denied. The applicant may request a formal adjudicatory proceeding within 30 days to review the decision. Such proceeding shall be conducted pursuant to the U.S. Department of Agriculture's Rules of Practice Governing Adjudicatory Proceedings, 7 CFR part 1, subpart H.

(b) Appealing a denied USDA-plan license renewal. A producer may appeal the denial of a license renewal.

(1) If the AMS Administrator grants a producer's appeal of a licensing renewal denial, the applicant's USDA hemp production license will be renewed.

(2) If the AMS Administrator denies the appeal, the applicant's license will not be renewed. The denied producer may request a formal adjudicatory proceeding within 30 days to review the decision. Such proceeding shall be conducted pursuant to the U.S. Department of Agriculture's Rules of Practice Governing Formal Adjudicatory Proceedings, 7 CFR part 1, subpart H.

(c) Appealing a USDA-plan license termination or suspension. A USDA hemp plan producer may appeal the revocation or suspension of a license.

(1) If the AMS Administrator grants the appeal of a license termination or suspension, the producer will retain their license.

(2) If the AMS Administrator denies the appeal, the producer's license will be terminated or suspended. The producer may request a formal adjudicatory proceeding within 30 days to review the decision. Such proceeding shall be conducted pursuant to the U.S. Department of Agriculture's Rules of Practice Governing Formal Adjudicatory Proceedings, 7 CFR part 1, subpart H.

(d) Filing period. The appeal of a denied license application, denied license renewal, suspension, or revocation must be filed within the time-period provided in the letter of notification or within 30 business days from receipt of the notification, whichever occurs later. The appeal will be considered “filed” on the date received by the AMS Administrator. The decision to deny an appeal of a license application or renewal, or suspend or terminate a license, is final unless a formal adjudicatory proceeding is requested within 30 days to review the decision. Such proceeding shall be conducted pursuant to the U.S. Department of Agriculture's Rules of Practice Governing Adjudicatory Proceedings, 7 CFR part 1, subpart H.

(e) Where to file. Appeals to the Administrator must be filed in the manner as determined by AMS.

(f) What to include. All appeals must include a copy of the adverse decision and a statement of the appellant's reasons supporting why the decision was not proper or made in accordance with applicable program regulations in this part, policies, or procedures.

§ 990.42 - Appeals under a State or Tribal hemp production plan.

(a) Appealing a State or Tribal hemp production plan application. A State or Indian Tribe may appeal the denial of a proposed State or Tribal hemp production plan by the USDA to the AMS Administrator.

(1) If the AMS Administrator grants a State or Indian Tribe's appeal of a denied hemp plan application, the proposed State or Tribal hemp production plan shall be established as proposed.

(2) If the AMS Administrator denies an appeal, the proposed State or Tribal hemp production plan shall not be approved. Prospective producers located in the State or territory of the Indian Tribe may apply for hemp licenses under the terms of the USDA plan. The State or Indian Tribe may request a formal adjudicatory proceeding be initiated within 30 days to review the decision. Such proceeding shall be conducted pursuant to the U.S. Department of Agriculture's Rules of Practice Governing Adjudicatory Proceedings, 7 CFR part 1, subpart H.

(b) Appealing the suspension or termination of a State or Tribal hemp production plan. A State or Tribe may appeal the revocation by USDA of an approved State or Tribal hemp production plan.

(1) If the AMS Administrator grants a State or Indian Tribe's appeal of a State or Tribal hemp production plan suspension or revocation, the associated hemp production plan will remain in place and effective.

(2) If the AMS Administrator denies an appeal, the State or Tribal hemp production plan will be suspended or revoked as applicable. Producers located in that State or territory of the Indian Tribe may continue to produce hemp under their State or Tribal license until the end the calendar year in which the State or Tribal plan's disapproval was effective or when the State or Tribal license expires, whichever is earlier. Producers may apply for a USDA license under subpart C of this part unless hemp production is otherwise prohibited by the State or Indian Tribe. The State or Indian Tribe may request a formal adjudicatory proceeding be initiated to review the decision. Such proceeding shall be conducted pursuant to the U.S. Department of Agriculture's Rules of Practice Governing Formal Adjudicatory Proceedings, 7 CFR part 1, subpart H.

(c) Filing period. The appeal of a State or Tribal hemp production plan suspension or revocation must be filed within the time-period provided in the letter of notification or within 30 business days from receipt of the notification, whichever occurs later. The appeal will be considered “filed” on the date received by the AMS Administrator. The decision to deny a State or Tribal plan application or suspend or revoke approval of a plan, is final unless the decision is appealed in a timely manner.

(d) Where to file. Appeals to the Administrator must be filed in the manner as determined by AMS.

(e) What to include in appeal. All appeals must include a copy of the adverse decision and a statement of the appellant's reasons supporting why the decision was not proper or made in accordance with applicable program regulations in this part, policies, or procedures.

authority: 7 U.S.C. 1639o note, 1639p, 1639q, 1639r
source: 86 FR 5680, Jan. 19, 2021, unless otherwise noted.
cite as: 7 CFR 990.42