§ 1970.101 - General.

(a) An EA is a concise public document used by the Agency to determine whether to issue a FONSI or prepare an EIS, as specified in subpart D of this part. If, at any point during the preparation of an EA, it is determined that the proposal will have a potentially significant impact on the quality of the human environment, an EIS will be prepared.

(b) Unless otherwise determined by the Agency, EAs will be prepared for all “Federal actions” as described in § 1970.8, unless such actions are categorically excluded, as determined under subpart B of this part, or require an EIS, as provided under subpart D of this part;

(c) Preparation of an EA will begin as soon as the Agency has determined the proper classification of the applicant's proposal. Applicants should consult as early as possible with the Agency to determine the environmental review requirements of their proposals. The EA must be prepared concurrently with the early planning and design phase of the proposal. The EA will not be considered complete until it is in compliance with this part.

(d) Failure to achieve compliance with this part will postpone further consideration of the applicant's proposal until such compliance is achieved or the applicant withdraws the application. If compliance is not achieved, the Agency will deny the request for financial assistance.

§ 1970.102 - Preparation of EAs.

The EA must focus on resources that might be affected and any environmental issues that are of public concern.

(a) The amount of information and level of analysis provided in the EA should be commensurate with the magnitude of the proposal's activities and its potential to affect the quality of the human environment. At a minimum, the EA must discuss the following:

(1) The purpose and need for the proposed action;

(2) The affected environment, including baseline conditions that may be impacted by the proposed action and alternatives;

(3) The environmental impacts of the proposed action including the No Action alternative, and, if a specific project element is likely to adversely affect a resource, at least one alternative to that project element;

(4) Any applicable environmental laws and Executive Orders;

(5) Any required coordination undertaken with any Federal, state, or local agencies or Indian tribes regarding compliance with applicable laws and Executive Orders;

(6) Mitigation measures considered, including those measures that must be adopted to ensure the action will not have significant impacts;

(7) Any documents incorporated by reference, if appropriate, including information provided by the applicant for the proposed action; and

(8) A listing of persons and agencies consulted.

(b) The following describes the normal processing of an EA under this subpart:

(1) The Agency advises the applicant of its responsibilities as described in subpart A of this part. These responsibilities include preparation of the EA as discussed in § 1970.5(b)(3)(iv)(B).

(2) The applicant provides a detailed project description including connected actions.

(3) The Agency verifies that the applicant's proposal should be the subject of an EA under § 1970.101. In addition, the Agency identifies any unique environmental requirements associated with the applicant's proposal.

(4) The Agency or the applicant, as appropriate, coordinates with Federal, state, and local agencies with jurisdiction by law or special expertise; tribes; and interested parties during EA preparation.

(5) Upon receipt of the EA from the applicant, the Agency evaluates the completeness and accuracy of the documentation. If necessary, the Agency will require the applicant to correct any deficiencies and resubmit the EA prior to its review.

(6) The Agency reviews the EA and supporting documentation to determine whether the environmental review is acceptable.

(i) If the Agency finds the EA unacceptable, the Agency will notify the applicant, as necessary, and work to resolve any outstanding issues.

(ii) If the Agency finds the EA acceptable, the Agency will prepare or review a “Notice of Availability of the EA” and direct the applicant to publish the notice in local newspapers or through other distribution methods as approved by the Agency. The notice must be published for three consecutive issues (including online) in a daily newspaper, or two consecutive weeks in a weekly newspaper. If other distribution methods are approved, the Agency will identify equivalent requirements. The public review and comment period will begin on the day of the first publication date or equivalent if other distribution methods are used. A 14- to 30-day public review and comment period, as determined by the Agency, will be provided for all Agency EAs.

(7) After reviewing and evaluating all public comments, the Agency determines whether to modify the EA, prepare a FONSI, or prepare an EIS that conforms with subpart D of this part.

(8) If the Agency determines that a FONSI is appropriate, and after preparation of the FONSI, the Agency will prepare or review a public notice announcing the availability of the FONSI and direct the applicant to publish the public notice in a newspaper(s) of general circulation, as described in § 1970.14(d)(2). In such case, the applicant must obtain an “affidavit of publication” or other such proof from all publications (or equivalent verification if other media were used) and must submit the affidavits and verifications to the Agency.

§ 1970.103 - Supplementing EAs.

If the applicant makes substantial changes to a proposal or if new relevant environmental information is brought to the attention of the Agency after the issuance of an EA or FONSI, supplementing an EA may be necessary before the action has been implemented. Depending on the nature of the changes, the EA will be supplemented by revising the applicable section(s) or by appending the information to address potential impacts not previously considered. If an EA is supplemented, public notification will be required in accordance with § 1970.102(b)(7) and (8).

§ 1970.104 - Finding of No Significant Impact.

The Agency may issue a FONSI or a revised FONSI only if the EA or supplemental EA supports the finding that the proposed action will not have a significant effect on the human environment. If the EA does not support a FONSI, the Agency will follow the requirements of subpart D of this part before taking action on the proposal.

(a) A FONSI must include:

(1) A summary of the supporting EA consisting of a brief description of the proposed action, the alternatives considered, and the proposal's impacts;

(2) A notation of any other EAs or EISs that are being or will be prepared and that are related to the EA;

(3) A brief discussion of why there would be no significant impacts;

(4) Any mitigation essential to finding that the impacts of the proposed action would not be significant;

(5) The date issued; and

(6) The signature of the appropriate Agency approval official.

(b) The Agency must ensure that the applicant has committed to any mitigation that is necessary to support a FONSI and possesses the authority and ability to fulfill those commitments. The Agency must ensure that mitigation, and, if appropriate, a mitigation plan that is necessary to support a FONSI, is made a condition of financial assistance.

(c) The Agency must make a FONSI available to the public as provided at 40 CFR 1501.4(e) and 1506.6.

(d) The Agency may revise a FONSI at any time provided that the revision is supported by an EA or a supplemental EA. A revised FONSI is subject to all provisions of this section.

§§ 1970.105-1970.150 - §[Reserved]
authority: 7 U.S.C. 6941
source: 81 FR 11032, Mar. 2, 2016, unless otherwise noted.
cite as: 7 CFR 1970.101