In addition to complying with applicable requirements of § 51.31(c), in a proceeding for the issuance of a manufacturing license, the presiding officer will determine whether, in accordance with the regulations in this subpart, the manufacturing license should be issued as proposed by the NRC's Director, Office of Nuclear Reactor Regulation.
[73 FR 5724, Jan. 31, 2008, as amended at 84 FR 65645, Nov. 29, 2019]
authority: Atomic Energy Act of 1954, secs. 161, 193 (
42 U.S.C. 2201,
2243; Energy Reorganization Act of 1974, secs. 201, 202 (
42 U.S.C. 5841,
5842; National Environmental Policy Act of 1969 (
42 U.S.C. 4332,
4334,
4335; Nuclear Waste Policy Act of 1982, secs. 144(f), 121, 135, 141, 148 (
42 U.S.C. 10134(f), 10141, 10155, 10161, 10168);
44 U.S.C. 3504 note
source: 49 FR 9381, Mar. 12, 1984, unless otherwise noted.
cite as: 10 CFR 51.105a