§ 503.7 - State approval—general requirement for new powerplants.

(a) Where approvals by the appropriate State regulatory authority are required prior to the construction or use of a new powerplant, a petition for an exemption for consideration by OFE may be submitted to OFE prior to obtaining such approvals from the State regulatory authority.

(b) An exemption granted for a powerplant shall not become effective until an adequate demonstration has been made to OFE that all applicable approvals required by the State regulatory authorities have been obtained.

authority: Department of Energy Organization Act, Pub. L. 95-91, 91 Stat. 565 (42 U.S.C. § 7101
source: 46 FR 59903, Dec. 7, 1981, unless otherwise noted.
cite as: 10 CFR 503.7