The provisions of this subpart apply to all Federal-aid projects within the right-of-way of a public highway, those projects required by law to be treated as if located on a Federal-aid highway, and other projects which are linked to such projects (i.e., the project would not exist without another Federal-aid highway project) that are to be delivered using the CM/GC contractor method.
authority: Sections 1525 and 1303 of Pub. L. 112-141, Sec. 1503 of Pub. L. 109-59, 119 Stat. 1144;
23 U.S.C. 101 (note), 109, 112, 113, 114, 116, 119, 128, and 315;
31 U.S.C. 6505;
42 U.S.C. 3334,
4601
cite as: 23 CFR 635.503