You should consider using two-phase selection procedures for all design-build projects. However, if you do not believe two-phase selection procedures are appropriate for your project (based on the criteria in § 636.202), you may use a single phase selection procedure or the modified-design-build contracting method. The following procedures are available:
Selection procedure
| Criteria for using a selection procedure
| Award criteria options
|
---|
(a) Two-Phase Selection Procedures (RFQ followed by RFP) | § 636.202 | Lowest price, Adjusted low-bid (price per quality point), meets criteria/low bid, weighted criteria process, fixed price/best design, best value.
|
(b) Single Phase (RFP) | Project not meeting the criteria in § 636.202 | All of the award criteria in item (a) of this table.
|
(c) Modified Design-Build (may be one or two phases) | Any project | Lowest price technically acceptable. |
authority: Sec. 1503 of Pub. L. 109-59, 119 Stat. 1144; Sec. 1307 of Pub. L. 105-178, 112 Stat. 107;
23 U.S.C. 101,
109,
112,
113,
114,
115,
119,
128,
and;
49 CFR 1.48(b)
source: 67 FR 75926, Dec. 10, 2002, unless otherwise noted.
cite as: 23 CFR 636.201