§ 661.37 - What are the funding limitations on an individual TTF bridge project?

The following funding provisions apply in administration of the TTFBP:

(a) There are no funding limitations on an individual TTF bridge application, but the PE estimated cost will be based on the following fee scale:

Estimated Construction Cost:

Up to $1,000,000—Use up to 20% for PE $1,000,000 to $5,000,000—Use up to 15%-20% for PE $5,000,000 to $10,000,000—Use up to 10%-15% for PE Over $10,000,000—Use up to 10% for PE

(b) Requests for additional funds for PE or construction may be submitted along with proper justification to FHWA for consideration. The request will be considered on a case-by-case basis. There is no guarantee for the approval of the request for additional funds.

authority: 23 U.S.C. 120(j) and (k), 202, and 315; 49 CFR 1.81, 1.84, 1.85; 23 CFR part 490, subpart D