§ 250.109 - What documents must I prepare and maintain related to welding?

(a) You must submit a Welding Plan to the District Manager before you begin drilling or production activities on a lease. You may not begin welding until the District Manager has approved your plan.

(b) You must keep the following at the site where welding occurs:

(1) A copy of the plan and its approval letter; and

(2) Drawings showing the designated safe-welding areas.

authority: 30 U.S.C. 1751,31.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334.
source: 76 FR 64462, Oct. 18, 2011, unless otherwise noted.