Regulations last checked for updates: Oct 17, 2024

Title 30 - Mineral Resources last revised: Oct 03, 2024
§ 250.195 - What notification does BSEE require on the production status of wells?

You must notify the appropriate BSEE District Manager when you successfully complete or recomplete a well for production. You must:

(a) Notify the District Manager within 5 working days of placing the well in a production status. You must confirm oral notification by telefax or e-mail within those 5 working days.

(b) Provide the following information in your notification:

(1) Lessee or operator name;

(2) Well number, lease number, and OCS area and block designations;

(3) Date you placed the well on production (indicate whether or not this is first production on the lease);

(4) Type of production; and

(5) Measured depth of the production interval.

authority: 30 U.S.C. 1751,31.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334.
source: 76 FR 64462, Oct. 18, 2011, unless otherwise noted.
cite as: 30 CFR 250.195