You must submit your request for a suspension to the Regional Supervisor, and BSEE must receive the request before the end of the lease term (i.e., end of primary term, end of the 1-year period following the last leaseholding operation, and end of a current suspension). Your request must include:
(a) The justification for the suspension including the length of suspension requested;
(b) A reasonable schedule of work leading to the commencement or restoration of the suspended activity;
(c) A statement that a well has been drilled on the lease and determined to be producible according to § 250.1603 (SOP only), 30 CFR 550.115, or 30 CFR 550.116;
(d) A commitment to production (SOP only); and
(e) The service fee listed in § 250.125 of this subpart.
[76 FR 64462, Oct. 18, 2011, as amended at 82 FR 26744, June 9, 2017]