Regulations last checked for updates: Nov 25, 2024

Title 30 - Mineral Resources last revised: Nov 19, 2024
§ 250.245 - May I combine the Project Conceptual Plan and the DWOP?

If your development project meets the following criteria, you may submit a combined Project Conceptual Plan/DWOP that complies with all applicable requirements for both, on or before the deadline for submitting the Project Conceptual Plan, as described in § 250.226:

(a) The project is similar to projects involving subsea tieback development technology for which you have obtained approval previously, and

(b) The project does not involve either new or unusual technology or a new platform.

authority: 30 U.S.C. 1751,31.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334.
source: 76 FR 64462, Oct. 18, 2011, unless otherwise noted.
cite as: 30 CFR 250.245