Regulations last checked for updates: Nov 25, 2024

Title 30 - Mineral Resources last revised: Nov 19, 2024
§ 250.1726 - When must I submit an initial platform removal application and what must it include?

An initial platform removal application is required only for leases and pipeline rights-of-way in the Pacific OCS Region or the Alaska OCS Region. It must include the following information:

(a) Platform or other facility removal procedures, including the types of vessels and equipment you will use;

(b) Facilities (including pipelines) you plan to remove or leave in place;

(c) Platform or other facility transportation and disposal plans;

(d) Plans to protect marine life and the environment during decommissioning operations, including a brief assessment of the environmental impacts of the operations, and procedures and mitigation measures that you will take to minimize the impacts; and

(e) A projected decommissioning schedule.

authority: 30 U.S.C. 1751,31.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334.
source: 76 FR 64462, Oct. 18, 2011, unless otherwise noted.
cite as: 30 CFR 250.1726