§ 250.1730 - When might BSEE approve partial structure removal or toppling in place?

The Regional Supervisor may grant a departure from the requirement to remove a platform or other facility by approving partial structure removal or toppling in place for conversion to an artificial reef if you meet the following conditions:

(a) The structure becomes part of a State artificial reef program, and the responsible State agency acquires a permit from the U.S. Army Corps of Engineers and accepts title and liability for the structure; and

(b) You satisfy any U.S. Coast Guard (USCG) navigational requirements for the structure.

authority: 30 U.S.C. 1751,31.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334.
source: 76 FR 64462, Oct. 18, 2011, unless otherwise noted.
cite as: 30 CFR 250.1730