§ 250.1740 - How must I verify that the site of a permanently plugged well, removed platform, or other removed facility is clear of obstructions?

Within 60 days after you permanently plug a well or remove a platform or other facility, you must verify that the site is clear of obstructions by using one of the following methods:

(a) For a well site, you must either:

(1) Drag a trawl over the site;

(2) Scan across the location using sonar equipment;

(3) Inspect the site using a diver;

(4) Videotape the site using a camera on a remotely operated vehicle (ROV); or

(5) Use another method approved by the District Manager if the particular site conditions warrant.

(b) For a platform or other facility site in water depths less than 300 feet, you must drag a trawl over the site.

(c) For a platform or other facility site in water depths 300 feet or more, you must either:

(1) Drag a trawl over the site;

(2) Scan across the site using sonar equipment; or

(3) Use another method approved by the Regional Supervisor if the particular site conditions warrant.

authority: 30 U.S.C. 1751,31.S.C. 9701, 33 U.S.C. 1321(j)(1)(C), 43 U.S.C. 1334.
source: 76 FR 64462, Oct. 18, 2011, unless otherwise noted.
cite as: 30 CFR 250.1740