(a) You must notify BSEE in writing within 30 days after completing installation activities approved in your GAP
(b) You must annually (or other frequency as determined by BOEM) submit a certification of compliance with those terms and conditions of your GAP that BOEM identifies under 30 CFR 585.648(e)(1). Together with your certification, you must submit:
(1) Summary reports that show compliance with the terms and conditions which require certification; and
(2) A statement identifying and describing any mitigation measures and monitoring methods and their effectiveness. If you identified measures that were not effective, you must include your recommendations for new mitigation measures or monitoring methods.