Regulations last checked for updates: Nov 23, 2024

Title 30 - Mineral Resources last revised: Nov 19, 2024
§ 285.705 - When must I use a Certified Verification Agent (CVA)?

(a) Unless BSEE waives this requirement under paragraph (c) of this section, you must use one or more CVAs to review and verify your FDRs, FIRs, and the Project Modification and Repair Reports.

(b) The purpose of a CVA is to:

(1) Ensure that your facilities are designed, fabricated, and installed in conformance with accepted engineering practices and the FDR(s) and FIR(s); and that the design of the facilities is suitable for the location where they will be installed;

(2) Ensure Critical Safety Systems and Equipment are commissioned in accordance with the procedures identified in § 285.702(a)(8);

(3) Ensure that major repairs and major modifications are completed in conformance with accepted engineering practices; and

(4) Provide BSEE and you with reports of all incidents that affect the facility design, fabrication, and installation, including commissioning of Critical Safety Systems and Equipment, for the project and its components.

(c) BSEE may waive in whole or in part the requirement that you use a CVA if you can demonstrate the following:

If you demonstrate that . . . Then BSEE may waive the requirement for a CVA for the following:
(1) The facility design conforms to a standard design that has been used successfully in a similar environment, and the installation design conforms to accepted engineering practicesThe design of your structure(s).
(2) The relevant fabricator has successfully fabricated similar facilities, and the facility will be fabricated in conformance with accepted engineering practices and to a nationally or internationally recognized quality assurance standardThe fabrication of your structure(s).
(3) The installation company has successfully installed similar facilities in a similar offshore environment, and your structures will be installed in conformance with accepted engineering practicesThe installation of your structure(s).
(4) Major repairs or major modifications will be completed in conformance with accepted engineering practices and to a nationally or internationally recognized quality assurance standardThe major repair or major modification on your structure(s).

(d) You must submit a request to waive, in whole or in part, the requirement to use a CVA to BSEE in writing.

(1) BSEE will review your request to waive, in whole or in part, the use of the CVA and notify you of its decision.

(2) If BSEE does not waive, in whole or in part, the requirement for a CVA, you may file an appeal under § 285.118.

(3) If BSEE waives, in whole or in part, the requirement that you use a CVA, your project engineer must perform the same duties and responsibilities as would have the CVA, except as otherwise provided. You must submit the project engineer's qualifications to BSEE as a part of your waiver request to demonstrate that your project engineer is a professional engineer with relevant experience and expertise in the facilities they will be verifying/certifying.

[89 FR 42717, May 15, 2024]
authority: 43 U.S.C. 1331
source: 88 FR 6413, Jan. 31, 2023, unless otherwise noted.
cite as: 30 CFR 285.705