Project information:
| Including:
|
---|
(1) Contact information | The name, address, email address, and phone number of an authorized representative.
|
(2) Designation of operator, if applicable | As provided in § 585.405.
|
(3) Your proposed construction, activities, and conceptual decommissioning plans, and/or technology testing concept | A discussion of the objectives; description of the proposed activities, including the technology you will use; and proposed schedule from start to completion.
|
(4) ROW or RUE grant, or limited lease stipulations, if known | A description of the measures you took, or will take, to satisfy the conditions of any grant or lease stipulations related to your proposed activities.
|
(5) A location plat, or indicative layout | The range of surface locations and associated water depths for proposed structures, facilities, and appurtenances located both offshore and onshore, including all anchor and mooring data; and the location and associated water depths of all existing structures.
|
(6) General structural and project design, fabrication, and installation | Preliminary design information for each facility associated with your project.
|
(7) Deployment activities | A description of the safety, prevention, and environmental protection features or measures that you will use.
|
(8) Your proposed measures for avoiding, minimizing, reducing, eliminating, and monitoring environmental impacts | A description of the measures you will use to avoid or minimize adverse effects and any potential incidental take before you conduct activities on your lease, and how you will mitigate environmental impacts from your proposed activities, including a description of the measures you will use as required by §§ 585.701 through 585.703.
|
(9) A list of solid and liquid wastes generated | Disposal methods and locations.
|
(10) A listing of chemical products used (if stored volume exceeds EPA reportable quantities) | A list of chemical products used; the volume stored on location; their treatment, discharge, or disposal methods used; and the name and location of the onshore waste receiving, treatment, and/or disposal facility. A description of how these products would be brought onsite, the number of transfers that may take place, and the quantity that will be transferred each time.
|
(11) A description of any vessels, vehicles, and aircraft you will use to support your activities | An estimate of the frequency and duration of vessel, vehicle, and aircraft traffic.
|
(12) Reference information | A bibliographic list of any document or published source that you cite as part of your plan. You may reference information and data discussed in other plans you previously submitted or that are otherwise readily available to BOEM.
|
(13) Decommissioning and site clearance procedures | A discussion of general concepts and methodologies.
|
(14) Air quality information | As described in § 585.700.
|
(15) A listing of all Federal, State, and local authorizations or approvals required to conduct activities on your grant or limited lease | A statement indicating whether you have applied for or obtained such authorization or approval from the U.S. Coast Guard, U.S. Army Corps of Engineers, and any other applicable Federal, State, or local authorizers pertaining to your activities.
|
(16) A list of agencies and persons with whom you have communicated, or with whom you will communicate, regarding potential impacts associated with your proposed activities | Contact information and issues discussed.
|
(17) Financial assurance information | Statements attesting that the activities and facilities proposed in your GAP are, or an explanation of how they will be, covered by an appropriate bond or other approved security, as required in §§ 585.520 and 585.521.
|
(18) Project verification strategy | You must describe your strategy for compliance with 30 CFR 285.705 through 285.714.
|
(19) Information you incorporate by reference | A list of the documents you have incorporated by reference and where they may be publicly accessed; for confidential information, you may reference information and data discussed in other plans previously submitted or that are otherwise readily available to BOEM.
|
(20) Other information | Additional information as required by BOEM. |