Regulations last checked for updates: Nov 22, 2024

Title 36 - Parks, Forests, and Public Property last revised: Nov 18, 2024
§ 51.57 - How does a concessioner request arbitration of the construction cost of a capital improvement?

If a concessioner requests arbitration of the construction cost of a capital improvement determined by the Director, the request must be made in writing to the Director within 3 months of the date of the Director's determination of construction cost under § 51.56. The arbitration procedures are described in § 51.51. The decision of the arbitration panel as to the construction cost of the capital improvement will be binding on the concessioner and the Director.

[66 FR 35083, July 3, 2001]
authority: 54 U.S.C. 101901-101926 and title IV of the National Parks Omnibus Management Act of 1998 (Pub. L. 105-391)
source: 65 FR 20668, Apr. 17, 2000, unless otherwise noted.
cite as: 36 CFR 51.57