Regulations last checked for updates: Nov 25, 2024

Title 43 - Public Lands: Interior last revised: Sep 06, 2024
§ 3922.10 - Application processing fee.

(a) An applicant nominating or applying for a tract for competitive leasing must pay a cost recovery or processing fee that the BLM will determine on a case-by-case basis as described in § 3000.11 of this chapter and as modified by the following provisions.

(b) The cost recovery process for a competitive oil shale lease is as follows:

(1) The applicant nominating the tract for competitive leasing must pay the fee before the BLM will process the application and publish a notice of competitive lease sale;

(2) The BLM will publish a sale notice no later than 30 days before the proposed sale. The BLM will include in the sale notice a statement of the total cost recovery fee paid to the BLM by the applicant, up to 30 calendar days before the sale;

(3) Before the lease is issued:

(i) The successful bidder, if someone other than the applicant, must pay to the BLM the cost recovery amount specified in the sale notice, including the cost of the NEPA analysis; and

(ii) The successful bidder must pay all processing costs the BLM incurs after the date of the sale notice;

(4) If the successful bidder is someone other than the applicant, the BLM will refund to the applicant the amount paid under paragraph (b)(1) of this section;

(5) If there is no successful bidder, the applicant is responsible for all processing fees; and

(6) If the successful bidder is someone other than the applicant, within 30 calendar days after the lease sale, the successful bidder must file an application in accordance with § 3922.20.

authority: 30 U.S.C. 241(a), 42 U.S.C. 15927,43.S.C. 1732(b) and 1740
source: 73 FR 69477, Nov. 18, 2008, unless otherwise noted.
cite as: 43 CFR 3922.10