§ 4300.23 - After I file my application, can I use the land before BLM issues my permit?

No. You cannot use the land until BLM issues you a permit. Generally, BLM will issue a permit within 120 days after receiving an application and will keep you informed if there are delays in meeting that timeframe.

authority: 25 U.S.C. 500k,and.S.C. 1701
source: 63 FR 55550, Oct. 16, 1998, unless otherwise noted.
cite as: 43 CFR 4300.23