Regulations last checked for updates: Oct 18, 2024

Title 46 - Shipping last revised: Oct 15, 2024
§ 52.20-17 - Opening between boiler and safety valve (modifies PFT-44).

Discharge pipes must be installed in accordance with the requirements of § 52.01-105.

[CGD 81-79, 50 FR 9434, Mar. 8, 1985]
authority: 46 U.S.C. 3306,3307,3703; E.O. 12234, 45 FR 58801, 3 CFR, 1980 Comp., p. 277; Department of Homeland Security Delegation No. 00170.1, Revision No. 01.3
source: CGFR 68-82, 33 FR 18815, Dec. 18, 1968, as amended by USCG-2020-0634, 89 FR 50095, June 12, 2024, unless otherwise noted.
cite as: 46 CFR 52.20-17