1832.111-70 - 1832.111-70 NASA contract clause.

The contracting officer shall insert the clause at 1852.232-79, Payment for On-Site Preparatory Costs, in solicitations and contracts for construction on a fixed-price basis when progress payments are contemplated and pro rata payment of on-site preparatory costs to the contractor is appropriate.

authority: 51 U.S.C. 20113(a) and 48 CFR chapter 1
source: 61 FR 55768, Oct. 29, 1996, unless otherwise noted.
cite as: 48 CFR 1832.111-70