Regulations last checked for updates: Oct 17, 2024

Title 48 - Federal Acquisition Regulations System last revised: Oct 10, 2024
207.171-1 - 207.171-1 Scope.

(a) This section provides policy for breaking out components of end items for future acquisitions so that the Government can purchase the components directly from the manufacturer or supplier and furnish them to the end item manufacturer as Government-furnished material.

(b) This section does not apply to—

(1) The initial decisions on Government-furnished equipment or contractor-furnished equipment that are made at the inception of an acquisition program; or

(2) Breakout of parts for replenishment (see appendix E).

[71 FR 14102, Mar. 21, 2006]
authority: 41 U.S.C. 1303 and 48 CFR chapter 1
source: 56 FR 36305, July 31, 1991, unless otherwise noted.
cite as: 48 CFR 207.171-1