Regulations last checked for updates: Nov 22, 2024

Title 48 - Federal Acquisition Regulations System last revised: Nov 15, 2024
422.302 - 422.302 Liquidated damages and overtime pay.

The Mission Area senior contracting official is authorized to review determinations of liquidated damages due under section 104(c) of the Contract Work Hours and Safety Standards Act, and to recommend remedial action, if appropriate, in accordance with FAR 22.302(c). Contractors or subcontractors may request review of administrative determinations of liquidated damages by written notice to the contracting officer. The contracting officer shall promptly forward appeals of liquidated damages determinations to the Mission Area senior contracting official.

authority: 5 U.S.C. 301 and 40 U.S.C. 486(c)
source: 89 FR 81015, Oct. 7, 2024, unless otherwise noted.
cite as: 48 CFR 422.302