(a) Pre-award costs. (1) PHMSA expects the recipient to be fully aware that pre-award costs result in borrowing against future support and that such borrowing must not impair the recipient's ability to accomplish the activities in the approved period of performance.
(2) A recipient may, at its own risk, incur pre-award costs to cover costs up to 90 days before the beginning date of the initial period of performance.
(3) The incurrence of pre-award costs in anticipation of a competitive or non-competitive grant imposes no obligation on PHMSA under any circumstances, including in the event of:
(i) The absence of appropriations;
(ii) A grant is not subsequently being made; or
(iii) A grant being made for a lesser amount than the recipient anticipated.
(b) Payments may not be made for activities not approved in the grant agreement. If a recipient seeks additional grant funds, the supplemental amendment request will be evaluated on the basis of needs, performance, and availability of grant funds. An existing grant is not a commitment of future funding.
[84 FR 4000, Feb. 14, 2019]