Regulations last checked for updates: Nov 25, 2024

Title 49 - Transportation last revised: Nov 18, 2024
§ 611.201 - New Starts eligibility.

(a) To be eligible for an engineering grant under this part for a new fixed guideway or an extension to a fixed guideway, a project must:

(1) Be a New Starts project as defined in § 611.105; and

(2) Be approved into engineering by FTA pursuant to § 611.209.

(b) To be eligible for a construction grant under section 5309 for a new fixed guideway or extension to a fixed guideway, a project must:

(1) Be a New Starts project as defined in § 611.105;

(2) Have completed engineering;

(3) Receive a “medium” or better rating on project justification pursuant to § 611.203;

(4) Receive a “medium” or better rating on local financial commitment pursuant to § 611.205;

(5) Meet the other requirements of 49 U.S.C. 5309.

authority: § 49 U.S.C. 5309(g)(6) and 5334(a)(11); 49 CFR 1.51
source: 78 FR 2031, Jan. 9, 2013, unless otherwise noted.
cite as: 49 CFR 611.201