(a) Protected species observer (PSO) and passive acoustic monitoring (PAM) operator qualifications. LOA Holder must implement the following measures applicable to PSOs and PAM operators:
(1) LOA Holder must use independent, NMFS-approved PSOs and PAM operators, meaning that the PSOs and PAM operators must be employed by a third-party observer provider, must have no tasks other than to conduct observational effort, collect data, and communicate with and instruct relevant crew with regard to the presence of protected species and mitigation requirements;
(2) All PSOs and PAM operators must have successfully attained a bachelor's degree from an accredited college or university with a major in one of the natural sciences, a minimum of 30 semester hours or equivalent in the biological sciences, and at least one undergraduate course in math or statistics. The educational requirements may be waived if the PSO or PAM operator has acquired the relevant skills through a suitable amount of alternate experience. Requests for such a waiver must be submitted to NMFS Office of Protected Resources and must include written justification containing alternative experience. Alternative experience that may be considered includes, but is not limited to: previous work experience conducting academic, commercial, or government-sponsored marine mammal visual and/or acoustic surveys; or previous work experience as a PSO/PAM operator. All PSOs and PAM operators should demonstrate good standing and consistently good performance of all assigned duties;
(3) PSOs must have visual acuity in both eyes (with correction of vision being permissible) sufficient enough to discern moving targets on the water's surface with the ability to estimate the target size and distance (binocular use is allowable); ability to conduct field observations and collect data according to the assigned protocols; sufficient training, orientation, or experience with the construction operation to provide for personal safety during observations; writing skills sufficient to document observations, including but not limited to, the number and species of marine mammals observed, the dates and times of when in-water construction activities were conducted, the dates and time when in-water construction activities were suspended to avoid potential incidental take of marine mammals from construction noise within a defined shutdown zone, and marine mammal behavior; and the ability to communicate orally, by radio, or in-person, with project personnel to provide real-time information on marine mammals observed in the area;
(4) All PSOs must be trained in northwestern Atlantic Ocean marine mammal identification and behaviors and must be able to conduct field observations and collect data according to assigned protocols. Additionally, PSOs must have the ability to work with all required and relevant software and equipment necessary during observations (as described in paragraphs (b)(4) and (5) of this section);
(5) All PSOs and PAM operators must successfully complete a relevant training course within the last 5 years, including obtaining a certificate of course completion;
(6) PSOs and PAM operators are responsible for obtaining NMFS' approval. NMFS may approve PSOs and PAM operators as conditional or unconditional. A conditionally-approved PSO or PAM operator may be one who has completed training in the last 5 years but has not yet attained the requisite field experience. An unconditionally approved PSO or PAM operator is one who has completed training within the last 5 years and attained the necessary experience (i.e., demonstrate experience with monitoring for marine mammals at clearance and shutdown zone sizes similar to those produced during the respective activity). Lead PSO or PAM operators must be unconditionally approved and have a minimum of 90 days in a northwestern Atlantic Ocean offshore environment performing the role (either visual or acoustic), with the conclusion of the most recent relevant experience not more than 18 months previous. A conditionally approved PSO or PAM operator must be paired with an unconditionally approved PSO or PAM operator;
(7) PSOs for cable landfall construction, marina activities, and HRG surveys may be unconditionally or conditionally approved. PSOs and PAM operators for foundation installation activities must be unconditionally approved;
(8) At least one on-duty PSO and PAM operator, where applicable, for each activity (e.g., impact pile driving, vibratory pile driving, and HRG surveys) must be designated as the Lead PSO or Lead PAM operator. The Lead PSO should be unconditionally approved for Tiers 1-3;
(9) LOA Holder must submit NMFS previously approved PSO and PAM operator resumes to NMFS Office of Protected Resources for review and confirmation of their approval for specific roles at least 30 days prior to commencement of the activities requiring PSOs/PAM operators or 15 days prior to when new PSOs/PAM operators are required after activities have commenced;
(10) For prospective PSOs and PAM operators not previously approved, or for PSOs and PAM operators whose approval is not current, LOA Holder must submit resumes for approval at least 60 days prior to PSO and PAM operator use. Resumes must include information related to relevant education, experience, and training, including dates, duration, location, and description of prior PSO or PAM operator experience. Resumes must be accompanied by relevant documentation of successful completion of necessary training and include which specific roles and activities the PSOs/PAM operators are being requested for. PAM operator experience must also include the information described in paragraph (a)(11) of this section;
(11) PAM operators are responsible for obtaining NMFS' approval. To be approved as a PAM operator, the person must meet the following qualifications: The PAM operator must demonstrate that they have prior large whale PAM experience with real-time acoustic detection systems and/or have completed specialized training for the PAM system(s) that will be used for the Project; PAM operators must demonstrate they are able to detect and identify Atlantic Ocean marine mammals sounds, in particular: North Atlantic right whale sounds, humpback whale sounds, and that they are able to deconflict humpback whale sounds from similar North Atlantic right whale sounds, and other co-occurring species' sounds in the area including sperm whales; must be able to distinguish between whether a marine mammal or other species sound is detected, possibly detected, or not detected; where localization of sounds or deriving bearings and distance are possible, the PAM operators need to have demonstrated experience in the localization of sounds or deriving bearings and distance; PAM operators must be independent observers (i.e., not construction personnel); PAM operators must demonstrate experience with relevant acoustic software and equipment; PAM operators must have the qualifications and relevant experience/training to safely deploy and retrieve equipment and program the software, as necessary; PAM operators must be able to test software and hardware functionality prior to operation; and PAM operators must have evaluated their acoustic detection software using the PAM Atlantic baleen whale annotated data set available at National Centers for Environmental Information (NCEI) and provide evaluation/performance metrics;
(12) PAM operators must be able to review and classify acoustic detections in near real-time prioritizing North Atlantic right whales and noting detection of other cetaceans) during the real-time monitoring periods; and
(13) PSOs may work as PAM operators and vice versa, pending NMFS-approval; however, they may only perform one role at any one time and must not exceed work time restrictions, which must be tallied cumulatively.
(b) General PSO and PAM operator requirements. The following measures apply to PSOs and PAM operators and must be implemented by LOA Holder:
(1) All PSOs must be located at the best vantage point(s) on any platform, as determined by the Lead PSO, in order to obtain 360-degree visual coverage of the entire clearance and shutdown zones around the activity area, and as much of the Level B harassment zone as possible. PAM operators may be located on a vessel or remotely on-shore. The PAM operator(s) must assist PSOs in ensuring full coverage of the clearance and shutdown zones. The PAM operator must monitor to and past the clearance zone for large whales;
(2) All on-duty PSOs must remain in real-time contact with the on-duty PAM operator(s), PAM operators must immediately communicate all acoustic detections of marine mammals to PSOs, including any determination regarding species identification, distance, and bearing (where relevant) relative to the pile being driven and the degree of confidence (e.g., detected, possibly detected, not detected) in the determination. All on-duty PSOs and PAM operator(s) must remain in real-time contact with the on-duty construction personnel responsible for implementing mitigations (e.g., delay to pile driving) to ensure communication on marine mammal observations can easily, quickly, and consistently occur between all on-duty PSOs, PAM operator(s), and on-water Project personnel;
(3) The PAM operator must inform the Lead PSO(s) on duty of animal detections approaching or within applicable ranges of interest to the activity occurring via the data collection software system (i.e., Mysticetus or similar system) who must be responsible for requesting that the designated crewmember implement the necessary mitigation procedures (i.e., delay);
(4) PSOs must use high magnification (25x) binoculars, standard handheld (7x) binoculars, and the naked eye to search continuously for marine mammals. During foundation installation, at least three PSOs on the pile driving and any dedicated PSO vessel that may be used must be equipped with functional Big Eye binoculars (e.g., 25 x 150; 2.7 view angle; individual ocular focus; height control). These must be pedestal mounted on the deck at the best vantage point that provides for optimal sea surface observation and PSO safety. A minimum of 3 PSOs must be active on a dedicated PSO vessel or an alternate monitoring technology (e.g., UAS) must be used that has been demonstrated as having greater visual monitoring capability compared to 3 PSOs on a dedicated PSO vessel and is approved by NMFS. PAM operators must have the appropriate equipment (i.e., a computer station equipped with a data collection software system available wherever they are stationed) and use a NMFS-approved PAM system to conduct monitoring. PAM systems are approved through the PAM Plan as described in § 217.284(c)(15);
(5) During periods of low visibility (e.g., darkness, rain, fog, poor weather conditions, etc.), PSOs must use alternative technology (i.e., infrared or thermal cameras) to monitor the clearance and shutdown zones as approved by NMFS;
(6) PSOs and PAM operators must not exceed 4 consecutive watch hours on duty at any time, must have a 2-hour (minimum) break between watches, and must not exceed a combined watch schedule of more than 12 hours in a 24-hour period;
(7) Any PSO has the authority to call for a delay or shutdown of project activities;
(8) Any visual observations of ESA-listed marine mammals must be communicated immediately to PSOs and vessel captains associated with other vessels to increase situational awareness; and
(9) LOA Holder personnel and PSOs are required to use available sources of information on North Atlantic right whale presence to aid in monitoring efforts. These include daily monitoring of the Right Whale Sightings Advisory System, consulting of the WhaleAlert app, and monitoring of the Coast Guard's VHF Channel 16 throughout the day to receive notifications of any sightings and information associated with any Dynamic Management Areas, to plan construction activities and vessel routes, if practicable, to minimize the potential for co-occurrence with North Atlantic right whales.
(c) PSO and PAM operator requirements during WTG and OSS foundation installation. The following measures apply to PSOs and PAM operators during WTG and OSS foundation installation and must be implemented by LOA Holder:
(1) PSOs and PAM operator(s), using a NMFS-approved PAM system, must monitor for marine mammals 60 minutes prior to, during, and 30 minutes following all pile-driving activities. If PSOs cannot visually monitor the minimum visibility zone prior to foundation pile driving at all times using the equipment described in paragraphs (b)(4) and (5) of this section, pile-driving operations must not commence or must shutdown if they are currently active. Foundation pile driving may only commence when the minimum visibility zone is fully visible (e.g., not obscured by darkness, rain, fog, etc.) and the clearance zones are clear of marine mammals for at least 30 minutes, as determined by the Lead PSO, immediately prior to the initiation of impact pile driving;
(2) At least three on-duty PSOs must be stationed on each vessel-based observer platform. If an aerial platform is used (per § 217.284(e)(7)), at least two on-duty PSOs must be actively searching for marine mammals. Concurrently, at least one PAM operator per acoustic data stream (i.e., equivalent to the number of acoustic buoys) must be actively monitoring for marine mammals 60 minutes before and during, and 30 minutes after impact pile driving in accordance with a NMFS-approved PAM Plan; and
(3) LOA Holder must conduct PAM for at least 24 hours immediately prior to pile driving activities. The PAM operator must review all detections from the previous 24-hour period immediately prior to pile driving activities.
(d) PSO requirements during cable landfall construction activities. The following measures apply to PSOs during cable landfall construction activities and must be implemented by LOA Holder:
(1) At least two PSOs must be on active duty during all activities related to cable landfall construction. These PSOs must be located at the best vantage points for observing marine mammals;
(2) PSOs must ensure that there is appropriate visual coverage for the entire clearance and shutdown zones and as much of the Level B harassment zone as possible; and
(3) PSOs must monitor the clearance zone for the presence of marine mammals for 30 minutes before and throughout pile driving, and for 30 minutes after all pile driving activities have ceased. Pile driving must only commence when visual clearance zones are fully visible (e.g., not obscured by darkness, rain, fog, etc.) and clear of marine mammals, as determined by the Lead PSO, for at least 30 minutes immediately prior to initiation of pile driving.
(e) PSO requirements during HRG surveys. The following measures apply to PSOs during HRG surveys using acoustic sources that have the potential to result in harassment (i.e., Compressed High Intensity Radiated Pulse (CHIRPs), boomers, and sparkers) and must be implemented by LOA Holder:
(1) At least one PSO must be on active duty monitoring during HRG surveys conducted during daylight (i.e., from 30 minutes prior to civil sunrise through 30 minutes following civil sunset) and at least two PSOs must be on active duty monitoring during HRG surveys conducted at night;
(2) PSOs on HRG vessels must begin monitoring 30 minutes prior to activating acoustic sources, during the use of these acoustic sources, and for 30 minutes after use of these acoustic sources has ceased;
(3) Any observations of marine mammals must be communicated to PSOs on all nearby survey vessels during concurrent HRG surveys; and
(4) During daylight hours when survey equipment is not operating, LOA Holder must ensure that visual PSOs conduct, as rotation schedules allow, observations for comparison of sighting rates and behavior with and without use of the specified acoustic sources. Off-effort PSO monitoring must be reflected in the monthly PSO monitoring reports.
(f) Reporting. LOA Holder must comply with the following reporting measures:
(1) Prior to initiation of any on-water project activities, LOA Holder must demonstrate in a report submitted to NMFS Office of Protected Resources that all required training for LOA Holder personnel (including the vessel crews, vessel captains, PSOs, and PAM operators) has been completed;
(2) LOA Holder must use a standardized reporting system during the effective period of the LOA. All data collected related to the Project must be recorded using industry-standard software that is installed on field laptops and/or tablets. Unless stated otherwise, all reports must be submitted to NMFS Office of Protected Resources ([email protected]), dates must be in MM/DD/YYYY format, and location information must be provided in Decimal Degrees and with the coordinate system information (e.g., NAD83, WGS84, etc.);
(3) For all visual monitoring efforts and marine mammal sightings, the following information must be collected and reported to NMFS Office of Protected Resources: the date and time that monitored activity begins or ends; the construction activities occurring during each observation period; the watch status (i.e., sighting made by PSO on/off effort, opportunistic, crew, alternate vessel/platform); the PSO who sighted the animal; the time of sighting; the weather parameters (e.g., wind speed, percent cloud cover, visibility); the water conditions (e.g., Beaufort sea state, tide state, water depth); all marine mammal sightings, regardless of distance from the construction activity; species (or lowest possible taxonomic level possible); the pace of the animal(s); the estimated number of animals (minimum/maximum/high/low/best); the estimated number of animals by cohort (e.g., adults, yearlings, juveniles, calves, group composition, etc.); the description (i.e., as many distinguishing features as possible of each individual seen, including length, shape, color, pattern, scars or markings, shape and size of dorsal fin, shape of head, and blow characteristics); the description of any marine mammal behavioral observations (e.g., observed behaviors such as feeding or traveling) and observed changes in behavior, including an assessment of behavioral responses thought to have resulted from the specific activity; the animal's closest distance and bearing from the pile being driven or specified HRG equipment and estimated time entered or spent within the Level A harassment and/or Level B harassment zone(s); the activity at time of sighting (e.g., vibratory installation/removal, impact pile driving, construction survey), use of any noise attenuation device(s), and the specific phase of the activity (e.g., ramp-up of HRG equipment, HRG acoustic source on/off, soft-start for pile driving, active pile driving, etc.); the marine mammal occurrence in Level A harassment or Level B harassment zones; the description of any mitigation-related action implemented, or mitigation-related actions called for but not implemented, in response to the sighting (e.g., delay, shutdown, etc.) and time and location of the action; other human activity in the area, and; other applicable information, as required in any LOA issued under § 217.286;
(4) If a marine mammal is acoustically detected during PAM monitoring, the following information must be recorded and reported to NMFS: location of hydrophone (i.e., latitude longitude; in Decimal Degrees) and site name; bottom depth and depth of recording unit (in meters); recorder (model manufacturer) and platform type (i.e., bottom-mounted, electric glider, etc.), and instrument ID of the hydrophone and recording platform (if applicable); time zone for sound files and recorded date/times in data and metadata (in relation to UTC. i.e., EST time zone is UTC-5); duration of recordings (i.e., start/end dates and times; in ISO 8601 format, yyyy-mm-ddTHH:MM:SS.sssZ); deployment/retrieval dates and times (in ISO 8601 format); recording schedule (must be continuous); hydrophone and recorder sensitivity (in dB re. 1µ Pa); calibration curve for each recorder; bandwidth/sampling rate (in Hz); sample bit-rate of recordings; and detection range of equipment for relevant frequency bands (in meters). The following information must be reported for each detection: species identification (if possible); call type and number of calls (if known); temporal aspects of vocalization (e.g., date, time, duration, etc.; date times in ISO 8601 format); confidence of detection (i.e., detected, or possibly detected); comparison with any concurrent visual sightings, location and/or directionality of call (if determined) relative to acoustic recorder or construction activities; location of recorder and construction activities at time of call; name and version of detection or sound analysis software used, with protocol reference; minimum and maximum frequencies viewed/monitored/used in detection (in Hz); and the name(s) of PAM operator(s) on duty;
(i) For each detection, the following information the following information must be noted: species identification (if possible); call type and number of calls (if known); temporal aspects of vocalization (e.g., date, time, duration, etc.; date times in ISO 8601 format); confidence of detection (i.e., detected, or possibly detected); comparison with any concurrent visual sightings; location and/or directionality of call (if determined) relative to acoustic recorder or construction activities; location of recorder and construction activities at time of call; name and version of detection or sound analysis software used, with protocol reference; minimum and maximum frequencies viewed/monitored/used in detection (in Hz); and the name(s) of PAM operator(s) on duty;
(ii) [Reserved]
(5) LOA Holder must compile and submit weekly reports during foundation installation to NMFS Office of Protected Resources that document the daily start and stop of all pile driving associated with the Project; the start and stop of associated observation periods by PSOs; details on the deployment of PSOs; a record of all acoustic and visual detections of marine mammals; any mitigation actions (or if mitigation actions could not be taken, provide reasons why); and details on the noise attenuation system(s) used and its performance. Weekly reports are due on Wednesday for the previous week (Sunday to Saturday) and must include the information required under this section. The weekly report must also identify which turbines become operational and when (a map must be provided). Once all foundation pile installation is completed, weekly reports are no longer required by LOA Holder;
(6) LOA Holder must compile and submit monthly reports to NMFS Office of Protected Resources during foundation installation that include a summary of all information in the weekly reports, including project activities carried out in the previous month, vessel transits (number, type of vessel, MMIS number, and route), number of piles installed, all detections of marine mammals, and any mitigative action taken. Monthly reports are due on the 15th of the month for the previous month. The monthly report must also identify which turbines become operational and when (a map must be provided). Full PAM detection data and metadata must also be submitted monthly on the 15th of every month for the previous month via the webform on the NMFS North Atlantic Right Whale Passive Acoustic Reporting System website at https://www.fisheries.noaa.gov/resource/document/passive-acoustic-reporting-system-templates;
(7) LOA Holder must submit a draft annual report to NMFS Office of Protected Resources no later than 90 days following the end of a given calendar year. LOA Holder must provide a final report within 30 days following resolution of NMFS' comments on the draft report. The draft and final reports must detail the following: the total number of marine mammals of each species/stock detected and how many were within the designated Level A harassment and Level B harassment zone(s) with comparison to authorized take of marine mammals for the associated activity type; marine mammal detections and behavioral observations before, during, and after each activity; what mitigation measures were implemented (e.g., number of shutdowns or clearance zone delays, etc.) or, if no mitigative actions was taken, why none were taken; operational details (e.g., days and duration of impact and vibratory pile driving, days and amount of HRG survey effort, etc.); any PAM systems used; the results, effectiveness, and which noise attenuation systems were used during relevant activities (i.e., impact pile driving); summarized information related to situational reporting; and any other important information relevant to the Project, including additional information that may be identified through the adaptive management process. The final annual report must be prepared and submitted within 30 calendar days following the receipt of any comments from NMFS on the draft report. If no comments are received from NMFS within 60 calendar days of NMFS' receipt of the draft report, the report must be considered final;
(8) LOA Holder must submit its draft 5-year report to NMFS Office of Protected Resources on all visual and acoustic monitoring conducted within 90 calendar days of the completion of activities occurring under the LOA. A 5-year report must be prepared and submitted within 30 calendar days following receipt of any NMFS Office of Protected Resources comments on the draft report. If no comments are received from NMFS Office of Protected Resources within 30 calendar days of NMFS Office of Protected Resources receipt of the draft report, the report shall be considered final;
(9) For those foundation piles requiring thorough SFV measurements, LOA Holder must provide the initial results of the SFV measurements to NMFS Office of Protected Resources in an interim report after each foundation installation event as soon as they are available and prior to a subsequent foundation installation, but no later than 48 hours after each completed foundation installation event. The report must include, at minimum: hammer energies/schedule used during pile driving, including the total number of strikes and the maximum hammer energy; the model-estimated acoustic ranges (R95percent) to compare with the real-world sound field measurements; peak sound pressure level (SPLpk), root-mean-square sound pressure level that contains 90 percent of the acoustic energy (SPLrms), and sound exposure level (SEL, in single strike for pile driving, SELss,), for each hydrophone, including at least the maximum, arithmetic mean, minimum, median (L50), and L5 (95 percent exceedance) statistics for each metric; estimated marine mammal Level A harassment and Level B harassment acoustic isopleths, calculated using the maximum-over-depth L5 (95 percent exceedance level, maximum of both hydrophones) of the associated sound metric; comparison of modeled results assuming 10-dB attenuation against the measured marine mammal Level A harassment and Level B harassment acoustic isopleths; estimated transmission loss coefficients; pile identifier name, location of the pile, and each hydrophone array in latitude/longitude; depths of each hydrophone; one-third-octave band single strike SEL spectra; if filtering is applied, full filter characteristics must be reported; and hydrophone specifications including the type, model, and sensitivity. LOA Holder must also report any immediate observations which are suspected to have a significant impact on the results including but not limited to: observed noise mitigation system issues; obstructions along the measurement transect; and technical issues with hydrophones or recording devices. If any in-situ calibration checks for hydrophones reveal a calibration drift greater than 0.75 dB, pistonphone calibration checks are inconclusive, or calibration checks are otherwise not effectively performed, LOA Holder must indicate full details of the calibration procedure, results, and any associated issues in the 48-hour interim reports;
(10) LOA Holder must conduct abbreviated SFV for all foundation installations for which the complete SFV monitoring is not carried out (refer back to § 217.284(c)(13)), whereas a single acoustic recorder must be placed at an appropriate distance from the pile, in alignment with the completed Biological Opinion. All results must be included in the weekly reports. Any indications that distances to the identified Level A harassment and Level B harassment thresholds for marine mammals were exceeded must be addressed by LOA Holder, including an explanation of factors that contributed to the exceedance and corrective actions that were taken to avoid exceedance on subsequent piles;
(11) The final results of SFV measurements from each foundation installation must be submitted as soon as possible, but no later than 90 days following completion of each event's SFV measurements. The final reports must include all details prescribed above for the interim report as well as, at minimum, the following: the peak sound pressure level (SPLpk); the root-mean-square sound pressure level that contains 90 percent of the acoustic energy (SPLrms); the single strike sound exposure level (SELss); the integration time for SPLrms; the spectrum; and the 24-hour cumulative SEL extrapolated from measurements at all hydrophones. The final report must also include at least the following: the maximum, mean, minimum, median (L50), and L5 (95 percent exceedance) statistics for each metric; the SEL and SPL power spectral density and/or one-third octave band levels (usually calculated as decidecade band levels) at the receiver locations; the sound levels reported must be in median, arithmetic mean, and L5 (95 percent exceedance) (i.e., average in linear space), and in dB; range of TL coefficients; the local environmental conditions, such as wind speed, transmission loss data collected on-site (or the sound velocity profile); baseline pre- and post-activity ambient sound levels (broadband and/or within frequencies of concern); a description of depth and sediment type, as documented in the Construction and Operation Plan (COP), at the recording and foundation installation locations; the extents of the measured Level A harassment and Level B harassment zone(s); hammer energies required for pile installation and the number of strikes per pile; the hydrophone equipment and methods (i.e., recording device, bandwidth/sampling rate; distance from the pile where recordings were made; the depth of recording device(s)); a description of the SFV measurement hardware and software, including software version used, calibration data, bandwidth capability and sensitivity of hydrophone(s), any filters used in hardware or software, any limitations with the equipment, and other relevant information; the spatial configuration of the noise attenuation device(s) relative to the pile; a description of the noise abatement system and operational parameters (e.g., bubble flow rate, distance deployed from the pile, etc.), and any action taken to adjust the noise abatement system. A discussion, which includes any observations which are suspected to have a significant impact on the results including but not limited to, observed noise mitigation system issues, obstructions along the measurement transect, and technical issues with hydrophones or recording devices, must also be included in the final SFV report;
(12) If at any time during the Project LOA Holder becomes aware of any issue or issues which may (to any reasonable subject-matter expert, including the persons performing the measurements and analysis) call into question the validity of any measured Level A harassment or Level B harassment isopleths to a significant degree, which were previously transmitted or communicated to NMFS Office of Protected Resources, LOA Holder must inform NMFS Office of Protected Resources within 1 business day of becoming aware of this issue or before the next pile is driven, whichever comes first;
(13) If a North Atlantic right whale is acoustically detected at any time by a project-related PAM system, LOA Holder must ensure the detection is reported as soon as possible to NMFS, but no longer than 24 hours after the detection via the 24-hour North Atlantic right whale Detection Template (https://www.fisheries.noaa.gov/resource/document/passive-acoustic-reporting-system-templates). Calling the hotline is not necessary when reporting PAM detections via the template;
(14) Full detection data, metadata, and location of recorders (or GPS tracks, if applicable) from all real-time hydrophones used for monitoring during construction must be submitted within 90 calendar days following completion of activities requiring PAM for mitigation via the ISO standard metadata forms available on the NMFS Passive Acoustic Reporting System website (https://www.fisheries.noaa.gov/resource/document/passive-acoustic-reporting-system-templates). Submit the completed data templates to [email protected]. The full acoustic recordings from real-time systems must also be sent to the National Centers for Environmental Information (NCEI) for archiving within 90 days following completion of activities requiring PAM for mitigation. Submission details can be found at: https://www.ncei.noaa.gov/products/passive-acoustic-data;
(15) LOA Holder must submit situational reports if the following circumstances occur (including all instances wherein an exemption is taken must be reported to NMFS Office of Protected Resources within 24 hours):
(i) If a North Atlantic right whale is observed at any time by PSOs or project personnel, LOA Holder must ensure the sighting is immediately (if not feasible, as soon as possible and no longer than 24 hours after the sighting) reported to NMFS and the Right Whale Sightings Advisory System (RWSAS). If in the Northeast Region (Maine to Virginia/North Carolina border) call (866-755-6622). If in the Southeast Region (North Carolina to Florida) call (877-WHALE-HELP or 877-942-5343). If calling NMFS is not possible, reports can also be made to the U.S. Coast Guard via channel 16 or through the WhaleAlert app (https://www.whalealert.org/). The sighting report must include the time, date, and location of the sighting, number of whales, animal description/certainty of sighting (provide photos/video if taken), Lease Area/project name, PSO/personnel name, PSO provider company (if applicable), and reporter's contact information;
(ii) If a North Atlantic right whale is observed at any time by PSOs or project personnel, LOA Holder must submit a summary report to NMFS Greater Atlantic Regional Fisheries (GARFO; [email protected]), NMFS Office of Protected Resources, and NMFS Northeast Fisheries Science Center (NEFSC; [email protected]) within 24 hours with the above information and the vessel/platform from which the sighting was made, activity the vessel/platform was engaged in at time of sighting, project construction and/or survey activity at the time of the sighting (e.g., pile driving, cable installation, HRG survey), distance from vessel/platform to sighting at time of detection, and any mitigation actions taken in response to the sighting;
(iii) If a large whale (not including a North Atlantic right whale) is observed at any time by PSOs or project personnel during vessel transit, LOA Holder must report the sighting to the WhaleAlert app (https://www.whalealert.org/);
(iv) In the event that personnel involved in the Project discover a stranded, entangled, injured, or dead marine mammal, LOA Holder must immediately report the observation to NMFS. If in the Greater Atlantic Region (Maine to Virginia) call the NMFS Greater Atlantic Stranding Hotline (866-755-6622); if in the Southeast Region (North Carolina to Florida), call the NMFS Southeast Stranding Hotline (877-942-5343). Separately, LOA Holder must report the incident to NMFS Office of Protected Resources ([email protected]) and, if in the Greater Atlantic region (Maine to Virginia), NMFS Greater Atlantic Regional Fisheries Office (GARFO; [email protected], [email protected]) or, if in the Southeast region (North Carolina to Florida), NMFS Southeast Regional Office (SERO; [email protected]), as soon as feasible. The report (via phone or email) must include contact information (e.g., name, phone number, etc.), the time, date, and location of the first discovery (and updated location information if known and applicable); species identification (if known) or description of the animal(s) involved; condition of the animal(s) (including carcass condition if the animal is dead); observed behaviors of the animal(s), if alive; photographs or video footage of the animal(s) if available; and general circumstances under which the animal was discovered; and
(v) In the event of a vessel strike of a marine mammal by any vessel associated with the Project or if the Project activities cause a non-auditory injury or death of a marine mammal, LOA Holder must immediately report the incident to NMFS. If in the Greater Atlantic Region (Maine to Virginia) call the NMFS Greater Atlantic Stranding Hotline (866-755-6622) and if in the Southeast Region (North Carolina to Florida) call the NMFS Southeast Stranding Hotline (877-942-5343). Separately, LOA Holder must immediately report the incident to NMFS Office of Protected Resources ([email protected]) and, if in the Greater Atlantic region (Maine to Virginia), NMFS GARFO ([email protected], [email protected]) or, if in the Southeast region (North Carolina to Florida), NMFS SERO ([email protected]). The report must include: the time, date, and location of the incident; species identification (if known) or description of the animal(s) involved; vessel size and motor configuration (e.g., inboard, outboard, jet propulsion); vessel's speed leading up to and during the incident; vessel's course/heading and what operations were being conducted (if applicable); status of all sound sources in use; description of avoidance measures/requirements that were in place at the time of the strike and what additional measures were taken, if any, to avoid strike; environmental conditions (e.g., wind speed and direction, Beaufort sea state, cloud cover, visibility) immediately preceding the strike; estimated size and length of animal that was struck; description of the behavior of the marine mammal immediately preceding and following the strike; if available, description of the presence and behavior of any other marine mammals immediately preceding the strike; estimated fate of the animal (e.g., dead, injured but alive, injured and moving, blood or tissue observed in the water, status unknown, disappeared); and, to the extent practicable, photographs or video footage of the animal(s). LOA Holder must immediately cease all on-water activities until the NMFS Office of Protected Resources is able to review the circumstances of the incident and determine what, if any, additional measures are appropriate to ensure compliance with the terms of the LOA. NMFS Office of Protected Resources may impose additional measures to minimize the likelihood of further prohibited take and ensure MMPA compliance. LOA Holder may not resume their activities until notified by NMFS Office of Protected Resources; and
(16) LOA Holder must report any lost gear associated with the fishery surveys to the NMFS GARFO Protected Resources Division ([email protected]) as soon as possible or within 24 hours of the documented time of missing or lost gear. This report must include information on any markings on the gear and any efforts undertaken or planned to recover the gear.