(a) Regulations in this subpart apply to activities associated with the Coastal Virginia Offshore Wind Commercial Project (hereafter referred to as the “Project”) by the Virginia Electric and Power Company, doing business as Dominion Energy Virginia (hereafter referred to as “LOA Holder”), and those persons it authorizes or funds to conduct activities on its behalf in the area outlined in paragraph (b) of this section. Requirements imposed on the LOA Holder must be implemented by those persons it authorizes or funds to conduct activities on its behalf.
(b) The specified geographical region is the Mid-Atlantic Bight, which includes, but is not limited to, the Bureau of Ocean Energy Management (BOEM) Lease Area Outer Continental Shelf (OCS)-A 0483 Commercial Lease of Submerged Lands for Renewable Energy Development, one export cable route, and one sea-to-shore transition point located at the State Military Reservation in Virginia Beach, Virginia.
(c) The specified activities are vibratory and impact pile driving of wind turbine generator (WTGs) and offshore substation (OSSs) foundations; vibratory pile driving (install and subsequently removal) of cofferdams; impact pile driving (install and subsequently removal) of goal posts; fishery and ecological monitoring surveys; placement of scour protection; trenching, laying, and burial activities associated with the installation of the export cable from OSSs to shore-based converter stations and inter-array cables between turbines; high-resolution geophysical (HRG) site characterization surveys; vessel transit within the specified geographical region to transport crew, supplies, and materials; and WTG operation.