(a) The plan for O&M shall be incorporated into and made a part of the O&M agreement. A separate plan of O&M shall be prepared for each project measure that is expected to a have a unique O&M need. Two or more measures with similar O&M needs may be included in a single plan for O&M.
(b) The plan of O&M shall include the known and anticipated items of O&M, an explanation of how the O&M activities may be carried out, a general time frame for making O&M inspections and for completing the needed O&M work, and the records and reports deemed appropriate by the sponsor(s) and NRCS.
authority: Pub. L. 83-566, 68 Stat. 666, as amended (
16 U.S.C. 1001-1008). Sec. 1, Pub. L. 86-468, 74 Stat. 131, as amended (
16 U.S.C. 1006a); sec. 2, Pub. L. 78-534, 58 Stat. 889 (
33 U.S.C. 701a-1); sec. 13, Pub. L. 78-534, 58 Stat. 905; sec. 5, Pub. L. 93-251, 88 Stat. 15; Pub. L. 87-703, 76 Stat. 607 (
7 U.S.C. 1010-1011); Pub. L. 74-46, 49 Stat. 163 (
16 U.S.C. 590a-f,
q; Pub. L. 84-1021, 70 Stat. 1115, as amended (
16 U.S.C. 590p(b)); sec. 216, Pub. L. 81-516, 64 Stat. 184 (
33 U.S.C. 701b-1);
7 CFR 2.62
source: 42 FR 58159, Nov. 8, 1977, unless otherwise noted.
cite as: 7 CFR 654.19