Regulations last checked for updates: Oct 20, 2024

Title 7 - Agriculture last revised: Oct 11, 2024
§ 1726.22 - Methods of construction.

The borrower is generally responsible for determining whether construction will be by contract or force account. If construction is by contract, the borrower must determine whether materials will be supplied by the contractor or will be furnished by the borrower. RUS reserves the right to require contract construction in lieu of force account construction on a case by case basis.

authority: 7 U.S.C. 901
source: 60 FR 10155, Feb. 23, 1995, unless otherwise noted.
cite as: 7 CFR 1726.22